Cities and airport operators are using innovative schemes to finance ambitious terminal projects at U.S. airports. The ultimate goal: improved passenger satisfaction.
The $4 billion renovation of New York City’s LaGuardia Airport is the first major U.S. aviation project delivered using a public-private partnership (P3) model. The airport’s new 1.3 million-sf Central Terminal B, which will replace the existing 1964 terminal building, is being led by a design-build joint venture of Skanska and Walsh Construction. WSP USA and HOK are the design partners.
“Given the extremely tight site and aggressive schedule, it would be extremely challenging to deliver this project through a traditional approach,” says Dwight Pullen, Director of Skanska’s Aviation Center of Excellence. “Our design and phasing solution worked a lot more seamlessly under a P3 arrangement.”
At Los Angeles International Airport, the new $1.6 billion Midfield Satellite Concourse, which is part of a wider $14 billion overhaul at LAX, is also being delivered using a P3 approach. Corgan and Gensler are collaborating on the design. A Turner-PCL joint venture is building the 12-gate concourse, which is scheduled to open in 2019.
“P3 is increasingly attractive to municipalities and airport operators, and I foresee a number of airports seizing the P3 opportunity in the next several years,” says Robert Chicas, AIA, LEED AP, Director of Aviation + Transportation in HOK’s New York shop.
They may not have a choice. According to Airports Council International–North America, airports will generate only about half the financing they’ll need to meet the estimated $100 billion infrastructure investment required through 2021. Combine the shortage of funds for capital infrastructure needs with uncertainty about whether the federal government will increase the passenger facilities charge, which is used for facility improvements, and “it’s a market ripe for new solutions,” says Pullen.
MAKING TERMINALS CUSTOMER-CENTRIC
Airports are creating hospitality-rich environments for passengers and visitors. “Customer satisfaction has bubbled to the top as one of the highest priorities at every airport in the country,” says Chicas. “All airlines see the terminals they operate in as an extension of their brand. They know the strength and perception of that brand is key to their commercial success.”
To adapt to changes in regulations and requirements, terminals are being designed as flexible environments with few columns, broad floor plates, clear lines of circulation, and lots of natural light. Air travelers are also demanding state-of-the-art technology and abundant amenities to enhance travel experience—or at least reduce some of the anxiety.
“Airlines and airports are working to put more control into passenger hands to streamline the process for experienced travelers,” says Wilson Rayfield, AIA, NCARB, LEED AP, Executive Vice President of Aviation with Gresham, Smith and Partners. His firm is helping Southwest Airlines integrate self-tagging kiosks in multiple locations across the SWA network.
Stuart Garrett, Project Manager in the Aviation and Federal Group at Burns & McDonnell, agrees. “People want to feel like they’re more in control of their journey. It makes them more comfortable. And less-stressed people spend more money,” he says.
ALSO SEE: BD+C Giants 300 airport rankings
Top 30 airport architecture firms
Top 30 airport engineering firms
Top 40 airport construction firms
FOCUS ON REVENUE-GENERATING ACTIVITIES
Terminal designers are creating intuitive layouts and passenger flow that increase touch points around concession and retail offerings.
“With the tightening of connection times for domestic travel in the U.S., there has been an increased focus on grab-and-go concession opportunities and interactive spaces where passengers can plug in, recharge, and order food while still maintaining close proximity to their boarding gates,” says Thomas Haag, PE, National Director of Aviation with Walsh Group.
At the same time, airport operators recognize the need to accommodate a growing population of older flyers who need more time and assistance to pass through security and board their flights. “If it takes 15 more minutes for a person to board a flight, over the course of a day, that’s a huge impact on gate and aircraft utilization, which impacts airports and airlines,” says GS&P’s Rayfield. His team is working with the Airport Cooperative Research Program to develop a wayfinding guidebook for airport operators and planners to assist elderly and disabled air travelers.
Most AEC firms that specialize in terminal work see nothing but blue skies for the foreseeable future. “It’s obviously a great market for those of us who design and build airport projects, but it’s going to be a challenge to keep up with it all,” says Jay Fraser, VP and General Manager of Turner Construction Company’s Aviation Group.
SEE ALL 2017 GIANTS 300 RANKINGS
Related Stories
Giants 400 | Aug 7, 2015
RECONSTRUCTION AEC GIANTS: Restorations breathe new life into valuable older buildings
AEC Giants discuss opportunities and complications associated with renovation, restoration, and adaptive reuse construction work.
Giants 400 | Aug 6, 2015
GREEN BUILDING GIANTS: Green building movement hits a new plateau, but the underlying problems remain
Today, the green building movement is all about eliminating toxic substances in building materials and systems and, for manufacturers, issuing environmental and health product declarations. Whether these efforts will lead to healthier products and building environments remains an open question.
Giants 400 | Aug 6, 2015
BIM GIANTS: Robotic reality capture, gaming systems, virtual reality—AEC Giants continue tech frenzy
Given their size, AEC Giants possess the resources and scale to research and test the bevy of software and hardware solutions on the market. Some have created internal innovation labs and fabrication shops to tinker with emerging technologies and create custom software tools. Others have formed R&D teams to test tech tools on the job site.
Giants 400 | Aug 6, 2015
GIANTS 300 REPORT: Top 75 Healthcare Construction Firms
Turner, McCarthy, and Skanska top Building Design+Construction's 2015 ranking of the largest healthcare contractors and construction management firms in the U.S.
Giants 400 | Aug 6, 2015
GIANTS 300 REPORT: Top 80 Healthcare Engineering Firms
AECOM, Jacobs, and Burns & McDonnell top Building Design+Construction's 2015 ranking of the largest healthcare engineering and engineering/architecture firms in the U.S.
Giants 400 | Aug 6, 2015
GIANTS 300 REPORT: Top 115 Healthcare Architecture Firms
HDR, Stantec, and Perkins+Will top Building Design+Construction's 2015 ranking of the largest healthcare architecture and architecture/engineering firms in the U.S.
Giants 400 | Aug 6, 2015
HEALTHCARE AEC GIANTS: Hospital and medical office construction facing a slow but steady recovery
Construction of hospitals and medical offices is expected to shake off its lethargy in 2015 and recover modestly over the next several years, according to BD+C's 2015 Giants 300 report.
Giants 400 | Aug 6, 2015
GIANTS 300 REPORT: Top 75 Construction Management Firms
Jacobs, AECOM, and Hill International head Building Design+Construction's 2015 ranking of the largest construction management and project management firms in the United States.
Giants 400 | Aug 6, 2015
GIANTS 300 REPORT: Top 100 Contractors
Turner Construction and Whiting-Turner Contracting top Building Design+Construction's 2015 ranking of the largest contractors in the United States.
Giants 400 | Aug 5, 2015
CONSTRUCTION GIANTS: Economists hedge their bets on prospects for nonresidential construction
Leading economists expect spending for nonresidential construction to rise in 2015 by somewhere in the 6.4–7.7% range, and remain strong in 2016, according to BD+C's 2015 Giants 300 report.