Reconstruction work is alive and kicking for many AEC firms. “Higher education is huge for us, and that sector just stopped spending when the recession hit,” recalls Mark DiNapoli, President and General Manager (Northeast Region), Suffolk Construction. “Now we’re seeing projects starting to take off.” Healthcare, science and technology, and commercial (office/retail/hospitality) are also coming back in the Northeast, he says, as clients “think about how to transform their existing buildings.”
“The reconstruction market has gotten much busier,” notes Karl Anoushian, Senior Vice President and Director of Preconstruction Services at Structure Tone. “The smart landlords, the financially stable ones, have timed the market and are pulling the trigger on deals.” The strategy: repositioning—reskinning exteriors to make them pop, sprucing up lobbies and core bathrooms, upgrading the lighting, air-conditioning, and elevators.
SCROLL DOWN FOR GIANTS 300 RECONSTRUCTION FIRM RANKINGS
Mary Miano-Sleeper, Vice President/Director of Corporate Development in the Dallas office of PageSoutherlandPage, says the growth in the rehabilitation of “tired spaces” in Class B and B+ buildings is “due to the availability of capital that was on the sidelines waiting for distressed assets to be vetted and put back into play.”
Wight & Co. has been getting “a good share of our work out of renovations,” notably for college and K-12 structures of the ’60s and ’70s, says Ken Osmun, PE, LEED BD+C, DBIA, Group President, Construction. The work often entails adding air-conditioning, bringing buildings up to code, and restoring their original appearance.
“Most of the activity we are seeing is in cities immediately adjacent to large cities,” says Mathew Dougherty, PE, Vice President, McShane Construction. High-density, mixed-use urban infill developments with substantial upgrading and direct access to public transportation remain “highly popular with both tenants and developers,” he says.
MAKING THE DEALS WORK
AEC firms have to help clients capture available funds, such as historic tax credits, says Suffolk’s DiNapoli. “We provide detailed cost information every month so that they can collect their funds,” he says. “We’re much more involved at an early stage on these projects, to help with financing.”
In older cities like Boston, infrastructure usually has to be upgraded when a building is renovated. “The utilities are requiring transformer vaults inside the buildings instead of pad-mounted transformers,” says DiNapoli. That’s a hidden cost the client has to absorb, but it’s necessary to help prevent brownouts.
AEC firms are making the business case for reconstruction. Wight & Co. recently completed the renovation of a 70-year-old college residence hall that came in at one-third the cost of new construction. “Our clients have limited budgets, so renovation can help them manage their resources,” says Osmun.
Structure Tone’s global procurement process provides dollar savings and accelerated product delivery for clients. The firm also uses its contractor-controlled insurance program and subcontractor qualification process to hold down costs. “We’re big in cost segregation, which can have real tax advantages for the owner,” says Anoushian, whose firm does 800-900 reconstruction projects a year. “We try to offer the client the best savings over the life of the project.”
USING TECHNOLOGY WISELY
For a 420-bed hostel in Boston, Suffolk laser-scanned the interiors of all six floors of a landmark building and created a Revit-based BIM model that informed the design. “In reconstruction, the unknown is more important than the known,” says DiNapoli. “We need to provide clients with as much information as possible, set budgets with appropriate contingencies for unknowns, and plan, plan, plan.”
“We’re doing animated flythroughs on our renovation jobs, using Revit and 3D, to articulate to clients what they’re actually going to get,” says Osmun. “There may be piping that will affect actual ceiling height, or a column that can’t be removed. This helps establish client expectations more realistically, before we start the work.”
Structure Tone routinely uses geothermal and ice-storage technology on office renovations. “Major financial institutions have huge data demands, and you have to keep their data centers at 60 degrees” [Fahrenheit], says Anoushian.
STEADY GROWTH, BOOST IN SUBCONTRACTOR COSTS
“The second half of 2012 will continue to show slow but steady growth in reconstruction,” says PageSoutherlandPage’s Miano-Sleeper.
