flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

‘Project first’ philosophy shows team’s commitment to a true IPD on the San Carlos Center

Building Team Awards

‘Project first’ philosophy shows team’s commitment to a true IPD on the San Carlos Center

Skanska and NBBJ join forces with Sutter Health on a medical center project where all three parties share the risk.


By John Caulfield, Senior Editor | April 5, 2015
‘Project first’ philosophy shows team’s commitment to a true IPD

An internal “connecting bridge” (above) brings the outdoors indoors via glass panels, and provides a welcome respite for staff and visitors moving from one area of the hospital to another. Photo: Bruce Damonte

This article first appeared in the April 2015 issue of BD+C.

Five years ago, owner/developer Sutter Health put its planned Palo Alto Medical Foundation San Carlos Center on hold due to the economic downturn. Two years later, a Building Team led by Skanska USA Building got the green light, only to uncover contaminated materials in the brownfield soil. That put the $182 million project in danger of being shelved for a second time.

Such delays might have left Building Team members with little choice but to move on to other projects. But Sutter, architect NBBJ, and general contractor Skanska were closely bound by an agreement they signed jointly in 2006 to produce what, at the time, was one of the first true integrated project delivery (IPD) jobs on the West Coast. That agreement formalized profit and risk sharing and incorporated a Lean delivery system into the project.

When the contamination was discovered, Sutter invested in keeping its team together and busy until construction could finally commence in late May 2012. The 194,000-sf medical center—including full-service radiology, diagnostic imaging, and ambulatory surgery center—was completed last September and opened November 17. Sutter Health expects 140,000 patient visits in its first year.

“Hospitals are among the most complex building types,” says Bill Kline, Vice President and Healthcare Studio Leader with SmithGroupJJR, a Building Team Awards judge. “It takes a smart team to make it look simple, and this elegant composition has been beautifully executed by all.”

During the recession, Sutter engaged its team to prepare a validation study for splitting the project into two phases. Phase one included the construction of the clinic, ambulatory surgery center, parking garage, and a significant portion of the site work. Design and construction allowed for future construction of phase two with minimal loss of value or disruption.

PROJECT SUMMARY
PLATINUM AWARD

Palo Alto Medical Foundation San Carlos Center
San Carlos, Calif.

BUILDING TEAM
Submitting firm: Skanska USA Building (GC/CM)
Owner/developer: Sutter Health
Architect: NBBJ
Structural engineer: KPFF Consulting Engineers
MEP engineer: Mazzetti

GENERAL INFORMATION
Project size: 194,000 sf
Construction cost: $182 million
Construction period: May 2012 to September 2014
Delivery method: Integrated project delivery

During the second postponement, the team educated themselves on the ins and outs of IPD and Lean delivery approach. This kept the project moving through activities such as:

  • Practicing Lean principles such as root cause analysis and reliable promising
  • Establishing principles and values to set the tone for collaboration and innovation
  • Target Value Design
  • Brainstorming design alternatives for optimization
  • Creating mockups of sinks, doors, headers, casework, and light fixtures.

To encourage collaboration and integration, about 40 team members, along with other trade partners, convened in an 8,000-sf “Big Room” for the project’s duration. The members were organized into scope clusters. They ate together and celebrated holidays. Skanska’s Lean Process Director led weekly training sessions and formed a book club, where The Toyota Way and Managing to Lean were dissected.

The team navigated this project by staying focused on key milestones. Along the way it identified prefabrication opportunities to streamline production and minimize waste. The team also used BIM to resolve plumbing, structural, mechanical, and screen wall conflicts.

By creating a Lean A3 dashboard, the team determined the lowest cost for critical and redundant systems. The group generated about 50 A3s, including one for how best to power hands-free faucets. That process led them to specify an eco-powered battery recommended by MEP partner Mazzetti.

During the 2009 delay, the team successfully executed a Lean Target Value Design that reduced the overall project cost while adding an estimated $7 million in value.

Team collaboration led to the decision to prefabricate exterior panels off site and install them with cranes. This method cut production time by 35% and reduced the need for laydown space on the site.

 

Lean building techniques were used to facilitate efficient delivery of this project. While the Building Team waited for construction to commence, Skanska’s Lean Process Director led weekly training sessions that covered such topics as Reliable Promising, S5, Last Planner System weekly work plans, Root Cause Analysis, and Plan Percent Complete. The team also successfully executed a Lean Target Value Design (TVD) process, which lowered the overall project cost while including about $7 million worth of added value. The photo above shows the hospital’s main entrance and imaging waiting room. Photo: Bruce Damonte

 

Research informed the team’s mechanical trade partner to recommend a specialized rooftop cooling unit over a high-capacity chiller. That decision saved nearly $75,000 in piping work.

Involving trade partners in the early stages of the design phase was an important part of building the project. The Building Team took the design review with end users to a higher level by creating mockups in Revit. Lab techs, physicians, and nurses were able to view real-time updates of model labs. The team went through a similar process with stakeholders for the center’s reception desks. Extensive revisions to the set designs were made as a result of this process.

Integrated project delivery is described as a journey. By traveling this road, the team was constantly surprised by its ability to find better ways to do things.

But they also learned that not all team members are prepared for the complexity of IPD’s core tenets. Success depends on the owner leading by example, with a strong commitment to accountability and integration. And every team member must commit to a “project first” approach. 

 

The Palo Alto Medical Foundation San Carlos Center’s design features include a vegetated green roof (left) that helps passively cool the 194,000-sf facility. The roof is also where the project’s mechanical trade partner, working with the medical center’s Building Team, researched and identified a rooftop unit that met the specialized needs of the facility’s surgical center, which saved the project $75,000 in piping and labor. Photo: Bruce Damonte

Related Stories

Giants 400 | Aug 11, 2021

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400

Building Team Awards | Mar 12, 2021

2021 Building Team Awards Entry Information

Only new construction projects completed on or after January 1, 2020 are eligible. Deadline for submissions: May 14, 2021.

Building Team Awards | Mar 12, 2021

Deadline extended for the 2021 Building Team Awards

BD+C's Building Team Awards is the industry's only recognition program to honor projects that achieve excellence in both design/construction and collaboration of the AEC/O team. Deadline for entries: May 14, 2021.

Building Team Awards | Nov 4, 2020

12 projects earn BD+C's 2020 Building Team Awards

The Statue of Liberty Museum, Allianz Field, and the Long Beach Civic Center are three of the projects awarded with BD+C's 2020 Building Team Awards.

Building Team Awards | Nov 3, 2020

Birmingham's haven for the homeless

A coalition of ministries raised millions to build a new home for homeless men in Alabama’s largest city. The Firehouse Shelter wins Honorable Mention in the 2020 Building Team Awards.

Building Team Awards | Nov 2, 2020

It's back to the future for this contractor

Poettker Construction’s new headquarters in rural Breese, Ill., is recognized with a Bronze Award in BD+C’s 2020 Building Team Awards.

Building Team Awards | Nov 2, 2020

Long Beach gets a municipal marvel

The Long Beach Civic Center is honored with a Bronze Award in the 2020 Building Team Awards.  

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021