The cathedral, dedicated in 1879, sorely needed work.


By BD+C Staff | November 16, 2016

The Building Team for St. Patrick’s Cathedral had the National Historic Landmark ready to greet Pope Francis on September 24, 2015, three months ahead of schedule. © John Baer / Building Images Photography

For sheer massiveness, the restoration of New York’s St. Patrick’s Cathedral is hard to beat. It took Structure Tone (CM) seven months just to build the 335-foot-high scaffolding—all the while safeguarding an average 15,000 visitors a day.

The cathedral, dedicated in 1879, sorely needed work. Using BIM 360 Field to track its progress, the Building Team made 300,000 repairs. Thirty-seven hundred stained glass panels were restored; a new, invisible venting system to create air movement was installed to protect the glass. A 200-foot undercroft with eight tunnels was renovated. The two rusted-out main doors, weighing 8,800 pounds each, were conserved using a titanium let for structural support and a coating system derived from the oil industry to prevent future condensation.

The team designed a fire-suppressant system like one used in submarines that employs a nitrogen mist to propel a much smaller amount of water than a conventional system. Structure Tone used a hand-powered trolley to install the fire system in the attic, saving $1.3 million.

 

The 335-foot scaffolding that Structure Tone erected over a seven-month period. © John Baer / Building Images Photography.

 

 

PROJECT SUMMARY 

 

Silver Award Winner | New York, N.Y.

Building Team: Structure Tone (submitting firm, CM); Trustees for the Cathedral of St. Patrick (owner); Zubatkin (owner’s representative); Murphy Burnham & Buttrick Architects (designer); Silman Associates (SE); Landmark Facilities Group (MEP); Langan Engineering, GB Geotechnics USA (geotechnics/surveying); Robin Key Landscape Architecture; Building Conservation Associates; and William Dailey Associates (codes).

Details: 160,000 sf. Construction cost: Confidential. Construction time: March 2012 to September 2015. Delivery method: CM at risk.

Related Stories

Reconstruction Awards | Dec 19, 2019

BD+C's 2019 Reconstruction Award Winners

The Museum at the Gateway Arch, the Senate of Canada building, and Google, Spruce Goose are just a few of the projects recognized with 2019 Reconstruction Awards.

Reconstruction Awards | Dec 13, 2019

A manse makeover: The Dahod Family Alumni Center at the Castle

A 1915 castle on BU’s campus is carefully restored for alumni events.

Reconstruction Awards | Dec 13, 2019

Community effort: Rose Collaborative

This post-Katrina project has become a citadel of the arts and education in the Crescent City.

Reconstruction Awards | Dec 12, 2019

New flight pattern: Google, Spruce Goose

The hangar that once housed the Spruce Goose is adapted to meet a tech giant’s workplace needs.

Reconstruction Awards | Dec 10, 2019

Enter the world of deep time: David H. Koch Hall of Fossils

The new enclosed FossiLab gives visitors a glimpse into the exacting work of Smithsonian scientists and preservationists.

Reconstruction Awards | Dec 6, 2019

TWA Hotel at JFK International Airport: Home away from home

A dormant, 1960s-era flight center is converted into a snazzy hotel and conference facility.

Reconstruction Awards | Dec 6, 2019

Columbus Metro Library Hilliard Branch

Senior living clubhouse becomes a modern library in central Ohio.

Reconstruction Awards | Dec 5, 2019

The 428: St. Paul's office corner

A long-forgotten five-and-dime store becomes a  speculative office property in Minnesota’s capital.

Reconstruction Awards | Dec 4, 2019

The squeeze is on: The Revolution Hotel

Once a 1950s-era YWCA, The Revolution is now a hip new hotel in The Hub.

Reconstruction Awards | Dec 2, 2019

Hudson Commons: Over the top

A project team converts a 1960s industrial structure into a Class A office gem.

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021