“After dropping their fees just to retain their people, subcontractors are trying to make a recovery,” says Suffolk’s DiNapoli. “We’re definitely seeing price escalation from subs, 6-8%, and it’s been a little startling for our clients—and for us.”
Wight & Co.’s Osmun says, “Our estimators are saying it’s a 2% increase overall in the last year. We have to sharpen our pencils more than ever. We have to be smart, and we can’t make a mistake in the field.”
“Firms need to develop ways to meet client needs for remodels and expansions,” says D. Bruce Henley, AIA, LEED AP, DBIA, Principal/Office Director with Dewberry. “It will mean survival for many.” +
TOP 25 RECONSTRUCTION SECTOR ARCHITECTURE FIRMS
Rank | Company | 2011 Reconstruction Revenue ($) |
1 | HOK | 133,348,629 |
2 | Cannon Design | 93,000,000 |
3 | EYP Architecture & Engineering | 48,332,935 |
4 | SmithGroupJJR | 44,275,000 |
5 | ZGF Architects | 38,566,000 |
6 | Gresham, Smith and Partners | 27,662,548 |
7 | PageSoutherlandPage | 27,585,000 |
8 | Perkowitz+Ruth Architects | 26,910,000 |
9 | RSP Architects | 26,190,000 |
10 | EwingCole | 25,500,000 |
11 | Corgan Associates | 23,850,000 |
12 | CTA Architects Engineers | 23,276,400 |
13 | Beyer Blinder Belle Architects & Planners | 22,700,000 |
14 | FRCH Design Worldwide | 21,690,000 |
15 | RBB Architects | 20,370,000 |
16 | S/L/A/M Collaborative, The | 17,764,184 |
17 | Reynolds, Smith and Hills | 16,800,000 |
18 | BSA LifeStructures | 15,860,773 |
19 | Albert Kahn Family of Companies | 14,000,000 |
20 | Swanke Hayden Connell Architects | 12,500,000 |
21 | Fletcher Thompson | 12,300,000 |
22 | Baskervill | 11,412,700 |
23 | CASCO Diversified Corp. | 11,000,000 |
24 | Wight & Co. | 10,027,500 |
25 | Ennead Architects | 9,944,000 |
TOP 25 RECONSTRUCTION SECTOR ENGINEERING FIRMS
Rank | Company | 2011 Reconstruction Revenue ($) |
1 | URS Corp. | 1,945,200,000 |
2 | Jacobs | 1,810,600,000 |
3 | STV | 275,000,000 |
4 | Stantec | 235,000,000 |
5 | Wiss, Janney, Elstner Associates | 64,080,000 |
6 | Dewberry | 63,384,145 |
7 | Middough | 51,750,000 |
8 | Simpson Gumpertz & Heger | 41,490,000 |
9 | Syska Hennessy Group | 40,121,834 |
10 | Thornton Tomasetti | 31,708,579 |
11 | Henderson Engineers | 31,000,000 |
12 | Eaton Energy Solutions | 30,374,875 |
13 | Sebesta Blomberg | 30,271,508 |
14 | Science Applications International Corp. | 28,696,000 |
15 | Clark Nexsen | 20,407,051 |
16 | RMF Engineering | 20,403,000 |
17 | H&A Architects & Engineers | 18,750,730 |
18 | Rolf Jensen & Associates | 16,000,000 |
19 | Michael Baker Jr., Inc | 15,184,500 |
20 | Bard, Rao + Athanas Consulting Engineers | 15,100,000 |
21 | Dunham Associates | 13,500,000 |
22 | TLC Engineering for Architecture | 13,463,203 |
23 | Degenkolb Engineers | 11,920,636 |
24 | Henneman Engineering | 10,800,000 |
25 | Bridgers & Paxton Consulting Engineers | 9,707,771 |
TOP 25 RECONSTRUCTION SECTOR CONSTRUCTION FIRMS
Rank | Company | 2011 Reconstruction Revenue ($) |
1 | Gilbane Building Co. | 2,149,930,000 |
2 | URS Corp. | 1,945,200,000 |
3 | Jacobs | 1,810,600,000 |
4 | Structure Tone | 1,699,180,000 |
5 | Turner Corporation, The | 1,476,646,000 |
6 | Shawmut Design and Construction | 465,000,000 |
7 | Holder Construction | 350,000,000 |
8 | Swinerton | 326,929,500 |
9 | Suffolk Construction | 238,619,421 |
10 | Walbridge | 216,975,000 |
11 | Ryan Companies US | 210,943,550 |
12 | Power Construction | 207,000,000 |
13 | Weitz Co., The | 179,880,756 |
14 | Walsh Group, The | 161,205,219 |
15 | W. M. Jordan Co. | 137,277,920 |
16 | O’Neil Industries/W.E. O’Neil | 130,140,000 |
17 | Bernards | 113,894,000 |
18 | KBE Building Corp. | 102,083,867 |
19 | EMJ Corp. | 100,905,397 |
20 | Robins & Morton | 89,106,900 |
21 | Clayco | 82,000,000 |
22 | Layton Construction | 75,200,000 |
23 | Hunt Construction Group | 75,000,000 |
24 | Kitchell | 71,070,000 |
25 | Doster Construction | 66,202,115 |
Related Stories
| Feb 11, 2011
RS Means Cost Comparison Chart: Office Buildings
This month's RS Means Cost Comparison Chart focuses on office building construction.
| Feb 11, 2011
Sustainable features on the bill for dual-building performing arts center at Soka University of America
The $73 million Soka University of America’s new performing arts center and academic complex recently opened on the school’s Aliso Viejo, Calif., campus. McCarthy Building Companies and Zimmer Gunsul Frasca Architects collaborated on the two-building project. One is a three-story, 47,836-sf facility with a grand reception lobby, a 1,200-seat auditorium, and supports spaces. The other is a four-story, 48,974-sf facility with 11 classrooms, 29 faculty offices, a 150-seat black box theater, rehearsal/dance studio, and support spaces. The project, which has a green roof, solar panels, operable windows, and sun-shading devices, is going for LEED Silver.
| Feb 11, 2011
BIM-enabled Texas church complex can broadcast services in high-def
After two years of design and construction, members of the Gateway Church in Southland, Texas, were able to attend services in their new 4,000-seat facility in late 2010. Located on a 180-acre site, the 205,000-sf complex has six auditoriums, including a massive 200,000-sf Worship Center, complete with catwalks, top-end audio and video system, and high-definition broadcast capabilities. BIM played a significant role in the building’s design and construction. Balfour Beatty Construction and Beck Architecture formed the nucleus of the Building Team.
| Feb 11, 2011
Kentucky’s first green adaptive reuse project earns Platinum
(FER) studio, Inglewood, Calif., converted a 115-year-old former dry goods store in Louisville, Ky., into a 10,175-sf mixed-use commercial building earned LEED Platinum and holds the distinction of being the state’s first adaptive reuse project to earn any LEED rating. The facility, located in the East Market District, houses a gallery, event space, offices, conference space, and a restaurant. Sustainable elements that helped the building reach its top LEED rating include xeriscaping, a green roof, rainwater collection and reuse, 12 geothermal wells, 81 solar panels, a 1,100-gallon ice storage system (off-grid energy efficiency is 68%) and the reuse and recycling of construction materials. Local firm Peters Construction served as GC.
| Feb 11, 2011
Former Richardson Romanesque hotel now houses books, not beds
The Piqua (Ohio) Public Library was once a late 19th-century hotel that sat vacant and deteriorating for years before a $12.3 million adaptive reuse project revitalized the 1891 building. The design team of PSA-Dewberry, MKC Associates, and historic preservation specialist Jeff Wray Associates collaborated on the restoration of the 80,000-sf Richardson Romanesque building, once known as the Fort Piqua Hotel. The team restored a mezzanine above the lobby and repaired historic windows, skylight, massive fireplace, and other historic details. The basement, with its low ceiling and stacked stone walls, was turned into a castle-like children’s center. The Piqua Historical Museum is also located within the building.
