Most daylight harvesting schemes fall short of performance goals, says study

Most daylight harvesting schemes fall short of performance goals, says study

A new study by the Energy Center of Wisconsin shows the importance of commissioning when implementing automatic daylighting control programs.


By BD+C Staff | April 8, 2013

Analysis of daylighting control systems in 20 office and public spaces in Minnesota and Wisconsin shows that while the automatic daylight harvesting schemes are helping to reduce lighting energy in the buildings, most are not achieving optimal performance, according to a new study by the Energy Center of Wisconsin (ECW).

According to ECW, the median daylighting control system studied was saving 23% of lighting energy, including impacts on heating and cooling. This translated to 915 kWh saved for every kW of lighting controlled. But the average effectiveness (the energy saved versus energy saved with ideal control) of the controls was only 51%. This meant that almost half of the potential savings from these controls was not captured due to imperfect controls operation. Even worse, four of the 20 spaces studied had zero savings.

The low level of effectiveness, says ECW, is evidence of a lack of controls execution. The findings show that successful implementation of automatic daylighting control requires a significant commissioning effort to reach full energy-savings potential.

Read the full daylighting commissioning report from the Energy Center of Wisconsin.

As part of the report, ECW developed a tip sheet on commissioning and calibration and function testing of lighting controls. Recommendations include assigning a single person of the construction team to be responsible for verifying completion of all steps in the daylighting commissioning process, and proper training of the building owner/operator on the controls equipment and systems. Download the tip sheet (PDF)

(http://www.ecw.org/project.php?workid=1&resultid=494)

Related Stories

| Nov 22, 2011

New Green Matters Conference examines emerging issues in concrete and sustainability

High-interest topics will be covered in technical seminars, including infrared reflective coatings for heat island mitigation, innovative uses of concrete to provide cooling and stormwater management, environmental benefits of polished concrete, and advancements in functional resilience of architectural concrete.

| Nov 22, 2011

Suffolk Construction selected as contractor for Boston luxury residential tower

Project team breaks ground on 488,000-sf building that will feature world-class amenities.

| Nov 22, 2011

Jones Lang LaSalle completes construction of two new stores in Manhattan

Firm creates new global design standard serving as project manager for Uniglo’s 89,000-sf flagship location and, 64,000-sf store.

| Nov 21, 2011

Mortenson and enXco partnership to build its 19th wind project

The 8,500 acres project will generate140 megawatts of wind power – enough energy to power approximately 39,000 homes.

| Nov 21, 2011

FDH Engineering acquires Energy Solutions

All ESI employees have been merged into FDH’s staff at its St. Louis office.

| Nov 18, 2011

Centre for Interactive Research on Sustainability opens

Designed to exceed LEED Platinum, the Centre for Interactive Research on Sustainability (CIRS) is one of the most innovative and high performance buildings in North America today, demonstrating leading-edge green building design products, technologies, and systems.

| Nov 17, 2011

SmithGroup changes name to SmithGroupJJR

SmithGroup and JJR join brands to become a single, multi-disciplinary company.

| Nov 17, 2011

Campus-wide energy-efficiency program aims to deliver $3.5 million in energy and operational savings

Merced College and Honeywell will use the school’s energy usage statistics to develop a course curriculum on sustainability, and raise awareness among students of the positive impact conservation practices contribute to the community.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021