San Francisco has long been known as a center for culture and the performing arts. Showcased by its War Memorial Opera House, considered the last Beaux Arts building constructed in the United States, this legacy continued with construction of the adjoining Louise M. Davies Symphony Hall. Opened in 1980 and renovated in 1992, its modern design was a collaboration of architects and acoustical engineers working in concert to create an intimate environment to enhance the music of the San Francisco Symphony and the beauty of the structure itself.
Recently, the San Francisco Public Utilities Commission (SFPUC) determined that installing a photovoltaic (PV) solar system on Davies Symphony Hall would benefit the people of San Francisco. The SFPUC retained engineering consultant AEPC of San Ramon, Calif., to design the PV solar system for the 25,000-sf roof.
In addition to AEPC, the project team for the roof revitalization and PV solar system installation included Technical Roof Services (TRS) of Concord, Calif., and Fidelity Roof Company of Oakland, a Duro-Last® Certified Elite Contractor.
Moisture Issues Necessitated New Game Plan
Initially, the installation of a rooftop solar energy system seemed to be straightforward. However, upon further inspection, significant moisture issues were discovered in the underlying roof insulation, contributing to deteriorating conditions in the 14-year-old tar and gravel roof.
Davies Symphony Hall. Photo: Duro-Last Roofing
To further assess the roof’s condition, AEPC brought in Technical Roof Services (TRS) to conduct a more thorough evaluation. According to Venk Mani of AEPC, “We knew the roof had some leaks and wanted to correct any problem areas before the solar panels were installed. Our goal was to ensure that the roof could last the life of the solar array, or a minimum of 25 years.”
Presenting the Options to Ready Roof for PV Solar
Dregger presented the two available options to the SFPUC: either tear off the current roof and install a new one, or overlay the existing roof with a new membrane. After careful consideration, the SFPUC opted to re-cover the existing roof since replacing the old roof with a new one would take longer and interfere with the symphony’s rehearsal and performance schedule. After evaluating the available membrane alternatives, Dregger recommended a white 60 mil thick thermoplastic PVC roof system from Duro-Last Roofing.
Material Prefabrication Expedited Installation
Prefabrication was another advantage of the Duro-Last Roofing System. The membrane was prefabricated into 22 foot wide rolls, reducing the application time and on-site welding. In addition the penetration flashings, parapet wall membrane, membrane curbs, solar hold down boots and other related roof materials were all custom fabricated at the factory. This not only assured installation accuracy at changes in plane on the roof, such as projections, curbs, drains, perimeters and abutting walls, but of equal importance was Fidelity Roof Company’s ability to expedite the installation process and meet critical deadlines.
Location: San Francisco
Client: San Francisco Public Utilities Commission
Contractor: Fidelity Roof Company
To read the entire article, visit www.duro-last.com/marketing.
For more information:
Phone number: 800-248-0280
Fax number: 800.432.9331
E-mail: jbruzews@duro-last.com
Website: www.duro-last.com
Related Stories
Sponsored | Roofing | Aug 30, 2019
A New Twist on TPO: Firestone UltraPly™ TPO Flex Adhered
The most flexible TPO on the market* makes complex jobs easier.
Sponsored | Roofing | Aug 17, 2018
Owens Corning® FOAMULAR® XPS solution brings game-changing solution to Mercedes-Benz Stadium
Bill Johnson, design principal for HOK, brought together experts from across the country to help realize the revolutionary engineering, design, and functionality envisioned for the $1.5 billion Mercedes-Benz Stadium project.
Sponsored | Roofing | Jul 24, 2018
Metal roofs take the residential market by storm
As metal roofing soars in popularity, so do the aesthetic options.
Sponsored | Roofing | Jun 22, 2018
U.S. Coast Guard Headquarters - vegetative roof assembly, Washington, D.C.
A cross-functional team collaborated throughout the three-phased VRA construction.
Sponsored | Roofing | Mar 21, 2018
Renovation at Cincinnati Music Hall includes new automatic smoke vents for life safety
Workers tackled a 16-month, $143-million project at Cincinnati Music Hall, and finished the project last October.
Codes and Standards | Nov 16, 2017
White roofing isn’t always the best choice
Adverse effects include heat reflection onto nearby walls.
Green | Sep 12, 2017
Brooklyn’s Windsor Terrace Library gets a living roof
The roof was funded through a process that allows local residents to decide how City capital dollars are spent in their neighborhoods.
Building Enclosure Systems | Jul 26, 2017
Balcony and roof railings and the code: Maintain, repair, or replace? [AIA course]
Lacking familiarity with current requirements, some owners or managers complete a roof or balcony rehabilitation, only to learn after the fact that they need to tear noncompliant railings out of their new roof or terrace and install new ones.
Roofing | Jul 17, 2017
EclipseEdge eases installation of raised roof edges, gravel stops, and full coping caps
The EclipseEdge edge metal profile uses a two-part design with a base and a top cover to eliminate steps often required in traditional installations.