December 14, 2012. A 20-year-old gunman named Adam Lanza invaded the Sandy Hook Elementary School in Connecticut and fatally shot 20 children, ages six and seven, and six adult staff members. Following that horrific event, the town of Newtown decided to build a new, 87,000-sf PreK-4 school, which required extreme sensitivity by the Building Team that worked hand and hand with the town on every aspect of the building’s planning, design, and construction.
On the recommendation of owner’s rep, STV|DPM, the school’s Public Building and Site Commission assembled the project team before planning began. The architects collaborated with more than 50 participants of the project’s programming committee. The Building Team also worked with teachers and parents to develop workshops to inform young children about the project’s design, engineering, and construction.
The Building Team went to great lengths to assuage a still-grieving community during the design and construction for this school. That included training sessions for subcontractors to reinforce the sensitive nature of this project. Robert Benson Photography.
To respect the community, the construction process closed off the site to gawkers, limited photography, and accommodated project tours for school staff members, families of survivors, and teachers. Construction manager Consigli hosted two subcontractor events to raise awareness among the trades about the project’s requirements.
The new school’s striking design emphasizes outdoor activities. Footbridges recall the geology of Newtown’s watercourses. The building’s largest central courtyard—overlooked by two small breakout spaces imagined as tree houses—is landscaped with two amphitheater-style classroom spaces for outdoor learning. The building’s light-filled main lobby includes a two-story wall of clear and colored glass and overhead corridor bridge, with nearby artwork evoking nature.
This finished product emphasizes outdoor activities and includes an overhead corridor bridge. Robert Benson Photography.
Building Team – Submitting firm, architect Svigals + Partners Owner Town of Newtown, Conn. Interior architect Lynn Brotman Interior Design Structural engineer Michael Horton Associates MEP BVH Integrated Services CM Consigli Constrution Owner’s representative STV|DPM
General Information – Size 87,160 sf Cost $39.8 million Construction time October 2014 to July 2016 Delivery method CM at risk
Related Stories
Architects | Jan 18, 2016
EHDD’s Monterey Bay Aquarium wins AIA Twenty-five Year Award
The aquarium set new technical standards for the building type, which still influence today, such as the flow-through seawater-based heat pump system, naturalistic exhibitions, and corrosion protection.
Building Team Awards | Apr 10, 2015
14 projects that push AEC teaming to the limits
From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.
Building Team Awards | Apr 10, 2015
Prefab saves the day for Denver hospital
Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.
Building Team Awards | Apr 10, 2015
Anaheim’s soaring intermodal hub
Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.
Building Team Awards | Apr 10, 2015
Virtual collaboration helps complete a hospital in 24 months
PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.
Building Team Awards | Apr 10, 2015
New arts venue reinvigorates Virginia Tech's campus
The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.
Building Team Awards | Apr 9, 2015
Multifaced fitness center becomes campus landmark
A sloped running track and open-concept design put this Building Team to the test.
Building Team Awards | Apr 9, 2015
Nation's first LEED-certified bus depot
A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.
Building Team Awards | Apr 9, 2015
Setting the bar for port-of-entry design
Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.
Building Team Awards | Apr 9, 2015
Big D’s billion-dollar baby: New Parkland Hospital Tops the Chart | BD+C
Dallas’s new $1.27 billion public hospital preserves an important civic anchor, Texas-style.