Target converts former prison dump into latest big-box store

Target converts former prison dump into latest big-box store

The site was full of hazardous materials, unstable ground when MBH Architects began work


By BD+C Staff | February 27, 2014

Recently, MBH Architects was approached by the Target Corporation, who asked them to design a new store in San Rafael, Calf. The problem: the building was slated for the former San Quentin Prison dump site, meaning that the lot was full of hazardous materials and that the ground was unstable.

MBH worked with a team of specialists—from structural, civil, and landscape specialists to experts in methane mitigation, vertical reciprocating conveyors, and onsite lighting—to make the lot suitable for the new store.

The unstable ground had been projected to sink two to three feet over the next 30-40 years. In order to make the building site more stable, the team started by driving prefabricated piles into the ground. In addition, Target San Rafael’s parking lot is connected by elevated walkways that minimize impact to the ground.

To counteract potentially hazardous materials, vents have been installed throughout the site and parking light poles release the methane build-up.

The LEED Gold-certified store features a number of green features, including 17 electric car chargers, solar panels, and a stormwater recycling system.

 


Before construction, the site was a literal dump.

Related Stories

| Dec 9, 2012

Modular classroom building makes the grade

SAGE modular classroom opens eyes, minds at Greenbuild 2012.

| Dec 9, 2012

14 great solutions

Welcome to the third installment of Building Design+Construction’s “Great Solutions,” highlighting 14 innovative technologies and products that you can put to work in your next project.

| Dec 9, 2012

AEC professionals cautiously optimistic about commercial construction in ’13

Most economists say the U.S. is slowly emerging from the Great Recession, a view that was confirmed to some extent by an exclusive survey of 498 BD+C subscribers whose views we sought on the commercial construction industry’s outlook on business prospects for 2013.

| Dec 7, 2012

Structural glazing sealant protects solar-rooftop stadium in Taiwan

Designers of the Kaohsiung World Games Main Stadium in Gaoxiong, Taiwan, powered by almost 9,000 rooftop solar panels, required an effective panel fixing design offering optimum energy transfer rate, plus thermal and weathertight performance. Dow Corning specialists recommended a four-sided structural sealant solution featuring Dow Corning 983 Structural Glazing Sealant.

| Dec 6, 2012

Ziegler Cooper names Soto as Director of Design, Broadens Design Capabilities

Soto will oversee design efforts, bringing a high level of quality and problem solving capabilities through active engagement with clients and studios firm wide.

| Dec 5, 2012

Gilbane publishes Winter 2012 construction economic report

Report outlines impact of recent events; predicts continued movement, while slow, toward recovery.

| Dec 5, 2012

Gehry-designed New York City tower receives Emporis Skyscraper Award

8 Spruce Street is now the third New York tower to win the Emporis Skyscraper Award.

| Dec 4, 2012

MKK’s Denver Human Services Eastside Building wins ACEC Excellence Award

MKK provided mechanical, plumbing and fire protection consulting services on this LEED-NC Gold project.

| Dec 4, 2012

Thornton Tomasetti opens new office in São Paulo, Brazil

The move to São Paulo is strategic and timely, as the country continues preparations for the 2014 World Cup and 2016 Olympic Games in Rio de Janeiro.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021