Updated AIA contracts clarify the role of construction managers

Contractors

Updated AIA contracts clarify the role of construction managers

The revised documents refine how CMs serve as general contractors or project advisers.


By John Caulfield, Senior Editor | November 5, 2019

This schematic shows how the family of Construction Manager as Constructor contracts works as a delivery method. Images: AIA

On Nov. 15, the American Institute of Architects (AIA) plans to release its new and updated Construction Manager as Constructor (CMc) family of contract documents. Next February, the AIA will release its updated Construction Manager as Adviser (CMa) family of documents.

These documents get updated on a 10-year revision cycle.

The AIA divides its contract documents into nine families, organized by delivery method. These include families for design-bid-build (the most widely used contract model), design-build, and integrated project delivery, as well as contracts that specifically cover interiors, small projects, and digital practices. The design-bid-build document family was updated in 2017.

Under CMc, the Construction Manager comes on the project during the preconstruction phase to provide early collaboration. In the construction phase, the CM does the construction work, as if it were a General Contractor.

Under the CMa, the Construction Manager is also retained by the owner for early collaboration during the preconstruction phase. But the CMas don’t perform the construction work. The CMa documents are designed for complex projects with more than one prime contractor. During the construction phase, the CMa coordinates and manages the contractors, as well as providing cost estimating and other functions.

Susan Van Bell, Senior Director and Counsel – AIA Contract Documents Content, tells BD+C that the AIA solicited input from CM practitioners about revisions to the documents so that they’d better reflect current practices.

From those conversations, CMs suggested that one change they wanted was a way to tailor the document for the scope of preconstruction services without having the standard contract language be too restrictive.

Van Bell says the 2019 CMc revision addresses this issue by inserting “fill points” into the contract where more preconstruction details can be identified. The update also makes some edits to the standard preconstruction services scope.

A schematic of the family of documents for Construction Manager as Advisor.

 

The CMc documents now include insurance and bond exhibits, which had been added to the design-bid-build document family in its 2017 revision. Van Bell says there are also new exhibits for both the CMc and CMa documents that cover the role of the CM in sustainable projects.

The revised CMa documents clarify the CMa’s role in such areas as analyzing and coordinating the contractors’ schedules. The CMa is also the responsible party for managing a project’s digital information systems. “We clarified the communication process,” Van Bell says. The 2017 updates that required the establishment of protocols for digital data and BIM were carried into the CMc and CMa updates.

Related Stories

| Dec 4, 2012

MKK’s Denver Human Services Eastside Building wins ACEC Excellence Award

MKK provided mechanical, plumbing and fire protection consulting services on this LEED-NC Gold project.

| Dec 4, 2012

Thornton Tomasetti opens new office in São Paulo, Brazil

The move to São Paulo is strategic and timely, as the country continues preparations for the 2014 World Cup and 2016 Olympic Games in Rio de Janeiro.

| Dec 4, 2012

Greenhorne & O’Mara signs letter of intent to join Stantec

Acquisitions of C3TS and Architecture 2000 also completed.

| Dec 4, 2012

Sto Corp. announces new distributor in the Carolinas

Company will now have coverage in several parts of North Carolina.

| Dec 4, 2012

Wirtz Beverage Illinois’ corporate headquarters completed

WBI Center, a new state-of-the-art facility, is designed by Ware Malcomb.

| Dec 4, 2012

City of Gainesville to break ground on $33 million bus fleet maintenance and ops facility

The 140,000-sf facility will include dispatch, administrative and maintenance facilities.

| Nov 28, 2012

Project team to showcase design for first mixed-use retail center of its kind in Mexico City

Project reaching construction milestone, offering national model for urban development in Mexico.

| Nov 28, 2012

Cummins announces ratings classification for data center power systems

The Data Center Continuous ratings span the range of Cummins Power Generation’s high horsepower diesel generator sets, from 1 MW up to 2.5 MW, and will apply to both 50 Hz and 60 Hz configurations.

| Nov 28, 2012

Francis Cauffman appoints Stainbrook Director of Higher Education

Stainbrook has 16 years of experience as a strategic planner and urban designer working on complex projects on- and off-campus.

| Nov 27, 2012

SFIA releases technical guide for cold-formed steel framing products

The 114-page book covers both structural and non-structural applications, including section properties of SFIA member product profiles, and complete load and span tables for most applications.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021