The 173-acre TechnipFMC John T. Gremp Campus is the first element in north Houston’s Generation Park planned community. The 1.7 million-sf complex was completed in March 2016. Two months later, FMC Technologies and European oil and gas equipment technology company Technip formally announced their merger.
The new campus consolidates manufacturing, offices, and amenities for thousands of employees who were spread across six locations in the Houston area.
The Building Team, led by design giant Gensler, developer Trammell Crow, and contractor D.E. Harvey Builders, successfully dealt with requests from the owner after work had already begun.
First, TechnipFMC wanted to change two primary office buildings that were connected at only one level into a single building that would be connected on all levels. The project team used 3D visualization for fast design approval to insert a multi-level vertical connector into shared amenity space on each level.
Next, the owner added a new sophisticated process equipment product line to the project scope very late in the design process. The Building Team created a new design that allowed for placement of an in-ground rail system, underground utility distribution system, and automated welding machine system; all this, after most of the structure was already built.
TechnipFMC then announced that it was developing a new subsea equipment system that was significantly larger and heavier than the original building was designed for. The Building Team modified floor thicknesses, added 50 tons to the crane capacity, revised equipment circulation, and increased the size of the testing area without affecting foundation pours that were already in progress.
The Technip FMC campus in north Houston is marked by a 369,000-sf LEED Gold office building. The 2,036-space parking garage gives priority space to fuel-efficient vehicles. Landscape irrigation uses non-potable water. Photo: Ryan Gobuty/Gensler.
Building Team – Submitting firm, architect, interior architect Gensler Developer Trammell Crow Co. Structural engineer Cardno Haynes Whaley Mechanical engineer Wylie Consulting Engineers Contractor D.E. Harvey Builders
General Information – Size 1.7 million sf Construction cost Confidential Construction period April 2014 to March 2016 Delivery method Design-bid-build
Related Stories
| Aug 29, 2022
Montana becomes first U.S. state to approve 3D printing in construction
Montana is the first U.S. state to give broad regulatory approval for 3D printing in building construction.
Architects | Apr 22, 2022
Top 10 green building projects for 2022
The American Institute of Architects' Committee on the Environment (COTE) has announced its COTE Top Ten Awards for significant achievements in advancing climate action.
Concrete Technology | Apr 19, 2022
SGH’s Applied Science & Research Center achieves ISO 17025 accreditation for concrete testing procedures
Simpson Gumpertz & Heger’s (SGH) Applied Science & Research Center recently received ISO/IEC17025 accreditation from the American Association for Laboratory Accreditation (A2LA) for several concrete testing methods.
2021 Building Team Awards | Jan 14, 2022
First public-private partnership project in Veterans Administration history saves $34 million in costs
LEO A DALY and McCarthy Building Companies head the project team for the Omaha VA Ambulatory Care Center in BD+C’s 2021 Building Team Awards.
Building Team Awards | Dec 8, 2021
A performing arts center celebrates a legendary rocker and his birthplace
Buddy Holly Hall in Texas receives BD+C’s Silver Building Team Award.
Building Team Awards | Dec 7, 2021
A rapid response to a health emergency
Baptist Hospital of Miami’s 233-bed Hope Tower receives BD+C’s Bronze Building Team Award
Building Team Awards | Dec 3, 2021
Putting science on display, thanks to a design-build approach
UC Riverside’s Plant Growth Environments Facility receives BD+C’s Bronze Building Team Award.
Building Team Awards | Dec 2, 2021
An academic ‘precinct’ brings arts and sciences together
Wofford College’s Chandler Center for Environmental Studies receives BD+C’s Silver Building Team Award.
Building Team Awards | Dec 1, 2021
Denver sets the bar for water reclamation and reuse
A new administration building for the city’s water utility company scores Platinum in BD+C’s 2021 Building Team Awards.
2021 Building Team Awards | Nov 17, 2021
Caltech's new neuroscience building unites scientists, engineers to master the human brain
The Tianqiao and Chrissy Chen Institute for Neuroscience at the California Institute of Technology in Pasadena wins a Gold Award in BD+C's 2021 Building Team Awards.