In popular culture, it hasn’t been cool to “raise the roof” since the late 1990s. But one company is trying to start a new, very literal “raise the roof” trend in the AEC industry.
That company is Upbrella Construction (upbrella.com), and the trend is to build the roof of a structure early in the construction process, and then raise it up as the building progresses.
This alternative process for building tall concrete or steel buildings consists of a mobile permanent roof, a roof lifting mechanism, a protective enclosure, and a high-capacity hoist.
The first step of the Upbrella process begins as soon as the first repeating floor is completed on the foundation. During this phase, an adapted roof that is suitable and equipped to support the construction is installed. The roof can remain on the building throughout construction and after the building is completed if it has the desired geometry. It can also be adapted at the end of the project.
Once the roof is in place, a protective enclosure, consisting of a metal structure covered with a reinforced canvas, is installed up to the parapet and descends to the working gateway. This enclosure keeps the work environment and the workers completely sheltered and allows the project team to better control risks associated with construction.
The floor above is assembled on the previous floor inside the sheltered environment and then positioned using the adapted roof and its hoisting system. The subassembly is finished prior to positioning it to its final height. Once the floor is installed, the entire roof system is raised and work can progress to the next level, where the process is repeated.
See Also: When is wood not really wood?
A large-format carrier replaces conventional elevators and can route all the necessary workers and building materials to the floors. The hoist comprises at least two masts anchored to the structure and remains in place during the entirety of the construction period. The capacity and quantity of the carriers can be adjusted to the size and scope of the project.
The adaptable roof and associated protective enclosure allow for finishing touches and occupancy of the lower floors faster. If sales stagnate, construction can be suspended while the completed floors can become and remain occupied. Then, if sales or demand increase, construction can quickly proceed once more.
Other benefits the company cites: reduced insurance costs; the elimination of lost days due to inclement weather; the reduction of overhead and high winter costs; an increased energy efficiency for the building site; and the reduction of public occupancy costs.
Related Stories
3D Printing | Sep 13, 2024
Swiss researchers develop robotic additive manufacturing method that uses earth-based materials—and not cement
Researchers at ETH Zurich, a university in Switzerland, have developed a new robotic additive manufacturing method to help make the construction industry more sustainable. Unlike concrete 3D printing, the process does not require cement.
Smart Buildings | Jul 25, 2024
A Swiss startup devises an intelligent photovoltaic façade that tracks and moves with the sun
Zurich Soft Robotics says Solskin can reduce building energy consumption by up to 80% while producing up to 40% more electricity than comparable façade systems.
Great Solutions | Jul 23, 2024
41 Great Solutions for architects, engineers, and contractors
AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.
Building Technology | Jun 18, 2024
Could ‘smart’ building facades heat and cool buildings?
A promising research project looks at the possibilities for thermoelectric systems to thermally condition buildings, writes Mahsa Farid Mohajer, Sustainable Building Analyst with Stantec.
75 Top Building Products | Apr 22, 2024
Enter today! BD+C's 75 Top Building Products for 2024
BD+C editors are now accepting submissions for the annual 75 Top Building Products awards. The winners will be featured in the November/December 2024 issue of Building Design+Construction.
AEC Tech | Feb 20, 2024
AI for construction: What kind of tool can artificial intelligence become for AEC teams?
Avoiding the hype and gathering good data are half the battle toward making artificial intelligence tools useful for performing design, operational, and jobsite tasks.
Sustainability | Nov 1, 2023
Researchers create building air leakage detection system using a camera in real time
Researchers at the U.S. Department of Energy’s Oak Ridge National Laboratory have developed a system that uses a camera to detect air leakage from buildings in real time.
Resiliency | Aug 7, 2023
Creative ways cities are seeking to beat urban heat gain
As temperatures in many areas hit record highs this summer, cities around the world are turning to creative solutions to cope with the heat. Here are several creative ways cities are seeking to beat urban heat gain.
AEC Innovators | Jun 15, 2023
Rogers-O'Brien Construction pilots wearables to reduce heat-related injuries on jobsites
Rogers-O'Brien Construction (RO) has launched a pilot program utilizing SafeGuard, a safety-as-a-service platform for real-time health and safety risk assessment. Non-invasive wearables connected to SafeGuard continuously monitor personnel to prevent heat exhaustion on jobsites, reducing the risk of related injuries. RO is the first general contractor to pilot this program.
Office Buildings | May 15, 2023
Sixteen-story office tower will use 40% less energy than an average NYC office building
This month marks the completion of a new 16-story office tower that is being promoted as New York City’s most sustainable office structure. That boast is backed by an innovative HVAC system that features geothermal wells, dedicated outdoor air system (DOAS) units, radiant heating and cooling, and a sophisticated control system to ensure that the elements work optimally together.