As they hone in on LEED certification, Building Teams need to look at the energy efficiency of every product and system that goes into a project, including vertical transport systems—elevators and escalators. Building owners and facility managers who are under pressure to reduce energy consumption and increase building efficiency are finding that one of the most economical solutions is to modernize and upgrade elevators.
Many of the same technological advancements that are improving energy efficiency in elevators are being applied to escalators. The end result is vertical transport systems that reduce a building’s operating costs and improve sustainability.
Several recent VTS innovations have been fine-tuned to better serve the nonresidential market.
TWEAKING MACHINE-ROOMLESS ELEVATORS
Over the past decade, machine-roomless (MRL) elevators have gained acceptance for a number of reasons: 1) they don’t require a separate machine room or electrical closet because the machinery is self-contained within the hoistway; 2) their motors are smaller and generate less heat; and 3) they don’t use petrochemical-based lubricants.
Sam Huleis, LEED AP, a senior project manager with C.W. Driver, a design-build firm in Pasadena, Calif., says that in addition to simplifying design and construction, MRLs use 40-50% less energy than conventional elevators, reducing operating costs for the building owner. C.W. Driver utilized Otis Elevator Co.’s Gen2 MRL traction elevators at the recently completed Valley Performing Arts Center at the California State University, Northridge.
“The Gen2 elevators use an in-hoistway motor and sheave system along with a unique flat-belt cable system,” Huleis says. “These polyurethane-coated steel belts take up less space than conventional braided steel cables and produce a quieter operation and a smoother ride. In addition, there’s no need to lubricate the belts or machinery.”
Another MRL innovation is the regenerative drive system, which feeds energy usually lost during braking back into the building’s electrical grid, where it can be used for other purposes such as stairwell lighting. Regen drives are standard on the Gen2, says Rick Pulling, director of worldwide new equipment for Otis Elevator.
Gen2 elevators with regen drives were used in the Proximity Hotel in Greensboro, N.C., the only LEED Platinum hotel in the U.S. “The energy aspect was a huge factor” in the choice of MRL and the Gen2 regenerative drive system, says Jeff Kennedy, general manager for Quaintance-Weaver Services, the GC arm of hotel operator Quaintance-Weaver Restaurants & Hotels. Kennedy says that, while it has been difficult to get an exact measurement on energy savings due exclusively to the use of the regen drive, he has been assured by the mechanical engineer he contracts with that “the elevators are the single largest energy saver in the building.”
Newer MRLs such as Schindler Elevator Corp.’s 3300 and Kone’s EcoSpace are designed specifically for low-rise buildings. Schindler claims the cab of its 3300 model is 5% larger than a traditional MRL or hydraulic elevator. ThyssenKrupp’s synergy line is available in six different designs to fit virtually any building, offering speeds ranging from 150 to 500 feet per minute.
In low-rise buildings, the first cost of an MRL is approximately 10% more than its hydraulic counterpart, says Michael Landis, vice president of Schindler Elevator Corp. But since the contractor doesn’t have to build a machine room or electrical closet with air conditioning, the savings can run to roughly $10,000, he says.
Latest Trends in Elevators and Escalators
- The latest machine-roomless elevators are designed specifically for low-rise buildings.
- More advanced destination dispatch technology saves energy and allows building owners to deliver a higher level of personalized elevator service and security.
- LED lighting in cabs reduces heat loss and increases lifespan.
- Urea formaldehyde-free elevator panels improve indoor air quality.
- Regenerative drives transfer unused energy back into the building’s electrical grid for other uses.
- Remote monitoring ensures seamless adjustments and repairs and minimizes costly elevator down time.
- Variable-speed escalators conserve energy by automatically slowing down during off-peak usage periods.
DESTINATION DISPATCH GETS PERSONAL
Destination dispatch technology is a sophisticated traffic management tool that has undergone recent improvements. Such systems do away with traditional up/down buttons; instead, passengers use keypads or interactive touchscreens to register floor calls. They are then assigned to specific cars, minimizing the number of starts and stops required as well as wait and travel times. Newer systems such as Schindler’s Personal Occupant Requirement Terminal (PORT) utilize card-reading technology through radio frequency waves.
Destination-dispatch can be used to put individual cars in standby mode when they’re not needed, shutting down lighting and ventilation. Building owners can use it to maintain security; for instance, they could restrict access by delivery people. People with special needs are discreetly assigned to elevators that can accommodate them. In hospitals, destination dispatch automatically directs medical personnel to elevators sized for gurneys or crash carts.
Building management firm Golub & Co. installed a destination dispatch system as part of an18-month elevator modernization project at 680 N. Lake Shore Drive in Chicago. Over the course of a single weekend, Schindler ID terminals and controllers were interfaced with existing elevator controllers, offering an immediate improvement in efficiency. The existing elevators were refurbished and components were replaced as necessary.
Taking the elevators out of service would have been a major inconvenience for the building’s medical and office tenants, says Tim Conway, general manager for Golub. Working with VTS consultant Desmond Associates of Carpentersville, Ill., the firm chose Schindler for the project “because they were able to put the destination technology on the front end,” says Conway. End users didn’t notice when a car was out of service because the destination interface was there to direct them to the right elevator.
