NIST investigation of Champlain Towers South collapse indicates no sinkhole

Engineers

NIST investigation of Champlain Towers South collapse indicates no sinkhole

No significant settling reported in preliminary finding


By Peter Fabris, Contributing Editor | September 15, 2023
NIST investigation of Champlain Towers South collapse indicates no sinkhole Photo courtesy NIST
Photo courtesy NIST

Investigators from the National Institute of Standards and Technology (NIST) say they have found no evidence of underground voids on the site of the Champlain Towers South collapse, according to a new NIST report.

The team of investigators have studied the site’s subsurface conditions to determine if sinkholes or excessive settling of the pile foundations might have caused the collapse. They have found no such evidence to support that potential cause.

Preliminary evaluation of data indicates about one quarter of an inch or less of settling in the pile foundations supporting the pool deck structure and basement. This would have had minimal impact on the pool deck structure, NIST says.

“Understanding exactly what caused this collapse is taking meticulous investigation and the collection of copious amounts of evidence and information,” said Joannie Chin, director of NIST’s Engineering Laboratory. “Our team members are dedicated to unraveling the complexities of this tragic event, and their rigorous research and analysis will not only help us understand the likely technical cause of the collapse but will improve the safety of our communities.”

The team’s preliminary evaluation of physical and historical evidence found that the pool deck construction deviated from design requirements. Specifically, the number of slab reinforcing bars centered over vertical columns was inadequate, and the reinforcing bars in the top of the slab in the vicinity of the columns were spaced farther apart than the design required, according to investigators. These deviations weakened the slab-column connections, they said.

NIST expects technical work on the investigation to be substantially completed in late June 2024 and aims to release a report with findings and recommendations in late June 2025.

Related Stories

| Apr 6, 2012

Flat tower green building concept the un-skycraper

A team of French designers unveil the “Flat Tower” design, a second place winner in the 2011 eVolo skyscraper competition.

| Apr 6, 2012

National Association of Women in Construction forum to be hosted in Philadelphia

The April Forum, titled “Declare your Independence!” will feature educational sessions on topics ranging from Managing the Generation Gap and Dealing with Contract language across state borders to Strategic and Succession Planning.

| Apr 6, 2012

Rooftop solar energy program wins critical approval from L.A. city council

Los Angeles Business Council applauds decision allowing LADWP to create new national model for rooftop solar energy

| Apr 6, 2012

Batson-Cook breaks ground on hotel adjacent to Infantry Museum & Fort Benning

The four-story, 65,000-ft property will feature 102 hotel rooms, including 14 studio suites.

| Apr 6, 2012

Perkins Eastman unveils Qatar mixed-use sports complex

Home stadium for Lekhwiya Club a vibrant addition to Doha’s architectural identity.

| Apr 5, 2012

5 tips for a successful door and window retrofit

An exclusive tip sheet to help the Building Team manage door and window retrofits successfully.

| Apr 4, 2012

HDS designs Mount Auburn Hospital’s new healthcare center in Waltham, Mass.

HDS Architecture provided design services for all the Mount Auburn Healthcare suites including coordination of HVAC and FP engineering.

| Apr 4, 2012

Bald joins the Harmon glazing team

Bald has 13 years of experience in the glazing industry, coming to Harmon from Trainor where he was the regional manager of the Mid-Atlantic region.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021