Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

| Dec 15, 2011

Dayton, Ohio schools saving $2.6 million annually by building to LEED

On average, green schools save about $100,000 a year on operating costs, including energy and water savings.

| Dec 15, 2011

Building to LEED standards can pose new risks for construction workers

Workers on these projects suffer a 24% increase in falls to lower levels during roof work, which researchers attributed to the installation of solar panels, and a few other risks.

| Dec 15, 2011

NRDC charges Maine governor with weakening green wood requirement

The FSC program is administered through the Leadership in Energy and Environmental Design (LEED) and requires wood to be harvested in a sustainable way.

| Dec 15, 2011

Post-tornado, Tuscaloosa seeks to create walkable urban, retail areas

Block sizes initially were limited to a maximum perimeter of 1,750 feet, with no side of the block being longer than 500 feet.

| Dec 15, 2011

Allentown, Pa. city council asked to repeal union-friendly law

The mayor of Allentown, Pa. asked the City Council to repeal a year-old ordinance that forces contractors to hire union workers for large city projects funded with state and federal dollars.

| Dec 13, 2011

LEED-EB outpaces LEED for new construction

The U.S. Green Building Council's (USGBC's) LEED certifications for existing buildings standard is outpacing LEED for new buildings for the first time.

| Dec 13, 2011

Regulators charge pervasive abuse of construction workers in Connecticut

Federal and state regulators say they have uncovered what they call "widespread noncompliance" with minimum wage and overtime laws in Connecticut's construction industry.

| Dec 13, 2011

Philadelphia mayor signs order for project labor agreements

Philadelphia Mayor Michael Nutter signed an executive order establishing project labor agreements for major public works projects in Philadelphia.

| Dec 13, 2011

Improved code requirements for attic ventilation

The Roof Assembly Ventilation Coalition (RAVC) participated in the development of the code.

| Dec 12, 2011

LEED-EB Outpaces LEED for New Construction

The U.S. Green Building Council’s (USGBC’s) LEED certifications for existing buildings standard is outpacing LEED for new buildings for the first time.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021