Tall ICF Walls: 9 Building Tips from the Experts

Tall ICF Walls: 9 Building Tips from the Experts

Want to go high with insulating concrete forms? Better keep these helpful tips in mind.


By By Dave Barista, Managing Editor | August 11, 2010
Tall ICF Walls 9 Building Tips from the Experts Insulating concrete forms

Photo courtesy NUDURA

   

This article first appeared in the 200908 issue of BD+C.

Insulating concrete forms have a long history of success in low-rise buildings, but now Building Teams are specifying ICFs for mid- and high-rise structures—more than 100 feet. ICF walls can be used for tall unsupported walls (for, say, movie theaters and big-box stores) and for multistory, load-bearing walls (for hotels, multifamily residential buildings, and student residence halls).

Our trusted ICF experts offer the following tips for designing and constructing tall ICF walls:

 

1. Pre-plan your job by drawing a simple cross section with the ICF you are using.

The cross section will show you how openings line up with the coursing of the ICF joints and where embeds will be placed, says Glen Klassen, regional manager with ICF manufacturer Arxx, Cobourg, Ont. "During the build process, your crew can follow this cross section to know when to stop placing forms and start placing embeds."

 

2. Account for the ICF formwork course height.

Designers can greatly reduce the amount of formwork cuts the contractor will be required to make by considering the course height of the ICF product when designing the walls, says Kelvin Doerr, VP of engineering and technical services for Reward Wall Systems, Omaha, Neb. Doerr says architects should factor in wall heights, window heights, and floor elevations when possible.

 

3. Base concrete slump and aggregate size on ICF manufacturer recommendations.

Both concrete slump and aggregate size are impacted by the formwork tie configuration within the formwork cavity, as well as by the amount of open space available around the ties to allow concrete to effectively flow within the forms, says Donn C. Thompson, AIA, LEED AP, CGP, director of Low Rise Buildings with the Portland Cement Association, Skokie, Ill. "Ties with smaller openings will require smaller aggregate to insure the concrete flows effectively through the forms," he says.

Arxx's Klassen offers this rule of thumb: If the concrete is restricted slightly at the top form around the rebar before flowing into the wall, it's just right. If the concrete gets restricted to the point of not flowing down into the wall, it's too low of a slump. If the concrete flows freely into the wall with no restriction, it is likely too high a slump.

 

4. Consider the STC rating needed for the job.

Once you know the sound transmission class, consider what needs to be added to the ICF wall if an STC rating of 50 or higher is required, says John Krzic, accounts manager with Amvic Building System, Toronto. "For example, by adding a resilient channel to the ICF wall and then installing the drywall, it will increase the STC rating of the wall assembly," says Krzic.

 

5. Take steps to ensure the concrete completely fills the form.

"One concern with tall ICF walls is that concrete may not fill all parts of the form since the walls are generally thin," says Lionel Lemay, PE, SE, LEED AP, CAE, senior VP of sustainable development, National Ready Mixed Concrete Association, Silver Spring, Md. To help avoid holes and gaps in the concrete pour, Lemay advises the following:

  • Place a single layer of reinforcement in the center of the wall to allow for more space on either side of the reinforcement.

  • Allocate greater spacing of reinforcement than is required in ACI 318 14.5, which requires a maximum spacing of three times the wall thickness or 18 inches, whichever is smaller.

Consider using self-consolidating concrete. "Keep in mind that self-consolidating concrete exerts greater pressure on forms, so additional bracing will be required for most ICF systems," says Lemay.

 

6. Specify an ICF that is fully reversible.

"These forms have no top, bottom, left, or right side, and, therefore, are more efficiently stacked, reducing construction costs," says Reward's Doerr.

 

7. Repeat window patterns when possible.

In multistory load-bearing applications such as multifamily, senior living, and hotel projects, try to repeat window patterns from floor to floor so that the openings remain stacked for the full height of the wall assembly, says PCA's Thompson. This maximizes efficiency in design and construction.

 

8. Make sure, in noncombustible Type I, II, III, and IV multistory building projects, that the noncombustible floor system intersects the foam plastic on the interior of the building.

"The foam plastic must not be continuous from floor to floor, and special detailing is necessary to meet these requirements," says Doerr. In addition, IBC states that interior walls must be covered with a 15-minute thermal barrier. Doerr says half-inch gypsum board will do the trick.

 

9. Brace from the inside.

The higher the wall, the more difficult and costly it is to reach the exterior of the wall with bracing, says Amvic's Krzic. "Proper bracing will help to ensure that walls will be straight and level," he says. "This is important as it can affect other sub trades, wall finishes, and structural integrity of the building."


More on insulating concrete forms at:
13 tips on working with insulating concrete forms

How Insulated Concrete Forms Help Reduce Energy Consumption
English inspired church built with insulated concrete forms

Related Stories

Sponsored | Building Team | Dec 12, 2017

3 tips to address the top causes of budget overruns

The most cited issues are communication breakdowns, inadequate fees for the work provided, and unrealistic deadlines or schedules.

Building Team | Nov 14, 2017

12 differences between average and high-growth firms

We’ve developed a pretty good understanding of what high-growth firms do differently from their average-growth peers.

Sponsored | Building Team | Nov 3, 2017

4 strategies for marketing your AEC firm

Having a clearly defined competitive brand and a fine-tuned marketing approach can give your firm a significant competitive advantage.

Sponsored | Building Team | Sep 21, 2017

The 11 project performance metrics that keep you on track

Projects are the backbone of the way you do business. Isn’t it time that you step up their analysis?

Architects | Aug 16, 2017

Staffelbach joins DLR Group

The firm will be merging operations immediately with full integration and the name change to DLR Group| Staffelbach effective October 2.

Multifamily Housing | Aug 14, 2017

Co-living: The next real estate disruptor or niche market?

From a practicality standpoint, co-living makes complete sense for young, single, and highly mobile working professionals.

Building Team | Jul 25, 2017

Managing workplace change: The three C's to building trust

Building trust takes time and consistency, and is typically much easier to break than build.

Giants 400 | Jul 12, 2017

Innovation abounds, but will it lead to growth for AEC Giants?

Engineering firms such as Arup, Glumac, and Thornton Tomasetti are leveraging their in-house expertise to develop products and tools for their design teams, clients, and even the competition. 

Building Team | Jun 27, 2017

Bruner Foundation announces 2017 Rudy Bruner Award for Urban Excellence gold and silver medalists

The SteelStacks Arts and Cultural Campus in Bethlehem, Pa., receives the gold medal and $50,000.

Urban Planning | Jun 26, 2017

Convenience and community lead the suburban shift

As the demand for well-connected urban locales increases, so too has the cost of property and monthly rent; and as suburbs typically offer a bargain on both, more people are looking for a compromise. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021