“We’re trending toward about a 23% reduction in energy usage,” Conway says. “We’ve also done some traffic studies with wait time and destination time, and those have improved closer to 50%. It’s incredible.”
Huleis says that with destination dispatch systems, control panels can be placed anywhere in the building, eliminating in-cab controls. “This feature is mostly useful on high-rise buildings,” he says.
Double-deck elevators have traditionally been used in very tall buildings because they can move large numbers of people with fewer cabs. Typically, the top deck serves the even-numbered floors, the bottom deck the odd-numbered floors.
“Double-deckers can reduce the need for space in the core of a building from 30-45%,” says Otis’s Pulling. While they can be installed as part of a modernization, they require significant project management and front-end planning, which is why they’re more common in new construction “where you design to a specific core requirement,” he says.
A look to the future: Schindler is currently developing a three-deck elevator.
GETTING DESIGN CONSIDERATIONS RIGHT
It may seem obvious, but elevators should always be designed based on the intended use of the building and the volume of traffic anticipated. “Traffic patterns are dependent on each floor’s population and whether the building is open for business 24/7, such as a hotel versus an office building,” says Brad Nemeth, director of sustainability for ThyssenKrupp Elevator Americas.
High-rise buildings may require customized engineering to compensate for elevator speeds approaching 2,000 meters (about 6,500 feet) per minute. “At these speeds,” Nemeth says, “aerodynamic considerations must be factored in along with pressure differentials above and below the elevator cab, which can produce vibration and excessive noise.”
In terms of energy efficiency, architect Brian Sipes, AIA, LEED AP, principal of Zehren & Associates in Avon, Colo., says MRLs perform as advertised, but their higher first cost is justifiable depending on how often the elevator is going to be used. “If it’s less than once a day, there’s no payback,” he says. “If it’s frequently, MRLs are an easy sell if you can prove the return on investment.”
One caveat: If a client wants high-end elevator finishes, MRLs may not be an option. Many of Zehren’s projects are ski and golf resorts where custom millwork on the walls and stone floors are a must, partly for aesthetics and partly to shield against damage from ski boots and golf cleats. “In those cases we have to go with traditional hydraulic elevators because they don’t have the design or weight limitations of an MRL,” Sipes says. BD+C
Related Stories
Mass Timber | Jan 27, 2023
How to set up your next mass timber construction project for success
XL Construction co-founder Dave Beck shares important preconstruction steps for designing and building mass timber buildings.
Sports and Recreational Facilities | Jan 26, 2023
Miami’s motorsport ‘country club’ to build sleek events center
Designed by renowned Italian design firm Pininfarina and with Revuelta as architect, The Event Campus at The Concours Club will be the first and only motorsport-based event campus located within minutes of a major metro area.
Student Housing | Jan 26, 2023
6 ways 'choice architecture' enhances student well-being in residence halls
The environments we build and inhabit shape our lives and the choices we make. NAC Architecture's Lauren Scranton shares six strategies for enhancing well-being in residence halls.
K-12 Schools | Jan 25, 2023
As gun incidents grow, schools have beefed up security significantly in recent years
Recently released federal data shows that U.S. schools have significantly raised security measures in recent years. About two-thirds of public schools now control access to school grounds—not just the building—up from about half in the 2017-18 school year.
AEC Tech Innovation | Jan 24, 2023
ConTech investment weathered last year’s shaky economy
Investment in construction technology (ConTech) hit $5.38 billion last year (less than a 1% falloff compared to 2021) from 228 deals, according to CEMEX Ventures’ estimates. The firm announced its top 50 construction technology startups of 2023.
Sports and Recreational Facilities | Jan 24, 2023
Nashville boasts the largest soccer-specific stadium in the U.S. and Canada
At 30,105 seats and 530,000 sf, GEODIS Park, which opened in 2022, is the largest soccer-specific stadium in the U.S. and Canada. Created by design firms Populous and HASTINGS in collaboration with the Metro Nashville Sports Authority, GEODIS Park serves as the home of the Nashville Soccer Club as well as a venue for performances and events.
Concrete | Jan 24, 2023
Researchers investigate ancient Roman concrete to make durable, lower carbon mortar
Researchers have turned to an ancient Roman concrete recipe to develop more durable concrete that lasts for centuries and can potentially reduce the carbon impact of the built environment.
Architects | Jan 23, 2023
PSMJ report: The fed’s wrecking ball is hitting the private construction sector
Inflation may be starting to show some signs of cooling, but the Fed isn’t backing down anytime soon and the impact is becoming more noticeable in the architecture, engineering, and construction (A/E/C) space. The overall A/E/C outlook continues a downward trend and this is driven largely by the freefall happening in key private-sector markets.
Multifamily Housing | Jan 23, 2023
Long Beach, Calif., office tower converted to market rate multifamily housing
A project to convert an underperforming mid-century office tower in Long Beach, Calif., created badly needed market rate housing with a significantly lowered carbon footprint. The adaptive reuse project, composed of 203,177 sf including parking, created 106 apartment units out of a Class B office building that had been vacant for about 10 years.
Hotel Facilities | Jan 23, 2023
U.S. hotel construction pipeline up 14% to close out 2022
At the end of 2022’s fourth quarter, the U.S. construction pipeline was up 14% by projects and 12% by rooms year-over-year, according to Lodging Econometrics.