| Feb 11, 2011
Justice center on Fall River harbor serves up daylight, sustainable elements, including eucalyptus millwork
Located on historic South Main Street in Fall River, Mass., the Fall River Justice Center opened last fall to serve as the city’s Superior and District Courts building. The $85 million facility was designed by Boston-based Finegold Alexander + Associates Inc., with Dimeo Construction as CM and Arup as MEP. The 154,000-sf courthouse contains nine courtrooms, a law library, and a detention area. Most of the floors have the same ceiling height, which will makes them easier to reconfigure in the future as space needs change. Designed to achieve LEED Silver, the facility’s elliptical design offers abundant natural daylight and views of the harbor. Renewable eucalyptus millwork is one of the sustainable features.
| Feb 11, 2011
Research facility separates but also connects lab spaces
California State University, Northridge, consolidated its graduate and undergraduate biology and mathematics programs into one 90,000-sf research facility. Architect of record Cannon Design worked on the new Chaparral Hall, creating a four-story facility with two distinct spaces that separate research and teaching areas; these are linked by faculty offices to create collaborative spaces. The building houses wet research, teaching, and computational research labs, a 5,000-sf vivarium, classrooms, and administrative offices. A four-story outdoor lobby and plaza and an outdoor staircase provide orientation. A covered walkway links the new facility with the existing science complex. Saiful/Bouquet served as structural engineer, Bard, Rao + Athanas Consulting Engineers served as MEP, and Research Facilities Design was laboratory consultant.
| Feb 11, 2011
A feast of dining options at University of Colorado community center, but hold the buffalo stew
The University of Colorado, Boulder, cooked up something different with its new $84.4 million Center for Community building, whose 900-seat foodservice area consists of 12 micro-restaurants, each with its own food options and décor. Centerbrook Architects of Connecticut collaborated with Denver’s Davis Partnership Architects and foodservice designer Baker Group of Grand Rapids, Mich., on the 323,000-sf facility, which also includes space for a career center, international education, and counseling and psychological services. Exterior walls of rough-hewn, variegated sandstone and a terra cotta roof help the new facility blend with existing campus buildings. Target: LEED Gold.
| Feb 11, 2011
Chicago high-rise mixes condos with classrooms for Art Institute students
The Legacy at Millennium Park is a 72-story, mixed-use complex that rises high above Chicago’s Michigan Avenue. The glass tower, designed by Solomon Cordwell Buenz, is mostly residential, but also includes 41,000 sf of classroom space for the School of the Art Institute of Chicago and another 7,400 sf of retail space. The building’s 355 one-, two-, three-, and four-bedroom condominiums range from 875 sf to 9,300 sf, and there are seven levels of parking. Sky patios on the 15th, 42nd, and 60th floors give owners outdoor access and views of Lake Michigan.
| Feb 11, 2011
Iowa surgery center addresses both inpatient and outpatient care
The 12,000-person community of Carroll, Iowa, has a new $28 million surgery center to provide both inpatient and outpatient care. Minneapolis-based healthcare design firm Horty Elving headed up the four-story, 120,000-sf project for St. Anthony’s Regional Hospital. The center’s layout is based on a circular process flow, and includes four 800-sf operating rooms with poured rubber floors to reduce leg fatigue for surgeons and support staff, two substerile rooms between each pair of operating rooms, and two endoscopy rooms adjacent to the outpatient prep and recovery rooms. Recovery rooms are clustered in groups of four. The large family lounge (left) has expansive windows with views of the countryside, and television monitors that display coded information on patient status so loved ones can follow a patient’s progress.