A new BSL-3 public-safety lab debuts in Vermont

A new BSL-3 public-safety lab debuts in Vermont

The project’s Building team is tested by this facility’s complex mechanical system and air exchange requirements. 


By John Caulfield, Senior Editor | November 17, 2014
Vermonts state-of-the-art public safety facility includes unique biosafety labs
Vermonts state-of-the-art public safety facility includes unique biosafety labs that rely on complicated mechanical systems to

The Vermont Department of Health and the University of Vermont in late October held ribbon-cutting ceremonies for a 60,000-sf public health laboratory that is nearly twice the size of the 62-year-old lab it replaces. The laboratory will be used to perform a wide range of analyses to detect biological, toxicological, chemical, and radiological threats to the health of the population, from testing for rabies, West Nile, pertussis and salmonella to water and food contaminants.

The new $31 million facility, located at the Colchester Business and Technology Park, took 18 months from its notice to proceed to its completion. It is distinguished by highly specialized Biosafety Level 3 and Animal Biosafety Level 3 (BSL-3 and ABSL-3) laboratories, as well as high-performance building enclosure, mechanical, electrical, plumbing and fire suppression systems to conduct specialized laboratory work.

That mechanical system accounted for about 40% of the project’s total cost, and posed the biggest installation challenge for Vermont-based PC Construction, the contractor on this project, according to Matt Cooke, PC’s senior project manager. “The building’s ‘penthouse’ is all mechanical, and the facility is jammed-packed with air recovery and exchange equipment.  

He says that “to make everything fit,” PC and the Building Team did extensive BIM modeling That team consisted of HDR (architectural design), Scott & Partners (exterior envelope), Krebs & Lansing (civil engineering), Zero by Design (energy consultation), as well as the State of Vermont Department of Building and General Services and the university (owners).

 


Westphalen Photography

 

PC Construction has built a number “clean rooms” in the past, but nothing as elaborate as this facility, which includes one of the few BSL3 labs in the country, says Cooke. He notes that some of the lab space requires zero leakage, so everything—including the electrical boxes and windows—needed to be sealed. Cooke adds that what also makes the facility unique are its “systems and automated controls” for the anterooms and air exchange machinery.

The building sits on a foundation supported by 180 H-piles that are driven to depths of between 70 and 90 feet. The original plans called for piles that would only need to be 60 to 65 feet deep. “But once we got out there and started drilling,” Cooke says PC found that the geological survey hadn’t sufficiently taken into account the location of underground rocks, which dictated far-deeper piles.

The facility design called for its six flue-gas stacks to be 75 feet above ground, which required FAA approval and a non-reflective coating due to their height and proximity to Burlington International Airport. 

 


Westphalen Photography

 


PC Construction

 


PC Construction

 


PC Construction

Related Stories

| Jun 23, 2014

Power of IPD: Is integrated project delivery truly a transformative delivery model?

Now that many of the first-generation IPD projects have been completed, CBRE Healthcare's Tim McCurley and Stephen Powell ponder the lessons learned and pros and cons of the industry's newest delivery model. 

| Jun 23, 2014

Lilker Associates launches Lighting Group; David Cyr announced as Director

New division rounds out building systems services offerings for the Manhattan-based consulting firm.

| Jun 23, 2014

Berlin House of One will accommodate Muslims, Jews, and Christians

The building will rise on the ruins of a 13th-century Christian church that was damaged during WWII and eventually demolished.

| Jun 22, 2014

5 ways to improve your firm’s branding efforts

Establishing, conveying, and maintaining a powerful brand is a critical component of an AEC firm’s marketing strategy. Here are five strategies to make a greater impact with your firm’s branding efforts.

Sponsored | | Jun 22, 2014

JW Marriott Indianapolis redefines city’s skyline

The 34-story JW Marriott is both the largest and tallest hotel in Indianapolis. One of the most prestigious hotels in the city, the JW Marriott has hosted celebrities and NFL teams alike. 

| Jun 20, 2014

HOK releases proposal for Obama Library and Museum Campus

Proposal would locate the library in Chicago's historic Bronzeville neighborhood, aiming for urban revitalization as well as Living Building certification.

| Jun 20, 2014

Sterling Bay pulled on board for Chicago Old Main Post Office project

Sterling Bay Cos. and Bill Davies' International Property Developers North America partner up for a $500 million restoration of Chicago's Old Main Post Office

| Jun 20, 2014

First look: Hive-like 'Learning Hub' to be built in Singapore

In a competition to design a "Learning Hub" for students at Nanyang University in Singapore, London-based firm Heatherwick studio has won with a rounded, hive-like design. 

| Jun 20, 2014

U.S. Energy Information Administration releases preliminary Commercial Buildings Energy Consumption Survey results

Federal survey project shows that commercial-building floorspace has grown 22% since 2003; energy-use data will be released in Spring 2015.

| Jun 19, 2014

First Look: 10 Design unveils new luxury apartments plan in Dubai

The Seventh Heaven complex features a stepped form that will offer stunning views of the Dubai skyline.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021