The best seat in the house at the new Seahawks Stadium in Seattle isn't on the 50-yard line. It's in the southeast corner, at the very top of the upper bowl. "From there you have a corner-to-corner view of the field and an inspiring grasp of the surrounding city," says Kelly Kerns, project leader with architect/engineer Ellerbe Becket, Kansas City, Mo. "You feel like you're part of something amazing."
That's just what the Building Team for Seahawks Stadium and Exhibition Center hoped for. Set against a backdrop of snow-capped mountains and the shimmering waters of Puget Sound, the new complex offers links to historic Pioneer Square, the city's International District, and downtown, melding it all into a unique Seattle experience.
The new football/soccer stadium, 325,000-sq.-ft. exhibition center, and 2,000-car parking garage are the product of First & Goal, Inc., an entity formed by Paul Allen, the multibillionaire co-founder of Microsoft and owner of the Portland Trailblazers of the National Basketball Association. In 1996, Allen took a 14-month option on the Seahawks when then-owner Ken Behring tried unsuccessfully to move the team to Los Angeles.
The deal required Allen to tear down the Kingdome and build a new stadium, at a time when Washington State taxpayers were soured by the $100 million in overruns that plagued construction of the $517 million Mariners baseball stadium. Allen put up $9 million to push through a referendum that, in June 1997, created the Washington State Public Stadium Authority and capped the public's obligation at $300 million. Allen guaranteed $130 million out of pocket, plus the cost of any overruns.
Reflecting the culture
At 8:31 a.m. on March 26, 2000, the 25-year-old Kingdome was imploded by Aman Environmental (at a cost of $9.2 million), and the Building Team of Ellerbe Becket and Turner Construction's Seattle office, headed by senior vice president Thomas Gerlach, Jr., set to work creating a structure for the Seahawks, a possible future Major League Soccer team, Seattle Flat Show Coalition and — most important — the community.
The building was designed to fit into an urban neighborhood, which includes the adjacent baseball dome, Safeco Field. "In the 1880s, the entire area was burnt to the ground," says Kerns. "As a result, all of the buildings there were built within the same 10- to 15-year timeframe — with the same construction elements, at the same height of about 85 feet."
To conform to the neighborhood's height limit, the stadium rests on an 85-ft.-high masonry base, from which rises the concrete seating and steel roof structure. Using a stained, colored concrete and concrete unit masonry, the masonry base echoes the historic structures found throughout Pioneer Square.
The U-shaped seating design and upper bowl, which sits a mere 50 feet from the sidelines, also creates a feeling of intimacy. "Paul Allen wanted to create the most intimate NFL stadium with unsurpassed sightlines — so we employed a 56-ft. cantilever, the largest in the NFL, of the upper bowl over the suite level, bringing the upper bowl seats closer to the field," said Kerns. With the open end of the "U" facing north toward downtown Seattle, spectators are connected to the surrounding communities, while those outside the stadium have views inside.
The new icon of the Seattle skyline is the stadium's 1.4 million pound roof, which spans 720 feet and features the largest post-tensioned arches in the U.S. The white-painted steel "rainbow span" connects the downtown high-rise structures with the Space Needle to the north.
This is no mean feat in a seismic zone of this nature. The structure was designed to withstand an earthquake of 7.0 strength; in fact, a lesser earthquake hit during construction in February 2001, causing only minor damage.
To decrease the lateral loads imparted from the trusses to the pylons during a seismic event, project structural engineer Magnusson Klemencic Associates of Seattle developed a creative application of industrial technology to solve the bearing condition at each end of the trusses. The plan uses base-isolating friction pendulum damper bearings that allow the roof to move 2 ft. differentially from the pylons.
The first application of this technology in the world on a large roof span, this solution reduced the amount of reinforcing in the cast-in-place concrete pylon walls and footings, which resulted in a $2.5 million savings and gave Seattle a monument to structural engineering.
Supported by 5,700 tons of steel, the roof itself is covered with UltraGard SR-50, a PVC membrane single-ply roofing system from Johns Manville. It covers 70% of the seats, but is open to the field.
From the project's beginning in early 1997, the team knew that this stadium, like the Kingdome before it, would be a significant feature of the Seattle skyline. For that reason, the project's schedule and budget needed to reflect the interests of the community as well. The complex is the only recent major public/private project to come in on time and on budget in the Northwest.
