Four years ago, The Weitz Company formed a public-private partnership with the city of Des Moines and Polk County, Iowa, for a $101 million hotel/convention center in downtown Des Moines.
Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project. The city and county formed the nonprofit Iowa Events Center Hotel Corp. to create a lease-purchase agreement for the property upon completion.
Weitz, DLR Group (design architect), RDG Planning & Design (AOR), and Raker Rhodes Engineering (SE) employed upfront planning to create parallel paths of construction. They used virtual reality to integrate 3D design models with the 3D construction model. The VR model served as a sales tool for Hilton and Greater Des Moines Convention & Visitors Bureau.
To address the shortage of skilled labor, Weitz, M/P engineer Waldinger, and Pivotek installed 300 bathroom pods that were built off site at Pivotek’s West Chester, Ohio, factory. This saved 11% in labor hours for each prefabbed bathroom and saved 7.5% in total construction costs.
Photo: Phillip Nicolino.
The team used 12 modular components—drain assemblies, PEX risers, aquatherm pressurized piping, framing, and pre-hardware doors. Weitz calculates the use of prefab components saved 3,750 trips to collect materials or remove trash from the job site.
The project was delivered 10 days ahead of schedule. Hilton took occupancy 30 days sooner than planned.+
Building Team — Submitting firm The Weitz Company (developer/design-builder) Owner Polk County, Iowa Hotel consultant Project Management Consultants Design architect DLR Group AOR RDG Planning & Design SE Raker Rhodes Engineering CE Snyder and Associates M/P The Waldinger Corp. EE Baker Electric Interior framing/finish Allied Construction Services
General information — Size 336,000 sf with conference space Cost $101 million Construction time April 2016 to March 2018 Delivery method Design-build lump-sum public-private partnership
Return to the Building Team Awards landing page
Related Stories
Building Team Awards | Jun 8, 2017
Narrow site, broad vision: LA Metro Light Rail Operations & Maintenance Facility
Gold Award: A slender building site had direct implications for the design of this light-rail facility.
Building Team Awards | Jun 8, 2017
Missing link: Denver International Airport and Transit Center
Gold Award: A new mixed-use transit center fulfills Denver’s 28-year plan to improve access to the nation’s fifth-busiest airport.
Building Team Awards | Jun 7, 2017
Rising above adversity: National Museum of African American History and Culture
Gold Award: The Smithsonian Institution’s newest museum is a story of historical and construction resolve.
Building Team Awards | Jun 7, 2017
Justice league: United States courthouse
Gold Award: The Building Team for L.A.’s newest courthouse went way beyond what was expected.
Building Team Awards | Jun 7, 2017
Blurring the lines: University of Chicago North Residential Commons
Gold Award: The University of Chicago’s new Residential Commons is part campus, part community.
Building Team Awards | Jun 7, 2017
Rebuilding to heal: Sandy Hook Elementary School
Gold Award: Community involvement was paramount as Newtown, Conn., replaced the school where a mass shooting occurred.
Building Team Awards | Jun 6, 2017
Nerves of steel: 150 North Riverside
Platinum Award: It took guts for a developer and its Building Team to take on a site others had shunned for most of a century.
Building Team Awards | Jun 1, 2016
Multifamily tower and office building revitalize Philadelphia cathedral
The Philadelphia Episcopal Cathedral capitalizes on hot property to help fund much needed upgrades and programs.
Building Team Awards | Jun 1, 2016
Central utility power plant takes center stage at UC San Diego Jacobs Medical Center
An undulating roof, floor-to-ceiling glass, and façade scheme give visual appeal to a plant that serves the 10-story medical center.
Building Team Awards | May 31, 2016
Gonzaga's new student center is a bustling social hub
Retail mall features, comfortable furniture, and floor-to-ceiling glass add vibrancy to the new John J. Hemmingson Center.