Three libraries in California were built in less than two years under a P3 contract

Libraries

Three libraries in California were built in less than two years under a P3 contract

A nonprofit with tax advantages funded the project.


By John Caulfield, Senior Editor | September 22, 2021
A new library in French Valley, Calif., one of three built under a P3 contract
Riverside County, Calif., teamed with a nonprofit to finance the design and construction of three libraries. Shown above is the 25,000-sf library in French Valley, Calif. Images: Courtesy of CannonDesign

Over the summer, a building team that included CannonDesign and McCarthy Building Companies completed three new libraries in Riverside County, Calif., that were built simultaneously in just 20 months under a $46 million public-private partnership contract that included a nonprofit specializing in funding P3 projects.

The three libraries—in Desert Hot Springs, Menifee, and French Valley—are now owned by Community Facility Public Private Partnerships (CFP3), a 501(c)(3) nonprofit that financed this project via tax-exempt bonds. Over the course of CFP3’s ownership contract, which can run up to 30 years, the County expects to save $25 million in debt service, operations, and maintenance costs. The installation of solar panels alone is expected to save $600,000.

As early as 2014, Riverside County—the fourth most-populous county in the state and the 10th most-populous in the U.S.—realized that its library system wasn’t keeping up with its growth. For example, at the time its existing 10,500-sf library in Menifee was serving 350,000 patrons. And that library’s location near a major roadway excluded expansion, according to a white paper about this project that CFP3 has published.

Back in the 1970s, the County’s Board of Supervisors approved the dedication of 1% of its general property tax for library services. But that wasn’t enough to build and maintain newer, larger branches.

P3 PRECEDENTS

 

A tech center inside of the library in French Valley, Calif.
While each library is configured differently, they share common elements like tech centers.

Prior to its library contract, the County had done about 15 P3s for different building types that covered 1 million sf and $600 million of property. To envision how many new libraries it needed, the County’s Office of Economic Development, in partnership with Library Systems and Services (which since the 1990s had operated Riverside’s library system), hired Group 4, a South San Francisco firm that specializes in project planning for libraries and community centers.

In 2018, the Riverside County Library System created an RFP for three new libraries, and received a dozen proposals. The County, which approved this project a year later, determined that the best, and least expensive, course of action would be to hire one team for all three projects under a P3 contract structure.

There were several advantages to taking this route, not the least being that the project could move forward without as many public hearings, procurement protocols, and referendums that can add months to scheduling. And because CFP3 is a nonprofit, it would not be saddled with property taxes as the libraries’ owner. The interest it charged the County for the cost of the project, at between 3% and 3.5%, was less than half of the return on equity a private P3 entity would have expected.

WHAT PARTNERS BROUGHT TO THE TABLE

 

New library in Desert Hot Springs, Calif.
The new library in Desert Hot Springs, Calif. (above) is five times larger than its predecessor. The library in Menifee, Calif. (below) was essential to meet the community's growth.

The new library in Menifee, Calif.

The partners in this P3 included Omni West Group, a development and property management firm, that came up with the libraries’ operational budget. CannonDesign created the blueprints for all three libraries that, while having different layouts, share similar attributes like children’s areas, tech centers, and community spaces.

McCarthy, which served as this project’s general contractor, was brought on board in part for its long-time relationships with local subcontractors, which prevented manpower-shortage delays. McCarthy assigned one project manager to monitor all three builds. CFP3 calculates that the design and construction of the libraries accounted for 20% of the total cost, with the rest going toward maintenance and operations.

During construction, there were some community concerns about the 25,000-sf library in French Valley, which opened July 31 and is the only one of the three located in a residential neighborhood. CFP3 states that these concerns were resolved with meetings and virtual fly-throughs of the building.

The new Menifee library opened July 24 at 20,000 sf, and was built to be an anchor for a larger retail development. The Desert Hot Springs library—the first of the three to open, on June 26—is 15,500 sf, and replaces a library that was only around one-fifth that size. “This library is a wonderful anchor for the community,” says Matthew Greiner, AIA, NCARB, Senior Vice President at CannonDesign. “It’s a home base for the wonderful people who live here. It’s where so many bright ideas and futures will be launched.” 

Tags

Related Stories

Cultural Facilities | Jun 30, 2016

Tod Williams Billie Tsien Architects selected to design Obama Presidential Center in Chicago

With experience designing cultural and academic facilities, Williams and Tsien got the nod over other search finalists like Renzo Piano, SHoP, and Adjaye Associates.

Building Team Awards | May 19, 2016

Chinatown library unites and serves two emerging Chicago neighborhoods

The 16,000-sf, pebble-shaped Chinatown Branch Library was built at the intersection of new and old Chinatown neighborhoods. The goal is for the building to unite the communities and serve as a catalyst for the developing area.

Libraries | Apr 21, 2016

New renderings released for Herzog & de Meuron’s National Library of Israel

The library is based around the light well in the center of a concave roof, a feature that will illuminate the spacious second story and the ground level.

Libraries | Apr 18, 2016

Best in Library Design: AIA names seven projects 2016 Library Building Awards winners

Snøhetta’s Ryerson University student center and the Billings (Mont.) Public Library by Will Bruder+Partners highlight the seven winning projects.

Libraries | Jan 26, 2016

Snøhetta designs research library at Temple University

The firm emphasized collaborative spaces, but the library will have room for plenty of books as well.

| Jan 14, 2016

How to succeed with EIFS: exterior insulation and finish systems

This AIA CES Discovery course discusses the six elements of an EIFS wall assembly; common EIFS failures and how to prevent them; and EIFS and sustainability.

Libraries | Aug 27, 2015

Barack Obama Foundation begins search for presidential library architect

Both national and foreign firms will compete for chance to design the Chicago-based Presidential Center.

Libraries | Apr 29, 2015

Designs for earthquake-resistant New Central Library in New Zealand unveiled

The Danish firm Schmidt Hammer Lassen Architects won the competition to design the New Central Library in Christchurch, New Zealand, which will replace the old building damaged by devastating earthquakes in 2010 and 2011.

Cultural Facilities | Apr 7, 2015

Mies’ Martin Luther King Jr. Library to get makeover

The architects say the modernization aims to improve “Mies in a contemporary Miesian way.”

Libraries | Apr 2, 2015

6 award-winning libraries showcase next-gen design strategies

The new Cedar Rapids Public Library and the restored Slover Library in Norfolk, Va., are among six breakthrough projects honored with 2015 AIA/ALA Library Building Awards.

boombox1
boombox2
native1

More In Category

Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021