Completed in June 2002 and opened for public view on July 20, the stadium hosted its first event — a soccer match between the Seattle Sounders and the Vancouver Whitecaps of the A League — last July 28, before 25,515 fans. The Seahawks lost their exhibition home opener 28-10 to the Indianapolis Colts on August 10 and their regular-season home opener to the Arizona Cardinals, 24-13, on September 15, 2002.
The $430 million facility features a cost-per seat that is 7% less than the average of the last 13 new NFL stadiums. Change orders ran 10% below the average cost on comparable buildings. "The project team stayed very committed to being on time and under budget," says Tom Gerlach, SVP/GM of Turner's Seattle office. "The project is a model for public-private partnerships."
The five-level complex features 67,000 permanent seats (plus room for 5,000 more, qualifying the stadium to host a Super Bowl), 84 suites (one of which is reserved for season ticket holders, by lottery), 48 concession stands, 841 televisions (including 80 Philips high-definition TVs), and 63 restrooms — more than twice as many as at the Kingdome.
The playing surface uses an artificial turf by FieldTurf. (Grass will be installed in the event the stadium is ever host to a World Cup-caliber soccer match.) The facility is illuminated by 672 Musco sports lights and contains $1.75 million in public art. The end-zone pylon contains a $7.5 million video board, 84x24 ft., designed by Lighthouse Technologies, Hong Kong.
Seats are priced as low as $20. In the end zones are a dozen so-called "Red Zone" suites at field level — a unique feature among NFL stadiums.
To maximize the stadium's use on non-game days, the exhibition center can use 92,900 sq. ft. of flex space within the stadium. The result of the integrated approach of restaurant, exhibition, and sports venue is a urban leisure center for Seattle.
Demanding diversity
The Building Team was dedicated to reaching Seattle's diverse population. Extraordinary steps were taken to meet the needs of fans with disabilities, says Kerns. Holding public forums and working with compliance consultant Kevin McGuire, himself a person with disabilities, they learned that disabled fans who have to travel long distances to attend games often can't sit through the whole event without rest, so they set up sleeping rooms for them in the First Aid areas.
Seven hundred seats were set aside for disabled fans, with another 700 for their companions, all in areas where fans with disabilities would not be obstructed by other cheering fans.
Town hall meetings were held to obtain input on community impact. As a result, $10 million was set aside for neighborhood improvements. Two of the groups the team specifically targeted to involve in the project were apprentices and minority and women business enterprises (M/WBE).
The Building Team voluntarily established a goal of hiring apprentices to fill 15% of all construction jobs, especially in the carpentry, electrical, masonry, painting, and plumbing trades. To encourage racial and ethnic diversity, Turner brought in a seasoned community affairs director, Ruby Jones, who spoke at numerous community meetings about career opportunities in construction.
The Building Team also set up liaisons with the trade unions and recruited apprentices from local union halls. The result: 19% apprentice participation, beating their goal by four percentage points.
"This is a good example of going beyond public policy," observed Building Team awards judge Philip Tobey, AIA, of the Washington, D.C., office of the SmithGroup. "The apprentice programs with Seattle Vocational are terrific."
To further diversity, the Building Team implemented an aggressive program to contract with M/WBE, even though a recent statewide initiative had done away with affirmative action requirements. "Projects you work on should reflect the community," says Jones.
"It's essential that you have this involvement if you're going to really reflect the community," says EB's Kerns. "We rely on local M/WBEs to help provide the local input that contributes to the success of the project."
Of the total $430 million budget, $81 million was awarded to some 116 M/WBE firms, including $69 million in construction contracts and $7 million in A/E work.
Locating M/WBE companies wasn't easy. The pool of certified minority and women workers had shrunk at an alarming rate after the passage of the state initiative. To find qualified businesses, Jones and her team conducted one-on-one interviews with prospective companies and worked to partner with them.
"For more than 30 years, M/WBE inclusion has been a part of the way Turner does business, so we needed to ensure that we had a viable group to work with not just for this project, but for other projects down the line," says Jones.
To ensure the appropriate work environment for minorities and women, the Building Team set a policy of zero tolerance with regard to on-site discrimination.
A key factor in the success of the program was the creation of the Turner School of Construction Management in Seattle. Conceived in 1969 by the firm's Cleveland office, the program has educated thousands of M/WBE contractors in basic and advanced construction techniques.
In Seattle, the program has been sponsored by the Associated General Contractors, the AGC Education Foundation, and the cities of Tacoma and Seattle. Since its creation in 2000, the Seattle school has graduated 52 M/WBE owners.
