Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

By using modular construction, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction.


September 19, 2012
During the construction of Mountaineer Hall, 129 modules were set and sealed in
During the construction of Mountaineer Hall, 129 modules were set and sealed in 12 days.

As the student population rose at Appalachian State University in Boone, N.C., so did the demand for housing. Because residence officials at the school needed to have a new dormitory in place for the upcoming academic year—and use a method in line with the school’s focus on sustainability—modular construction was the logical choice for one of two dorms on campus.

“After visiting other campuses, we decided a modular style project was the correct approach,” said Tom Kane, director of University Housing.

By using modular, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction. The traditional dorm, a 333-bed suite style hall, opened in August 2012. The modular facility, a 460-bed complex, was finished in just nine months and was ready for students by August 2011.

Even though the project was completed quickly, construction was not without challenges.

“Coordinating the transport of the units to the site without interrupting traffic on campus was a concern from the very beginning because of the sharp turn and incline entering the site,” said project manager Dustin Hunter of Hunter Saak Modular. “Safety was our number one concern from the very beginning.”

Once finished, Mountaineer Hall became a beautiful home for students. The 97,000-sf, brick-exterior facility features two-person hotel style rooms with individual bathrooms for increased student privacy. Common areas on each floor lend a feeling of community between the residents.

Not only is the dorm attractive and comfortable, it is LEED Gold certified. The facility received a total of 68 points based on its energy-saving and sustainability features. (Sixty-five points are needed to receive Gold certification). LEED-certified homes complete a technically rigorous process that often includes a home energy (HERS) rating and onsite inspections to verify that the home is built to be energy and water efficient, environmentally sound and a healthier place to live.

The building’s energy and water conserving features include energy-efficient, tinted windows and a 40-panel solar thermal system to provide hot water.? Site stewardship involved erosion control measures taken during construction, landscaping and storm water controls.

Mold-resistant drywall was used throughout the entire building, improving future indoor air quality. The same type of drywall was placed throughout the building to reduce the amount of drywall waste.

Pre-built floor assembly was utilized at the factory to lessen production time. Identical boxes with an average size of 12- x 64- x 10-ft allowed for shortened production and installation time. The dormitory was 80 percent complete when it arrived on site, lessening the time spent on trim work and finishing on site.

All utility chases were designed to be accessed from the building exterior, eliminating unnecessary down time when crane setting the units. The modules were set and sealed in 12 days.

With its outstanding design features, Mountaineer Hall received Honorable Mention in the Permanent Commercial Housing: Over 10,000 Square Feet category in the Modular Building Institute’s 2012 Awards of Distinction. The modular contractor on the project was Hunter Saak Modular with affiliates Clayton Building Solutions and R&S Tavares.

For more information about the project, visit Hunter Saak Modular.

The Modular Building Institute (MBI) is the international non-profit trade association serving the modular construction industry. Members are suppliers, manufacturers and contractors engaged in all aspects of modular projects from complex multi-story solutions to temporary accommodations.

As the Voice of Commercial Modular Construction, it is MBI's mission to expand the use of offsite construction through innovative construction practices, outreach and education to the construction community and customers, and recognition of high quality modular designs and facilities. To learn more about modular construction, go to www.modular.org. +

Related Stories

Religious Facilities | Mar 23, 2015

Is nothing sacred? Seattle church to become a restaurant and ballroom

A Seattle-based real estate developer plans to convert a historic downtown building, which for more than a century has served as a church sanctuary, into a restaurant with ballroom space.

Government Buildings | Mar 23, 2015

SOM leads planning for Egypt’s new $45 billion capital city

To alleviate overcrowding and congestion in Cairo, the Egyptian government is building a new capital from scratch.

BIM and Information Technology | Mar 23, 2015

Skanska hosts three-week 'hackathon' to find architect for Seattle tower development

Searching for a nimble, collaborative design firm for its 2&U tower project in Seattle, the construction giant ditches the traditional RFQ/RFP process for a hackathon-inspired competition.

Healthcare Facilities | Mar 23, 2015

Can advanced elevator technology take vertical hospitals to the next level?

VOA's Douglas King recalls the Odyssey project and ponders vertical transportation in high-rise healthcare design.

Healthcare Facilities | Mar 22, 2015

New Joplin, Mo., hospital built to tornado-resistant standards

The new hospital features a window and frame system that can protect patients from winds of up to 250 mph. 

Sports and Recreational Facilities | Mar 19, 2015

Populous design wins competition for UK's most sustainable arena

The live-concert venue will seat an audience of 12,000, which the firm says will be masked by “the atmosphere and intimacy of a 4,000-seat amphitheatre.” 

Architects | Mar 18, 2015

Architecture Billings Index rises in February

The ABI score was 50.4 last month, up slightly from a mark of 49.9 in January. This score reflects a minor increase in design services, according to AIA. 

Multifamily Housing | Mar 18, 2015

Prefabricated skycubes proposed with 'elastic' living apartments inside

The interiors for each unit are designed using an elastic living concept, where different spaces are created by sliding on tracks.

Architects | Mar 18, 2015

Boston selects finalists in resilient design competition

The competition asks for creative approaches for planning for a not-so-distant future Boston where higher sea levels and more frequent flooding will be real and critical issues to contend with.

Cultural Facilities | Mar 17, 2015

The High Line’s co-designer wins contract for The Underline in Miami

James Corner Field Operations will design the master plan for this 10-mile restoration project. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021