MILITARY GIANTS: Cross-laminated timber construction gets a salute from the Army

MILITARY GIANTS: Cross-laminated timber construction gets a salute from the Army

By privatizing the construction, renovation, operation, maintenance, and ownership of its hotels the Army expects to cut a 20-year timetable for repairs and replacement of its lodging down to eight years.


By David Malone, Associate Editor | August 15, 2016

A construction crew installs one of 1,200 prefabricated cross-laminated timber (CLT) wall panels that make up the 92-room Candlewood Suites at Redstone Arsenal, Huntsville, Ala. Leadlease was the GC, developer, and owner on the project. It is the nation’s first all-CLT hotel project. Photo courtesy of Lendlease.

The United States Army has enough on its plate without having to worry about operating as a hotel manager, too.  

TOP 30 MILITARY ARCHITECTURE FIRMS
Rank, Firm, 2015 Revenue
1. HDR $24,971,124
2. Clark Nexsen $13,005,940
3. Guernsey $10,279,317
4. EwingCole $8,541,000
5. RS&H $8,100,000
6. Integrus Architecture $8,054,265
7. Leo A Daly $6,179,243
8. VOA Associates $4,600,000
9. Morris Architects $4,227,000
10. Emersion Design $4,095,748

SEE FULL LIST 

 

TOP 40 MILITARY CONSTRUCTION FIRMS
Rank, Firm, 2015 Revenue
1. Fluor Corp. $823,562,993
2. Walsh Group, The $382,116,917
3. Hensel Phelps $340,673,000
4. Gilbane Building Co. $303,821,000
5. Lendlease $269,240,000
6. Whiting-Turner Contracting Co., The $180,266,105
7. Balfour Beatty US $167,548,244
8. Turner Construction Co. $137,117,144
9. McCarthy Holdings $121,411,531
10. Haskell $81,252,088

SEE FULL LIST

 

TOP 40 MILITARY ENGINEERING FIRMS
Rank, Firm, 2015 Revenue
1. Jacobs $67,384,666
2. AECOM $50,000,000
3. Burns & McDonnell $41,464,789
4. Benham Design $15,481,228
5. Sherlock, Smith & Adams $14,439,000
6. Thornton Tomasetti $10,840,435
7. Jensen Hughes $8,068,991
8. Dewberry $5,353,171
9. RMF Engineering $5,028,000
10. Woolpert $4,083,332

SEE FULL LIST

On the heels of a U.S. Government Accountability Office report that showed that more than 80% of Army lodging needed repairs or replacement—at an estimated price tag of $1.8 billion over 20 years—the Army kicked its Privatization of Army Lodging (PAL) program into high gear.

By privatizing the construction, renovation, operation, maintenance, and ownership of its hotels (it is the only military branch to do so), the Army expects to cut that 20-year timetable down to eight years. 

Lendlease is a key partner in the PAL program, serving as the exclusive developer and owner of the hotels (the Army owns the land). InterContinental Hotels Group (IHG) is the PAL hotel operator under the Holiday Inn Express brand (for renovated Army hotels) and Candlewood Suites name (for newly constructed hotels).

The relationship between the Department of Defense, the Army, Lendlease, and IHG has produced lodging that has far exceeded anything created before PAL went into effect. For instance, the 310-room extended-stay hotel built on Joint Base San Antonio, completed in 2014, is the largest Candlewood Suites in the world.

The recently completed 92-room Candlewood Suites at Redstone Arsenal in Huntsville, Ala., is the first cross-laminated timber structure on a U.S. military installation and the first all-CLT hotel under any ownership type in the country.

Lendlease’s use of CLT, which is made of several layers of pressed lumber board stacked in alternating directions, is not a surprise. The company has committed $1 billion over the next five years to its Sydney, Australia-based startup, Design Make, which is dedicated to manufacturing prefabricated building components such as CLT.

Despite some early obstacles, such as meeting the highly restrictive military Anti-Terrorism and Force Protection requirements, the Building Team found that CLT construction was a great solution for the Redstone Arsenal project. Testing showed that the material performed well against the ATFP requirements due to its ability to carry load in varying directions.

“Labor scarcity, labor cost issues, schedule concerns, and foundation issues are all challenges that make CLT an attractive proposition,” says Lendlease’s Murray Woolcock, Executive General Manager, Strategic Business Units.

The Candlewood Suites on Redstone Arsenal totals 62,688 sf and can house 492 occupants. The structure used 1,200 CLT wall panels and 200,000 CLT fasteners. It is the first PAL structure to use prefabricated bathroom pods, which further helped to accelerate the construction schedule and reduce on-site waste.