The stadium was designed to handle the community's needs well into the future. "The project includes spare infrastructure capacity, including the ability to expand the seating area," says Kerns. The parking garage structure is oversized to accommodate future additions.
According to competition judge Larry Griffis, of Walter Moore & Co., "For a huge, bulky stadium with massive scale, the design is good "
After maintenance and operating costs are met, any profits generated by the stadium and exhibition center will be split three ways—one part going to the Seahawks, another placed in reserve to cover any revenue shortfalls, and a third used to build youth playfields across the state.
First & Goal also funded a $6 million mitigation fund for three nearby neighborhoods. "The project stayed focused on the community goals from the very start—that was the key ingredient of success in the eyes of First & Goal and the Public Stadium Authority," says Turner's Gerlach.
Construction Costs
* Includes cost of permits; design, legal, and consultant fees and expenses, environmental impact study; public relations and community outreach program costs | |
General requirements | $34,320,000 |
Site construction | 31,200,000 |
Concrete/masonry | 91,300,000 |
Metals | 57,000,000 |
Woods and plastics | 2,952,000 |
Thermal and moisture protection | 9,600,000 |
Doors and windows | 7,600,000 |
Finishes and specialties | 21,500,000 |
Equipment, furnishings, conveying systems | 19,760,000 |
Mechanical/electrical | 74,768,000 |
SUBTOTAL | $350,000,000 |
Neighborhood mitigation fund | 10,000,000 |
Additional costs* | 70,000,000 |
TOTAL | $430,000,000 |
Related Stories
Giants 400 | Feb 5, 2024
Top 30 Entertainment Center, Cineplex, and Theme Park Architecture Firms for 2023
Gensler, JLL, Nelson Worldwide, AO, and Stantec top BD+C's ranking of the nation's largest entertainment center, cineplex, and theme park architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.
Urban Planning | Feb 5, 2024
Lessons learned from 70 years of building cities
As Sasaki looks back on 70 years of practice, we’re also looking to the future of cities. While we can’t predict what will be, we do know the needs of cities are as diverse as their scale, climate, economy, governance, and culture.
Giants 400 | Feb 5, 2024
Top 90 Shopping Mall, Big Box Store, and Strip Center Architecture Firms for 2023
Gensler, Arcadis North America, Core States Group, WD Partners, and MBH Architects top BD+C's ranking of the nation's largest shopping mall, big box store, and strip center architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.
Laboratories | Feb 5, 2024
DOE selects design-build team for laboratory focused on clean energy innovation
JE Dunn Construction and SmithGroup will construct the 127,000-sf Energy Materials and Processing at Scale (EMAPS) clean energy laboratory in Colorado to create a direct path from lab-scale innovations to pilot-scale production.
Architects | Feb 2, 2024
SRG Partnership joins CannonDesign to form 1,300-person design giant across 18 offices
SRG Partnership, a dynamic architecture, interiors and planning firm with studios in Portland, Oregon, and Seattle, Washington, has joined CannonDesign. This merger represents not only a fusion of businesses but a powerhouse union of two firms committed to making a profound difference through design.
Giants 400 | Feb 1, 2024
Top 90 Restaurant Architecture Firms for 2023
Chipman Design Architecture, WD Partners, Greenberg Farrow, GPD Group, and Core States Group top BD+C's ranking of the nation's largest restaurant architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.
Standards | Feb 1, 2024
Prioritizing water quality with the WELL Building Standard
In this edition of Building WELLness, DC WELL Accredited Professionals Hannah Arthur and Alex Kircher highlight an important item of the WELL Building Standard: water.
Luxury Residential | Feb 1, 2024
Luxury 16-story condominium building opens in Chicago
The Chicago office of architecture firm Lamar Johnson Collaborative (LJC) yesterday announced the completion of Embry, a 58-unit luxury condominium building at 21 N. May St. in Chicago’s West Loop.
Industry Research | Jan 31, 2024
ASID identifies 11 design trends coming in 2024
The Trends Outlook Report by the American Society of Interior Designers (ASID) is the first of a three-part outlook series on interior design. This design trends report demonstrates the importance of connection and authenticity.
Museums | Jan 30, 2024
Meier Partners' South Korean museum seeks to create a harmonious relationship between art and nature
For the design of the newly completed Sorol Art Museum in Gangneung, South Korea, Meier Partners drew from Korean Confucianism to achieve a simplicity of form, material, and composition and a harmonious relationship with nature. The museum is scheduled to open on February 14. It is the firm’s first completed project since restructuring as Meier Partners.