Rank Company 2012 Reconstruction Revenue ($)
1 URS Corp. $292,591,405
2 STV $125,755,000
3 Wiss, Janney, Elstner Associates $72,500,000
4 Science Applications International Corp. $57,788,875
5 Middough $54,100,000
6 Dewberry $53,086,519
7 SSOE Group $52,518,417
8 Thornton Tomasetti $50,250,524
9 Syska Hennessy Group $49,258,501
10 AKF Group $45,000,000
11 Simpson Gumpertz & Heger $43,800,000
12 Buro Happold Consulting Engineers $38,844,000
13 Henderson Engineers $33,000,000
14 TTG $30,728,610
15 Environmental Systems Design $28,211,025
16 RDK Engineers $26,520,850
17 Smith Seckman Reid $21,167,725
18 H&A Architects & Engineers $20,982,548
19 Rolf Jensen & Associates $20,800,000
20 TLC Engineering for Architecture $20,577,575
21 RMF Engineering Design $18,698,000
22 Degenkolb Engineers $18,338,904
23 Ross & Baruzzini $17,765,787
24 Interface Engineering $16,895,439
25 Michael Baker Jr. $16,480,000
26 Bard, Rao + Athanas Consulting Engineers $15,500,000
27 Newcomb & Boyd $14,428,325
28 Coffman Engineers $14,200,000
29 KCI Technologies $13,432,000
30 ThermalTech Engineering $12,900,000
31 Affiliated Engineers $12,660,000
32 Glumac $12,633,000
33 Dunham Associates $12,500,000
34 Clark Nexsen $12,454,770
35 KPFF Consulting Engineers $11,000,000
36 Walker Parking Consultants $10,939,513
37 H.F. Lenz $10,796,600
38 Bergmann Associates $10,159,200
39 CCRD Partners $10,100,000
40 Allen & Shariff $10,000,000
41 Bridgers & Paxton Consulting Engineers $9,277,886
42 Merrick & Co. $9,000,000
43 Heapy Engineering $8,846,776
44 Sparling $8,518,471
45 Hixson Architecture, Engineering, Interiors $8,500,000
46 M-E Engineers $8,000,000
47 M/E Engineering $7,940,450
48 KLH Engineers $7,036,415
49 Peter Basso Associates $6,609,600
50 Bala Consulting Engineers $6,572,000
51 CTLGroup $5,500,000
52 Paulus, Sokolowski and Sartor $5,200,000
53 P2S Engineering $4,717,436
54 GRAEF $4,620,000
55 Rist-Frost-Shumway Engineering $4,300,000
56 Brinjac Engineering $4,018,072
57 Davis, Bowen & Friedel $3,616,428
58 Wallace Engineering $3,500,000
59 Kamm Consulting $3,313,597
60 OLA Consulting Engineers $3,200,000
61 Primera Engineers $2,990,000
62 Magnusson Klemencic Associates $2,719,958
63 FBA Engineering $2,160,000
64 Haynes Whaley Associates $639,876
65 Walter P Moore $320,431

 

Back to the Reconstruction Giants article

 

Read BD+C's full Giants 300 Report

Related Stories

| Dec 17, 2010

Luxury condos built for privacy

A new luxury condominium tower in Los Angeles, The Carlyle has 24 floors with 78 units. Each of the four units on each floor has a private elevator foyer. The top three floors house six 5,000-sf penthouses that offer residents both indoor and outdoor living space. KMD Architects designed the 310,000-sf structure, and Elad Properties was project developer.

| Dec 17, 2010

Subway entrance designed to exude Hollywood charm

The Hollywood/Vine Metro portal and public plaza in Los Angeles provides an entrance to the Red Line subway and the W Hollywood Hotel. Local architect Rios Clementi Hale Studio designed the portal and plaza to flow with the landmark theaters and plazas that surround it.

| Dec 17, 2010

New engineering building goes for net-zero energy

A new $90 million, 250,000-sf classroom and laboratory facility with a 450-seat auditorium for the College of Electrical and Computer Engineering at the University of Illinois at Urbana/Champaign is aiming for LEED Platinum.

| Dec 17, 2010

Vietnam business center will combine office and residential space

The 300,000-sm VietinBank Business Center in Hanoi, Vietnam, designed by Foster + Partners, will have two commercial towers: the first, a 68-story, 362-meter office tower for the international headquarters of VietinBank; the second, a five-star hotel, spa, and serviced apartments. A seven-story podium with conference facilities, retail space, restaurants, and rooftop garden will connect the two towers. Eco-friendly features include using recycled heat from the center’s power plant to provide hot water, and installing water features and plants to improve indoor air quality. Turner Construction Co. is the general contractor.

| Dec 17, 2010

Toronto church converted for condos and shopping

Reserve Properties is transforming a 20th-century church into Bellefair Kew Beach Residences, a residential/retail complex in The Beach neighborhood of Toronto. Local architecture firm RAWdesign adapted the late Gothic-style church into a five-story condominium with 23 one- and two-bedroom units, including two-story penthouse suites. Six three-story townhouses also will be incorporated. The project will afford residents views of nearby Kew Gardens and Lake Ontario. One façade of the church was updated for retail shops.

| Dec 17, 2010

ARRA-funded Navy hospital aims for LEED Gold

The team of Clark/McCarthy, HKS Architects, and Wingler & Sharp are collaborating on the design of a new naval hospital at Camp Pendleton in Southern California. The $451 million project is the largest so far awarded by the U.S. Navy under the American Recovery and Reinvestment Act. The 500,000-sf, 67-bed hospital, to be located on a 70-acre site, will include facilities for emergency and primary care, specialty care clinics, surgery, and intensive care. The Building Team is targeting LEED Gold.

| Dec 17, 2010

Arizona outpatient cancer center to light a ‘lantern of hope’

Construction of the Banner MD Anderson Cancer Center in Gilbert, Ariz., is under way. Located on the Banner Gateway Medical Center campus near Phoenix, the three-story, 131,000-sf outpatient facility will house radiation oncology, outpatient imaging, multi-specialty clinics, infusion therapy, and various support services. Cannon Design incorporated a signature architectural feature called the “lantern of hope” for the $90 million facility.

| Dec 17, 2010

Cladding Do’s and Don’ts

A veteran structural engineer offers expert advice on how to avoid problems with stone cladding and glass/aluminum cladding systems.

| Dec 17, 2010

5 Tips on Building with SIPs

Structural insulated panels are gaining the attention of Building Teams interested in achieving high-performance building envelopes in commercial, industrial, and institutional projects.

| Dec 17, 2010

How to Win More University Projects

University architects representing four prominent institutions of higher learning tell how your firm can get the inside track on major projects.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021