By using prefabricated CLT, the Candlewood Suites was erected in just 10 working weeks by an 11-person crew, a 37% speed increase compared to conventional framing materials and methods for a similar-sized structure, according to Lendlease. 

The Redstone Arsenal hotel represents a small portion of the PAL program, which encompasses 12,492 guestrooms across 41 Army installations. Because CLT lends itself to structures with a repetitive room types, such as hotels, there is a good chance the Redstone Arsenal project will not be the only building on an Army base to utilize the material.

“Lendlease is currently evaluating numerous sites in our PAL portfolio to implement the use of CLT,” says Woolcock. “We are confident that CLT will gain traction in many areas, and Lendlease is well positioned to grow our platform off the back of the successful delivery of Redstone Arsenal.”

House approves $81B military Construction bill

With a vote of 277 to 147, the House on May 19 passed the Military Construction and Veterans Affairs bill, which, if enacted, would provide $81.6 billion in discretionary funding for the sectors in 2017. The total is $1.8 billion more than the 2016 budget, but $1.2 billion short of what President Obama requested.

Contained within the bill is funding to house, train, and equip military personnel, provide housing and services to military families, and maintain infrastructure. 

Nearly 10% of the total ($7.9 billion) would be used for large- and small-scale military construction projects at military bases in the U.S. and abroad. The allocation marks a $305 million decrease from fiscal year 2016, but is $250 million more than the President’s request. 

Other allocations of note: 

• $172 million for Overseas Contingency Operations and European Reassurance Initiative projects involving overseas bases

• $1.3 billion for the construction, operation, and maintenance of military family housing; while meeting the President’s budget request, it is $84 million off the budgeted amount in FY2015

• $304 million for the construction and alteration of military medical facilities

• $673 million for construction projects at National Guard and Reserve facilities across 21 states

• $900 million for VA construction projects

• $246 million for safety improvements and infrastructure work at DOD Education Activities facilities.

More on the bill at: http://bit.ly/28L8vwb.

 

RETURN TO THE GIANTS 300 LANDING PAGE

Related Stories

Laboratories | Oct 5, 2022

Bigger is better for a maturing life sciences sector

CRB's latest report predicts more diversification and vertical integration in research and production.

Multifamily Housing | Oct 5, 2022

Co-living spaces, wellness-minded designs among innovations in multifamily housing

The booming multifamily sector shows no signs of a significant slowdown heading into 2023. Here is a round up of Giants 400 firms that are driving innovation in this sector.

Contractors | Oct 5, 2022

Materials shortages, cost spikes throwing Design-Bid-Build process out of whack

The traditional Design-Bid-Build delivery process is under considerable stress this year as materials shortages and cost spikes are upending usual practices, according to a new report from JLL.

Green | Oct 5, 2022

In California, a public power provider’s new headquarters serves as a test case for an innovative microgrid and for reducing greenhouse gas emissions

Sonoma Clean Power (SCP), the public power provider for California’s Sonoma and Mendocino Counties, recently unveiled its new all-electric headquarters.

Contractors | Oct 4, 2022

Which comes first, the building or the cost estimate?

At the start of a project, don’t forget to establish financial parameters when you’re discussing the design and program. By establishing the costs up front, you can avoid the pitfalls that might derail your project and guarantee its lasting success.

Fire and Life Safety | Oct 4, 2022

Fire safety considerations for cantilevered buildings

Bold cantilevered designs are prevalent today, as developers and architects strive to maximize space, views, and natural light in buildings. Cantilevered structures, however, present a host of challenges for building teams, according to José R. Rivera, PE, Associate Principal and Director of Plumbing and Fire Protection with Lilker.

| Oct 4, 2022

Rental property owners want access to utility usage data for whole properties

As pressure from investors for ESG reporting mounts, owners of multifamily properties increasingly look to collect whole-building utility usage data.

| Oct 4, 2022

In dire need of affordable housing, Aspen, Colo. will get a development that provides 277 affordable homes

A few miles from downtown Aspen, Colo., a development will provide 277 new affordable homes for an area experiencing a dire affordable housing crisis.

Green | Oct 3, 2022

California regulators move to ban gas heaters for existing buildings

California regulators voted unanimously recently on a series of measures that include a ban on the sale of natural gas-powered heating and hot water systems beginning in 2030.

| Oct 3, 2022

The College of the Holy Cross completes a $110 million performing arts center

In Worcester, Mass., a one-hour drive from Boston, the College of the Holy Cross has completed its $110 million Prior Performing Arts Center.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021