It's a world record! Largest uninterrupted concrete pour kicks off Wilshire Grand project

It's a world record! Largest uninterrupted concrete pour kicks off Wilshire Grand project

Guinness World Records verifies the concrete pour as the largest ever


By BD+C Staff | February 19, 2014

After about 20 hours of continuous pouring, judges from Guinness World Records verified that the concrete pour at the $1 billion Wilshire Grand project in Los Angeles is the largest uninterrupted pour of slurry on record.  

It took 208 trucks making as many as 10 deliveries each last weekend to complete the pour. In all, 21,000 cubic yards of concrete were poured to form the foundation for the 73-story tower. 

The project, led by Turner Construction for developer Korean Air, includes office space, restaurants, retail, and 900 luxury hotel rooms. Scheduled to open in 2016, the tower will be the tallest building west of Chicago. AC Martin Partners is designing the 1,100-foot-tall tower, with Thornton Tomasetti as structural engineer.

Here are some of the pour’s impressive numbers:
• 19 pumps dispensed concrete into the pit through 13 hoses
• 24 temperature sensors provided hourly readings (the concrete should remain between 120 and 160 degrees)
• 45 degree water pumped through 100,000 feet of polyethylene hose snaked throughout the pit will help counteract the natural heating
• The concrete weighs some 82 million pounds


12:00 noon PST February 15, 2014

12:00 midnight PST February 15, 2014


12:00 noon PST February 15, 2014

Related Stories

| Oct 17, 2011

Aerialogics announces technology partnership with CertainTeed Corp.

  CertainTeed to provide Aerialogics’ Aerial Measurement Services to its credentialed contractor base and utilize the technology in its Roofing Products Division.

| Oct 17, 2011

Big D Floor covering supplies to offer Johnsonite Products??

Strategic partnership expands offering to south and west coast customers. 

| Oct 17, 2011

Clery Act report reveals community colleges lacking integrated mass notification systems

  “Detailed Analysis of U.S. College and University Annual Clery Act Reports” study now available. 

| Oct 17, 2011

USGBC L.A. Chapter's Green Gala to feature Jason McLennan as keynote speaker

  Chapter to presents inaugural Sustainable Innovation Awards,

| Oct 17, 2011

Schneider Electric introduces UL924 emergency lighting control devices

The emergency lighting control devices require fewer maintenance costs and testing requirements than backup batteries because they comply with the UL924 standard, reducing installation time. 

| Oct 14, 2011

AISC develops new interoperability strategy to move construction industry forward

AISC is working to bring that vision to reality by developing a three-step interoperability strategy to evaluate data exchanges and integrate structural steel information into buildingSMART's Industry Foundation Classes.

| Oct 14, 2011

University of New Mexico Science & Math Learning Center attains LEED for Schools Gold

Van H. Gilbert architects enhances sustainability credentials.

| Oct 14, 2011

BD+C Survey on Building Information Modeling: The Good, the Bad, and the Solutions

In a recent survey conducted by Building Design+Construction, more than 75% of respondents indicated they currently use BIM or plan to use it. Respondents were also asked to comment on their experiences with BIM, what they liked and disliked about BIM, and what BIM-related advice they would give to their peers. 

| Oct 14, 2011

ACI partners with CRSI to launch new adhesive anchor certification program

Adhesive anchor installer certification required in new ACI 318-11.

| Oct 14, 2011

Midwest construction firms merge as Black and Dew

  Merger is aimed at increasing market sector capabilities and building on communication and core contracting competencies.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021