Transforming a landmark coastal resort

Transforming a landmark coastal resort

Originally built in 1973, the building had received several alterations over the years but the progressive deterioration caused by the harsh salt water environment had never been addressed.


November 8, 2011
The extent of concrete deterioration was so severe that the balconies and walkways were completely removed and replaced with new

The Royal Floridian is a seven story vacation resort that is a major economic driver in the small coastal town of Ormond Beach, Fla. Originally built in 1973, the building had received several alterations over the years but the progressive deterioration caused by the harsh salt water environment had never been addressed.

The restoration team, led by ConTech Construction, was hired 1½ years before construction started, which allowed for extensive planning. The engineer performed both non-destructive and limited destructive testing to determine the extent and cause of structural deficiencies. These explorations uncovered severe corrosion of the structural steel support columns and beams under the north and south cantilevered ends of the building. Other findings were chloride content in the concrete balconies of over 5 lbs per cubic yard, hundreds of top and bottom spalls, and large areas of cracked and disbonded stucco. Water intrusion was causing deterioration inside the living areas.

The extent of concrete deterioration was so severe that the balconies and walkways were completely removed and replaced with new concrete containing a corrosion inhibitor admixture. Other concrete areas were selectively repaired with pre-packaged structural repair mortars.

The team also executed an architectural aesthetic make over that transformed the worn out, drab facility into a gorgeous, modern destination resort. The entire east face of the building was reconstructed, including new balconies, new insulated windows and doors and 15 BASF products, including Sonoguard waterproofing membranes and Thorocoat, Thorolastic and Thorosheen acrylic exterior coatings.

New pavers were installed over the waterproofing membrane on the pool deck over the parking garage, and new concrete swimming pools completed the transformation of this landmark resort. 

To learn more about the Royal Floridian project, click here to watch the video. BD+C

Related Stories

Multifamily Housing | Apr 22, 2015

Condo developers covet churches for conversions

Former churches, many of which are sitting on prime urban real estate, are being converted into libraries, restaurants, and with greater frequency condominiums.

High-rise Construction | Apr 22, 2015

Architects propose sustainable ‘vertical city’ in the Sahara

Designers aim to make the 1,476-foot tower sustainable, relying on rainwater collection, solar power, and geothermal energy.

Architects | Apr 22, 2015

Architecture Billings Index accelerates in March

For the second consecutive month, the Architecture Billings Index indicated a modest increase in design activity in March.

Green | Apr 22, 2015

AIA Committee on the Environment recognizes Top 10 Green Projects

Seattle's Bullitt Center and the University Center at The New School are among AIA's top 10 green buildings for 2015.

Museums | Apr 22, 2015

Check out Ralph Johnson's stunning nature-inspired Shanghai museum

The newly opened Shanghai Natural History Museum, designed by Perkins+Will’s Global Design Director Ralph Johnson, mimics the shape of a nautilus shell, and features natural elements throughout. 

Green | Apr 22, 2015

GSA's Federal Center South Building honored with AIA Top Ten Plus Award for 'verified' sustainable performance

The annual award recognizes green building projects that have quantifiable metrics demonstrating the performance and positive impact of the sustainable design.

Architects | Apr 21, 2015

Megatrends shaping commercial building design

Gensler’s 2015 Design Forecast focuses on how changes in demographics, workplace preferences, and technology are affecting how and why structures get built.

Office Buildings | Apr 21, 2015

Stop the endless debate over open vs. closed work environments

Rather than be confused by the constant stream of opinions, leadership teams contemplating workplace investments should start with powerful employee engagement strategies that drive results.

BIM and Information Technology | Apr 21, 2015

Software tools shouldn't dictate the AEC process

With over 200 solutions on the market, construction software is one of the most complex and fragmented markets, writes Gensler's Mark Thole.

Cultural Facilities | Apr 20, 2015

Jean Nouvel loses court battle against Philharmonie de Paris over alleged design ‘sabotage’

Nouvel boycotted the January opening of the facility and asked for his name to be removed from all references to the work. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021