Manhattan’s first freestanding emergency department, the Lenox Hill Healthplex in Greenwich Village is the result of a sensitive restoration and adaptive reuse of the once-endangered Curran O’Toole Building, a maritime-inspired structure designed in the early 1960s by Frank Lloyd Wright protégé Albert C. Ledner.
BRONZE AWARD
Building Team: Perkins Eastman (submitting firm, architect); North Shore–LIJ (owner); JLL (owner’s representative); Robert Silman Associates (SE, façade consultant); Bard, Rao + Athanas Consulting Engineers (MEP); Turner Construction Company (contractor)
General Information: Size: 160,000 sf. Completion: July 2014. Delivery method: design assist
The building’s interior was stripped down to the bones, while the exterior was carefully preserved and updated. Its newly restored circular glass-block walls flood the ground-floor ED with natural light—an unusual feature in ED design—and the removal of portions of a previously-added second floor created an uplifting double-height space.
The tight urban site and outdated structure posed a number of thorny issues for the team, such as: accommodating emergency vehicle drop-off (solution: carve out a portion of the ground floor to make way for an ambulance bay without disturbing the façade); adding surgical functions (solution: reinforce the existing structure to meet vibration standards on the surgical floor and roof, and cut new shafts for ventilation); maintaining security (solution: minimize entrance points, maximize sight lines, lighting, and cameras); and delivery/storage of medical supplies and food (solution: transform the below-grade garage into space for support services).
The upper floors, currently under construction, will feature medical offices, walk-in imaging services, ambulatory surgery, orthopedics, physical medicine and rehabilitation, and health and wellness services.
Related Stories
Reconstruction Awards | Nov 13, 2017
Harlem Renaissance: A vacant school provides much-needed housing and a clubhouse for children
Word that PS 186 might be demolished brought out the preservationists, whose letter-writing campaign gained the support of the New York Landmarks Conservancy.
Reconstruction Awards | Nov 16, 2016
BD+C's 2016 Reconstruction Award Winners
St. Patrick’s Cathedral, Lovejoy Wharf, and the Bay Area Metro Center are just a few of the projects recognized as 2016 Reconstruction Award winners.
Reconstruction Awards | Nov 16, 2016
Reconstruction Awards: The Renwick Gallery of The Smithsonian American Art Museum
The renovation restored two long-concealed vaulted ceilings in the second-floor galleries and recreated the original 19th-century window configuration.
Reconstruction Awards | Nov 16, 2016
Reconstruction Awards: Massachusetts Maritime Academy
The two-story “overbuild” employed block and plank construction with drag strut detailing to connect it to the existing building.
Reconstruction Awards | Nov 16, 2016
Reconstruction Awards: The Masonic Temple
The building team suspended a new eighth-floor mezzanine and added 18 9x15-foot windows to the north, south, and west façades.
Reconstruction Awards | Nov 16, 2016
Reconstruction Awards: San Francisco War Memorial Veterans Building
The building team used a system of rocking concrete shear walls, which eliminated the need for deep foundations and reduced the shear force on each wall.
Reconstruction Awards | Nov 16, 2016
Reconstruction Awards: Arc at Old Colony
The Arc at Old Colony's vintage floor plans, voluminous lobby, and myriad elevators were perfect for redevelopment as a historically charming residential building.
Reconstruction Awards | Nov 16, 2016
Reconstruction Awards: Noble Chapel
In May 2013 the 124-year-old Noble Chapel, suffered a three-alarm fire that almost completely destroyed its 1937 crematorium.