Project completion of BRAC 132, Office of the Chief Army Reserve Building, Ft. Belvoir, Va.

Project completion of BRAC 132, Office of the Chief Army Reserve Building, Ft. Belvoir, Va.

This fast-tracked, design-build project consists of a three-story, 88,470 sf administrative command building housing approximately 430 employees.


By By BD+C Staff | November 16, 2011
Hensel Phelps BRAC-132 Office of the Chief Army Reserve Building
This fast-tracked, design-build project consists of a three-story, 88,470 sf administrative command building housing approximate

Hensel Phelps Construction Co. (Hensel Phelps) recently completed the BRAC 132 -Office of the Chief Army Reserve (OCAR) Building at Fort Belvoir, Va. 

As a result of the 2005 Base Closure and Realignment Commission’s (BRAC) Recommendations, OCAR operations moved from Arlington, Va. to their new facility at Fort Belvoir, Va.

The Chief, Army Reserve (CAR) is responsible for plans, policies and programs affecting all Army Reserve Soldiers, including those who report directly to the Army. OCAR is comprised of specialized groups that advise and support the CAR on a wide variety of issues. 

Despite the aggressive twelve (12) month schedule the Hensel Phelps team achieved the Certificate of Occupancy on budget and ahead of schedule. As a result of Hensel Phelps exemplary safety culture the project was completed with over 95,000 manhours with zero lost time incidences, earning two (2) safety accolades from the U.S. Army Corps of Engineer.

This fast-tracked, design-build project consists of a three-story, 88,470 sf administrative command building housing approximately 430 employees. The OCAR facility was designed to adhere to the Fort Belvoir Master Campus Plan and features precast panels with a light sandblasted limestone-like finish and embedded brick veneer. 

Hensel Phelps, as the design-builder, was teamed with Fentress Architects as the Architect of Record, as well as Draper Aden Associates for civil engineering. The project scope included administrative space, an emergency operations center, sensitive compartmented information facility (SCIF), secure and non-secure conference rooms, video teleconference centers, data processing center, General Officer/senior executive service office suites, storage, and administrative support areas, site work, core and shell, and interior tenant planning.

The OCAR Project is registered as a LEED-NC v2.2 Silver Certification through the U.S. Green Building Council. BD+C

Related Stories

Giants 400 | Aug 28, 2020

2020 Giants 400 Report: Ranking the nation's largest architecture, engineering, and construction firms

The 2020 Giants 400 Report features more than 130 rankings across 25 building sectors and specialty categories.

Architects | Aug 27, 2020

Strategically planning your firm past the COVID-19 pandemic

As AEC firm leaders consider worst-case scenarios and explore possible solutions to surmount them, they learn to become nimble, quick, and ready to pivot as circumstances demand.

Digital Twin | Aug 27, 2020

The Weekly show: Digital twin technology and social equity in the AEC market

The August 27 episode of BD+C's "The Weekly" is available for viewing on demand. 

Architects | Aug 26, 2020

We the People: Four steps for the architecture profession to build unity through design

Architect offers a 4-point manifesto to the design community to work for racial and social justice in the U.S. following the death of George Floyd.

Coronavirus | Aug 25, 2020

Video: 5 building sectors to watch amid COVID-19

RCLCO's Brad Hunter reveals the winners and non-winners of the U.S. real estate market during the coronavirus pandemic.

Architects | Aug 19, 2020

Japan’s Tokyo Toilet project looks to improve the perception of public restrooms

17 toilets throughout Shibuya will be redesigned as part of the project.

Architects | Aug 5, 2020

Final report: BD+C's 2020 Color Trends Report

This special research report from the editors of BD+C explores the leading trends and drivers related to the use of color on commercial, institutional, and multifamily building projects. 

University Buildings | Aug 2, 2020

R&D hubs, modular-built hotels, and an award-winning student center on the August 6 “The Weekly”

R&D hubs, modular-built hotels, and an award-winning student center on the August 6 “The Weekly”

University Buildings | Jul 24, 2020

A hybrid learning approach could redefine higher education

Universities reassess current assets to determine growth strategies.

Coronavirus | Jun 19, 2020

Experts address COVID-19's impact on nursing homes and schools on The Weekly

The June 18 episode of BD+C's "The Weekly" is available for viewing on demand. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021