Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Healthcare Facilities

Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Robotics and Takt Planning credited for boosting efficient performance


By Peter Fabris, Contributing Editor | August 21, 2023
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Pictured: A mock surgery room at Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center. Photo courtesy Sutter Health

Sutter Health’s Samaritan Court Ambulatory Care and Surgery Center (Samaritan Court), a three-story, 69,000 sf medical office building, was recently completed three months early and $3 million under budget, according to general contractor Skanska

The project “marks the first time a general contractor has collaborated seamlessly with all trade partners (mechanical, electrical, plumbing, framing, and drywall) on layout strategy and responsibilities simultaneously,” Skanska says.

The accomplishment was aided by Dusty Robotics, a robot tool that its manufacturer says, “allows project teams to dramatically reduce schedule time and rework costs through accurate, full-scale floor layout.” Skanska worked with trade partners specializing in mechanical, electrical, plumbing, framing and drywall, to develop a combined layout plan in a “first-of-its-kind collaboration and implementation of Dusty Robotics.”

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

The project team also used a virtual punch list and Takt Planning, starting punch list activities during the design and preconstruction phases rather than in the closeout phase. The team focused on where improvements could be made to cut rework in half in comparison to projects of similar size and complexity. 

The virtual punch list allowed each stakeholder to review final conditions—furniture, casework and equipment placement, ADA clearances, device and outlet alignment, utility connections, and item placements that would require unique finish details—in the building model. This allowed the team to achieve its goal of cutting rework by 50% on the project.  

The design team strove for a warm, timeless, easy-to-maintain, and inviting space by incorporating warm woods, recessed modern lighting, natural stone, and visually stimulating wayfinding graphics. Wayfinding throughout the building used imagery of local flora and fauna elemental themes assigned to each floor, such as water, pebbles, and trees. Natural element-themed graphics were assigned to each medical practice to create an intuitive orientation in the building.    

Located near the border of San Jose and Los Gatos, Calif., the building aims for patient-centered care. Design highlights include:

  • Single entry/exit for patients, promoting clear wayfinding 
  • Centralized reception areas for upper floors at patient entry points 
  • Centralized waiting spaces on upper floors to allow a variety of clinical services to share seating and maximize efficiency for staff movement
  • Localized departments to achieve the greatest operational efficiency for the best patient care with ease of access to core modalities including Diagnostic Imaging and Laboratory Services 
  • Departmental adjacencies to share point-of-care rooms and support spaces between clinic modules and services
  • Locating of the surgery center on the first floor for ease of patient access and discharge 
  • Orientation of patient care and recovery rooms toward pleasant views of the natural environment to encourage patient recovery

On the project team:  
Owner and/or developer: Sutter Health 
Design architect: Boulder Associates 
Architect of record: Boulder Associates 
MEP engineer: Southland Industries (mechanical, plumbing); Prime Electric (electric);  
Structural engineer: Miyamoto 
General contractor/construction manager: Skanska

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

 

Related Stories

| Dec 29, 2014

New mobile unit takes the worry out of equipment sterilization during healthcare construction [BD+C's 2014 Great Solutions Report]

Infection control, a constant worry for hospital administrators and clinical staffs, is heightened when the hospital is undergoing a major construction project. Mobile Sterilization Solutions, a mobile sterile-processing department, is designed to simplify the task. The technology was named a 2014 Great Solution by the editors of Building Design+Construction.

| Dec 29, 2014

HealthSpot station merges personalized healthcare with videoconferencing [BD+C's 2014 Great Solutions Report]

The HealthSpot station is an 8x5-foot, ADA-compliant mobile kiosk that lets patients access a network of board-certified physicians through interactive videoconferencing and medical devices. It was named a 2014 Great Solution by the editors of Building Design+Construction.

BIM and Information Technology | Dec 28, 2014

The Big Data revolution: How data-driven design is transforming project planning

There are literally hundreds of applications for deep analytics in planning and design projects, not to mention the many benefits for construction teams, building owners, and facility managers. We profile some early successful applications.  

| Dec 28, 2014

AIA course: Enhancing interior comfort while improving overall building efficacy

Providing more comfortable conditions to building occupants has become a top priority in today’s interior designs. This course is worth 1.0 AIA LU/HSW.

| Dec 2, 2014

Nonresidential construction spending rebounds in October

This month's increase in nonresidential construction spending is far more consistent with the anecdotal information floating around the industry, says ABC's Chief Economist Anirban Basu.

| Dec 1, 2014

How public-private partnerships can help with public building projects

Minimizing lifecycle costs and transferring risk to the private sector are among the benefits to applying the P3 project delivery model on public building projects, according to experts from Skanska USA. 

| Nov 25, 2014

Emerging design and operation strategies for the ambulatory team in transition

As healthcare systems shift their care models to be more responsive to patient-centered care, ambulatory care teams need to be positioned to operate efficiently in their everyday work environments, write CannonDesign Health Practice leaders Tonia Burnette and Mike Pukszta.

| Nov 20, 2014

Lean Led Design: How Building Teams can cut costs, reduce waste in healthcare construction projects

Healthcare organizations are under extreme pressure to reduce costs, writes CBRE Healthcare's Lora Schwartz. Tools like Lean Led Design are helping them cope.

| Nov 18, 2014

5 big trends changing the world of academic medicine

Things are changing in healthcare. Within academic medicine alone, there is a global shortage of healthcare professionals, a changing policy landscape within the U..S., and new view and techniques in both pedagogy and practice, writes Perkins+Will’s Pat Bosch.

| Nov 14, 2014

Haskell acquires FreemanWhite, strengthens healthcare design-build business

The combination expands Haskell’s geographic presence by adding FreemanWhite’s offices in Chicago, Charlotte, Nashville, and San Diego. FreemanWhite will retain its name and brand.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021