Massachusetts Supreme Court clarifies building code liability issue on mixed-use projects

Massachusetts Supreme Court clarifies building code liability issue on mixed-use projects

Distinct portions of a building can be considered separate structures


By BD+C Staff | April 18, 2014
Photo: Albert Herring via Wikimedia Commons/Flickr
Photo: Albert Herring via Wikimedia Commons/Flickr

The Massachusetts Supreme Judicial Court recently ruled that distinct portions of a mixed-used building may be treated as distinct and different structures under the state building code. The ruling clarifies more than 40 years of sometimes contradictory decisions.

The case pertained to a resident of a mixed-use building who fell and was seriously injured when a guardrail on a staircase broke. A key question in the case was: “does a building containing both commercial and residential components fall entirely under the section of the state building code applying to commercial buildings?”

The court said that it was significant that resident's apartment wasn't in a commercial portion of the building with the staircase being separate from the commercial section of the structure. The court wrote: “In some cases, the term ‘building’ may encompass only a portion of a larger structure.”

 

(http://www.bizjournals.com/boston/news/2014/04/10/massachusetts-supreme-judicial-court-clarifies.html)

Related Stories

| May 3, 2012

Green-roof requirement now includes industrial facilities in Toronto

A mandate that requires installation of green roofs on new commercial and residential buildings in Toronto has been expanded to include industrial facilities.

| May 3, 2012

Innovative wastewater treatment helps achieve LEED rating

LEED for New Construction, Neighborhood Development and the LEED Volume Program offer some ways to achieve LEED points when dealing with wastewater treatment.

| Apr 26, 2012

Lack of bolts on steel support caused collapse at Cincinnati casino

Too few bolts connecting horizontal steel support beams with vertical steel columns was the cause of January’s construction accident at Horseshoe Casino Cincinnati, according to the report of the Occupational Safety and Health Administration.

| Apr 26, 2012

OSHA criticized for taking too long to roll out safety rules

The Occupational Safety and Health Administration takes far too long to adopt new safety regulations compared to other agencies’ development of rules, safety experts said during a Senate hearing.

| Apr 26, 2012

Contractors fear that GSA scandal will lead to fewer federal construction contracts

In the wake of the recent scandal at the General Services Administration in which workers spent lavishly at a Las Vegas conference, a spokesman for Associated General Contractors of America said contractors are worried the scandal will result in cuts to GSA's construction and renovation budgets.

| Apr 26, 2012

Developers can use LEED wastewater credits to help gain approvals in environmentally sensitive locales

Those wanting to pursue development in heavily regulated and environmentally sensitive areas are benefiting by designing projects that qualify for LEED points, even if the project as a whole does not achieve certification.

| Apr 26, 2012

New York City Council moves to license elevator mechanics

New York’s City Council introduced a measure last week that would require the city’s 7,000 elevator mechanics to meet national standards and be licensed by the city.

| Apr 23, 2012

AAMA releases updated specification for anodized aluminum

AAMA 611-12 describes test procedures and requirements for high performance (Class I) and commercial (Class II) architectural quality aluminum oxide coatings applied to aluminum extrusions and panels for architectural products.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021