St. Louis recently passed a new law requiring all new buildings to be made solar-ready.
All new structures—commercial and residential—must reserve rooftop sections for solar panels to be easily installed. The ordinance does not mandate that rooftop solar be installed.
The solar-ready zone must be at least 40% of the roof area. It can be one contiguous area or multiple smaller sub-zone areas that are no less than five feet in width at their narrowest point. The solar-ready area cannot be obstructed by pipes, vents, HVAC equipment, or other shadow-casting elements.
Construction documents must outline pathways for routing of piping from the solar-ready zone to the building’s electrical service panel or service hot water system. The electrical panel must also have reserved space for a dual-pole circuit breaker to support future solar installations.
New buildings that have permanently-installed onsite generation systems already, buildings whose solar-ready zones would be shaded from sunlight for more than 70% of the day, and buildings where a licensed design professional has deemed that the solar radiation available to the building is not suitable to a solar-ready zone or because the area requirement cannot be met due to extensive rooftop obstructions, may be exempt.
Related Stories
| Dec 29, 2011
OSHA enforcing new fall hazard standards
OSHA is enforcing its new fall protection standards, as evidenced by a recent crackdown in New York.
| Dec 29, 2011
NRCA offers program on new fall-protection requirements
The National Roofing Contractors Association's (NRCA's) program "Roofing Industry Fall Protection from A to Z" will be held Feb. 21 during the organization's 125th Annual Convention.
| Dec 29, 2011
Decision not to fireproof the new World Trade Center Transportation Hub criticized
Some criticized the decision, reasoning that the structure could be a terrorist target.
| Dec 29, 2011
Seismic safety in question at thousands of California public schools
California regulators responsible for enforcing earthquake safety laws have failed to certify more than 16,000 construction projects in California public schools, increasing the risk that some projects may be unsafe, according to a state audit report.
| Dec 29, 2011
GreenWizard offers cloud-based LEED credit management, assessment
The company recently began offering companies the ability to run assessments for design credits, in addition to traditional product-specific LEED credits.
| Dec 22, 2011
Federal home weatherization program has impacted 6.8 million homes
More than 6.8 million homes have been weatherized using federal, state, utility, and other funds under the American Recovery and Reinvestment Act.
| Dec 22, 2011
Group developing BIM data standards
A collaboration among Georgia Tech’s Digital Building Lab, the Precast Concrete Institute, the American Concrete Institute, and the American Institute of Steel Construction aims to develop global standards for transportation of three-dimensional digital models among fabricator, architecture, engineering, and construction groups.
| Dec 22, 2011
New green code spells out thermal requirement for roof retrofits
The 2012 International Green Construction Code (IgCC) includes a straightforward approach to minimum thermal requirements for roof and wall systems.
| Dec 22, 2011
AGC’s safety conference Jan. 11-13 in San Antonio
The Associated General Contractors of America’s national meeting for safety and health professionals will take place Jan. 11-13, 2012 in San Antonio, TX.
| Dec 22, 2011
Proposed New York City zoning revamp encourages rooftop solar and wind energy
New zoning regulation proposals to make it easier for building owners in New York City to make their structures more sustainable have entered the public approval process.