Tishman Construction Corp. completed Revel, a $2.4-billion beachfront destination, six weeks early. Tishman was contracted to provide construction management services for this 20-acre, 47-story resort--which features nearly 1,000 feet of beach frontage during 2007--and despite a pause in construction, turned over 6.3 million-sf of space in time for the hotel’s preview on April 2, 2012.
Tishman managed the construction for the project, which includes 1,898 guest rooms with ocean views, a 130,000-sf casino, a large performance space with capacity for more than 5,000 fans, a more intimate performance space for 700 people, retail spaces, restaurants, an expansive spa, indoor and outdoor pools, a four-story nightclub, and meeting space.
Also included is 250,000-sfof back-of-house function space and a 50,000-sf warehouse with full loading dock access, as well as a car parking garage for more than 7,000 vehicles and a central utility plant to service the project.
In total, Revel stands more than 730 feet tall, consists of over 6.3 milliont--sf of space, and is enclosed by 836,762-sf of glass--equivalent to more than 16 football fields.
Furthermore, Tishman installed more than 5 million pounds of sheet metal and over 7,500 plumbing fixtures. +
Related Stories
| Mar 19, 2012
Smith Carter joins forces with Genivar
Smith Carter has a workforce of some 190 employees and designs complex buildings in challenging environments.
| Mar 19, 2012
HKS Selected for Baylor Medical Center at Waxahachie
Baylor Medical Center at Waxahachiewill incorporate advanced technology including telemedicine, digital imaging, remote patient monitoring, electronic medical records and computer patient records.
| Mar 19, 2012
Mixed-use project redefines Midtown District in Plantation, Fla.
Stiles Construction is building the residential complex, which is one of Broward County’s first multifamily rental communities designed to achieve LEED certification from the USGBC.
| Mar 16, 2012
Temporary fix to CityCenter's Harmon would cost $2 million, contractor says
By contrast, CityCenter half-owner and developer MGM Resorts International determined last year that the Harmon would collapse in a strong quake and can't be fixed in an economical way. It favors implosion at a cost of $30 million.
| Mar 16, 2012
Work on Oxnard, Calif. shopping center resumes after a three-year hiatus
Stalled since 2009, developers of the Collection at RiverPark decided to restart construction on the outdoor mall.
| Mar 16, 2012
Stego embarks on HPD Pilot Program
Vapor barrier manufacturer strives to provide better green choices to designers and builders.
| Mar 16, 2012
Marvin Windows and Doors accepting entries for fourth-annual myMarvin Architect’s Challenge
Architects in U.S. and abroad offered the chance to showcase their very best work.
| Mar 14, 2012
Hearing to decide fate of unfinished Harmon in Las Vegas under way
The testimony began with CityCenter consulting engineer Chukwuma Ekwueme methodically showing photo after photo of parts of the Harmon, where he and his team had chipped away the concrete pillars and beams to examine the steel reinforcing bars inside.
| Mar 14, 2012
Firestone names 2012 Master Contractor Award Winners
Annual award acknowledges industry’s top roofing professionals.