L.A.’s John Anson Ford Amphitheater might finally be ready for its close-up

Performing Arts Centers

L.A.’s John Anson Ford Amphitheater might finally be ready for its close-up

The performing arts venue, nearly a century old, has undergone an extensive refurbishing.


By John Caulfield, Senior Editor | June 30, 2017

The 1,200-seat John Anson Ford Amphitheater will reopen next month after a nearly four-year, $72.2 million renovation and expansion. Image: Gennia Cui

On July 14, Los Angeles County will conduct a dedication and open house for its 1,200-seat John Anson Ford Theater, the 97-year-old outdoor performance center nestled in the Hollywood Hills that has received a $72.2 million facelift, which took more than four years to complete.

Two of the three construction phases for this project were completed a year ago, including the restoration of the Ford Amphitheater stage with a Brazilian walnut Ipe hardwood deck. The theater is adjacent to a 32-acre park, whose hillside sloping was stabilized with retaining walls and other erosion-control measures.

Artist support spaces have been expanded, and new theatrical and AV infrastructure was installed, including the creation of a sound wall that encompasses a projection booth and control room, catwalks, and an upgraded lighting platform. A sound barrier will help muffle vehicular noise coming from the nearby Highway 101.

 

The outdoor theater is located in the hills of Cahuenga Pass, surrounded by a 32-acre park whose landscaping was stabilized and upgraded as part of the renovation. Image: Tom Bonner

 

In addition, a new three-story structure with a full-service loading dock below and offices above was constructed. An 87-seat black box theater, [Inside] the Ford, was repurposed as a 580-sf self-serve food marketplace and community room. All told the renovation and restoration added 3,500 sf of “found space” from bedrock under the stage, and a 2,315-sq picnic terrace that can seat up to 110. (Crumble Catering is the marketplace partner.)

The John Anson Ford Amphitheater has always been a less-conspicuous, littler cousin to the more-famous, 17,500-seat Hollywood Bowl.

Among the refurbishings of John Anson Ford Amphitheater is the installation of a new Ipe hardware deck for the stage. Image: Tom Bonner

Opened in 1920, the amphitheater was designed, somewhat bizarrely, to resemble the gates of ancient Jerusalem. Christine Wetherill Stevenson, heiress to the Pittsburgh Paint fortune and a playwright, was instrumental in securing the land and building for the original theater, which staged her drama “The Pilgrimage Play.”

In 1976, the theater was renamed in honor of John Anson Ford, and L.A. County supervisor who founded the L.A. County Arts Commission. (The county owns the theater.)

The Building Team for the renovation and restoration included Levin & Associates Architects (design architect), Pankow Builders (construction services), Cumming Construction Management (project manager), Structural Focus (SE), Lucci & Associates (EE), The Sullivan Partnership (M/P engineer), Mollenhauer Group (CE, Survey), McKay Conant Hoover (acoustical and AV engineer), Wiss Janney Elstner Associates (material conservation), Mia Lehrer + Associates (landscape architect), Horton Lees Brogden (lighting design), Leighton (geotechnical), Sussman Prejza & Company (signage), and Theatre Projects (theatrical).

 

Related Stories

| Jul 19, 2013

Reconstruction Sector Construction Firms [2013 Giants 300 Report]

Structure Tone, DPR, Gilbane top Building Design+Construction's 2013 ranking of the largest reconstruction contractor and construction management firms in the U.S.

| Jul 19, 2013

Reconstruction Sector Engineering Firms [2013 Giants 300 Report]

URS, STV, Wiss Janney Elstner top Building Design+Construction's 2013 ranking of the largest reconstruction engineering and engineering/architecture firms in the U.S.

| Jul 19, 2013

Reconstruction Sector Architecture Firms [2013 Giants 300 Report]

Stantec, HOK, HDR top Building Design+Construction's 2013 ranking of the largest reconstruction architecture and architecture/engineering firms in the U.S.

| Jul 19, 2013

Renovation, adaptive reuse stay strong, providing fertile ground for growth [2013 Giants 300 Report]

Increasingly, owners recognize that existing buildings represent a considerable resource in embodied energy, which can often be leveraged for lower front-end costs and a faster turnaround than new construction.

| Jul 19, 2013

Best in brick: 7 stunning building façades made with brick [slideshow]

The Brick Industry Association named the winners of its 2013 Brick in Architecture Awards. Here are seven winning projects that caught our eye. 

| Jul 18, 2013

LEGO takes on the iconic Sydney Opera House

This September, LEGO will expand its LEGO Creator Expert series with a 2,989-brick model of the iconic Sydney Opera House.

| Jul 18, 2013

Koolhaas plan selected for Miami Beach Convention Center redevelopment [slideshow]

The master plan by OMA's Rem Koolhaas and Shohei Shigematsu beat out a submission by Danish studio Bjarke Ingels Group for the massive redo of the Miami Beach Convention Center.

| Jul 2, 2013

LEED v4 gets green light, will launch this fall

The U.S. Green Building Council membership has voted to adopt LEED v4, the next update to the world’s premier green building rating system.

| Jul 1, 2013

Report: Global construction market to reach $15 trillion by 2025

A new report released today forecasts the volume of construction output will grow by more than 70% to $15 trillion worldwide by 2025.

| Jun 28, 2013

Building owners cite BIM/VDC as 'most exciting trend' in facilities management, says Mortenson report

A recent survey of more than 60 building owners and facility management professionals by Mortenson Construction shows that BIM/VDC is top of mind among owner professionals. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021