Transforming a landmark coastal resort

Transforming a landmark coastal resort

Originally built in 1973, the building had received several alterations over the years but the progressive deterioration caused by the harsh salt water environment had never been addressed.


November 8, 2011
The extent of concrete deterioration was so severe that the balconies and walkways were completely removed and replaced with new

The Royal Floridian is a seven story vacation resort that is a major economic driver in the small coastal town of Ormond Beach, Fla. Originally built in 1973, the building had received several alterations over the years but the progressive deterioration caused by the harsh salt water environment had never been addressed.

The restoration team, led by ConTech Construction, was hired 1½ years before construction started, which allowed for extensive planning. The engineer performed both non-destructive and limited destructive testing to determine the extent and cause of structural deficiencies. These explorations uncovered severe corrosion of the structural steel support columns and beams under the north and south cantilevered ends of the building. Other findings were chloride content in the concrete balconies of over 5 lbs per cubic yard, hundreds of top and bottom spalls, and large areas of cracked and disbonded stucco. Water intrusion was causing deterioration inside the living areas.

The extent of concrete deterioration was so severe that the balconies and walkways were completely removed and replaced with new concrete containing a corrosion inhibitor admixture. Other concrete areas were selectively repaired with pre-packaged structural repair mortars.

The team also executed an architectural aesthetic make over that transformed the worn out, drab facility into a gorgeous, modern destination resort. The entire east face of the building was reconstructed, including new balconies, new insulated windows and doors and 15 BASF products, including Sonoguard waterproofing membranes and Thorocoat, Thorolastic and Thorosheen acrylic exterior coatings.

New pavers were installed over the waterproofing membrane on the pool deck over the parking garage, and new concrete swimming pools completed the transformation of this landmark resort. 

To learn more about the Royal Floridian project, click here to watch the video. BD+C

Related Stories

| Jun 13, 2012

Free webinar on Designing and Building Green Schools scheduled for June 20

USGBC Center for Green Schools and other experts to present practical tips.

| Jun 13, 2012

GAF’s Roving Truck promotion coming to your town soon

Professional roofing contractors or builders/remodelers in the U.S. can enter to win a Ford F-150 truck.

| Jun 13, 2012

Is it time to stop building convention centers?

Over the last 20 years, convention space in the United States has increased by 50%; since 2005, 44 new convention spaces have been planned or constructed in this country alone.

| Jun 13, 2012

Steven L. Newman Real Estate Institute to hold energy asset conference for property owners, senior real estate managers

Top-level real estate professionals have been ignored as the industry has pushed to get sustainability measures in place.

| Jun 12, 2012

SAC Federal Credit Union selects LEO A DALY to design corporate headquarters

LEO A DALY also provided site selection, programming and master planning services for the project over the past year.

| Jun 12, 2012

Restoration Millwork exterior trim achieves GreenCircle certification

Made from cellular polyvinyl chloride, the full line of Restoration Millwork trim, beadboard and accessories is engineered to look, feel and work like top-grade lumber.

| Jun 12, 2012

Piché joins C.W. Driver as director of business development

Piché will expand upon project opportunities for firm’s Southern California operations.

| Jun 12, 2012

BCA Architects transforms Anaheim schools into dynamic learning environments

BCA Architects was selected to update the district's long-range master plan.

| Jun 11, 2012

Survey reveals emerging trends in parking

Industry-transforming innovations are changing the way we park.

| Jun 11, 2012

Buro Hapold hires new principal Neil Porto

Porto brings a broad depth of expertise in civil and structural engineering to new and existing projects.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021