Most top U.S. contractors rarely deliver projects on time: new study

Contractors

Most top U.S. contractors rarely deliver projects on time: new study

Struggles with supply chain disruptions, construction costs, and new sustainability requirements cause delays, according to a new study by XYZ Reality.


By Peter Fabris, Contributing Editor | June 26, 2023
Photo by Ricardo Gomez Angel on Unsplash
Photo by Ricardo Gomez Angel on Unsplash

About 63% of leading U.S. contractors are delivering projects out of schedule, according to a survey of over 300 C-suite executives and owners in the construction industry by XYZ Reality.

The study implies that the industry is struggling with significant backlogs due, in part, to avoidable defects, scan, and rework. The construction sector is also hampered by supply chain disruptions (cited by 52% of respondents), rising construction costs (43%), and meeting new sustainability requirements (36%).

Other reasons cited for falling short of schedule benchmarks include poor communication (45%), inexperienced workers (39%), and insufficient supervision (34%). This data suggests that a significant amount of human error is to blame, XYZ notes.

Design changes, or the misinterpretation of them, were also cited by about a quarter of respondents. To control costs and cope with industry challenges, contractors are increasingly looking to technology solutions such as augmented reality.

Related Stories

| Mar 7, 2012

Turner appointed Batson-Cook CFO and treasurer

Cecil G. Hood to continue in advisory role.

| Mar 7, 2012

Thornton Tomasetti names Dowdall VP of Kansas City office

Dowdall will be responsible for supporting the Property Loss Consulting, Building Performance and Building Sustainability practices nationally.

| Mar 7, 2012

LEO A DALY selected to design Minnesota Fallen Firefighters Memorial

The bronze, figurative sculpture of a firefighter rescuing a child, which is currently on display at the Minneapolis/St. Paul International Airport, is lit by natural light through a circular void in the monolith.

| Mar 7, 2012

Houlihan Lokey adds Steffen to Industrials Group

Steffen bolsters group with experience in the building materials and rorest product sectors.

| Mar 6, 2012

Country’s first Green House home for veterans completed

Residences at VA Danville to provide community-centered housing for military veterans.

| Mar 6, 2012

EwingCole completes first design-build project for the USMA

The second phase of the project, which includes the academic buildings and the lacrosse and football fields, was completed in January 2012.

| Mar 6, 2012

Gensler and Skender complete new corporate headquarters for JMC Steel in Chicago

Construction was completed by Skender in just 12 weeks.

| Mar 6, 2012

BLT Architects promotes two to associate

Architect Nicole Dress and interior designer Jessica Moser acknowledged for excellence.

| Mar 6, 2012

Joliet Junior College achieves LEED Gold

With construction managed by Gilbane Building Company, Joliet Junior College’s Facility Services Building combines high-performance technologies with sustainable materials to meet aggressive energy efficiency goals.

| Mar 5, 2012

Tishman constructing new courthouse in Philadelphia

Construction is underway for the Pennsylvania Department of General Services’ 510,000-sf facility.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021