Rank | Company | 2013 Data Center Revenue |
1 | Holder Construction | $1,124,000,000 |
2 | Turner Construction | 512,000,000 |
3 | DPR Construction | 506,001,637 |
4 | Structure Tone | 400,450,000 |
5 | Mortenson Construction | 298,590,000 |
6 | Gilbane | 241,967,522 |
7 | Balfour Beatty US | 202,427,241 |
8 | Hensel Phelps | 177,120,000 |
9 | Hoffman Construction | 168,000,000 |
10 | HITT Contracting | 136,900,000 |
11 | Fortis Construction | 136,102,000 |
12 | Carlson Design Construct | 114,070,000 |
13 | Clune Construction | 101,583,530 |
14 | James G. Davis Construction | 98,601,699 |
15 | Skanska USA | 95,067,555 |
16 | Beck Group, The | 91,445,591 |
17 | JE Dunn Construction | 91,178,219 |
18 | Yates Companies, The | 30,000,000 |
19 | URS Corp. | 25,100,000 |
20 | McGough | 24,000,000 |
21 | Tutor Perini Corp. | 18,036,474 |
22 | BlueScope Construction | 17,849,218 |
23 | IMC Construction | 13,000,000 |
24 | Parsons Brinckerhoff | 12,185,435 |
25 | Brasfield & Gorrie | 11,948,769 |
26 | Flintco | 11,300,000 |
27 | Pepper Construction | 10,880,000 |
28 | Ryan Companies US | 9,802,824 |
29 | Hunt Construction Group | 8,000,000 |
30 | Hathaway Dinwiddie Construction | 6,000,000 |
31 | Hill International | 6,000,000 |
32 | Austin Commercial | 4,210,253 |
33 | Harkins Builders | 3,700,000 |
34 | Weitz Company, The | 2,566,066 |
35 | O'Neil Industries/W.E. O'Neil | 2,441,614 |
36 | JLL | 2,334,082 |
37 | Walsh Group, The | 2,242,483 |
38 | Layton Construction | 1,700,000 |
39 | Messer Construction | 1,433,071 |
40 | W. M. Jordan Company | 682,821 |
41 | Heery International | 589,726 |
42 | Wight & Company | 502,000 |
43 | STV | 217,000 |
44 | Sundt Construction | 69,754 |
45 | Allen & Shariff | 65,000 |
Read the Data Center Giants article
Read BD+C's full 2014 Giants 300 Report
Related Stories
| Aug 11, 2010
SAFTI FIRST hires Tim Nass as National Sales Manager
SAFTI FIRST, a leading USA manufacturer of fire rated glazing and framing systems, is pleased to announce the addition of Tim Nass as National Sales Manager. In his new role, Tim will be working closely with architects and contract glaziers in selecting the appropriate and most economical fire rated glazing solution for their project. He will also be coordinating SAFTI FIRST’s extensive network of architectural representatives throughout the United States.
| Aug 11, 2010
NCARB welcomes new board of directors
The National Council of Architectural Registration Boards (NCARB) introduces its Board of Directors for FY10, who were installed during the culmination of the Council’s 90th Annual Meeting and Conference in Chicago.
| Aug 11, 2010
Berkebile wins $100K award for commitment to environment
Robert Berkebile, the founding principal of BNIM Architects and a founding member of the U.S. Green Building Council, has been selected to receive a $100,000 Heinz Award. The award honors his role in promoting green building design and for his commitment and action toward restoring social, economic, and environmental vitality to America’s communities through sustainable architecture and planning.
| Aug 11, 2010
Polshek Partnership unveils design for University of North Texas business building
New York-based architect Polshek Partnership today unveiled its design scheme for the $70 million Business Leadership Building at the University of North Texas in Denton. Designed to provide UNT’s 5,400-plus business majors the highest level of academic instruction and professional training, the 180,000-sf facility will include an open atrium, an internet café, and numerous study and tutoring rooms—all designed to help develop a spirit of collaboration and team-oriented focus.
| Aug 11, 2010
University of Florida aiming for nation’s first LEED Platinum parking garage
If all goes as planned, the University of Florida’s new $20 million Southwest Parking Garage Complex in Gainesville will soon become the first parking facility in the country to earn LEED Platinum status. Designed by the Boca Raton office of PGAL to meet criteria for the highest LEED certification category, the garage complex includes a six-level, 313,000-sf parking garage (927 spaces) and an attached, 10,000-sf, two-story transportation and parking services office building.
| Aug 11, 2010
Draft NIST report on Cowboys practice facility collapse released for public comment
A fabric-covered, steel frame practice facility owned by the National Football League’s Dallas Cowboys collapsed under wind loads significantly less than those required under applicable design standards, according to a report released today for public comment by the Commerce Department's National Institute of Standards and Technology (NIST).
| Aug 11, 2010
Callison, MulvannyG2 among nation's largest retail design firms, according to BD+C's Giants 300 report
A ranking of the Top 75 Retail Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants