Wyoming Capitol Square renovation project is all about the details

Reconstruction Awards

Wyoming Capitol Square renovation project is all about the details

The Wyoming Capitol Square project has won a Gold Award in BD+C's 2020 Reconstruction Awards.


By David Malone, Associate Editor | December 14, 2020
Wyoming Capitol Square at night

Photo: Dan Schwalm Photography

Originally built in 1886, the Wyoming Capitol Square has recently undergone a renovation project of the 129,539-sf Historic State Capitol, the 360,862-sf Herschler Office Building, and an underground connector gallery that serves as a tunnel for the Capitol Square. 

The $300 million project replaced outdated building systems, added critical life safety infrastructure, and addressed public space needs, especially for larger meeting rooms. The Herschler Building was remodeled and expanded by 56,000 sf to house state agencies and elected officials. The atrium on the north side of the building was removed to improve and restore views to the Capitol.

The Capitol Extension, a below-grade building that connects the Capitol to the Herschler Building, has been expanded by 28,000 sf to accommodate public space needs that could not be met in the Capitol. These spaces include large public meeting rooms, a 238-seat auditorium, a visitor’s center, and a student learning center. 

 

Wyoming Capitol House of Representatives ChambersPhoto: Dan Schwalm Photography.

 

A new below-grade utility plant, which serves five state buildings, was also included to replace the aging central utility plant originally located in the connector. In order to move the MEP systems below grade, existing rubble, masonry, and concrete footings needed to be repaired. The build team coordinated and installed over 600 micropyles with shotcrete foundations to stabilize existing foundations and allow MEP systems to run below footings without destabilizing them. 

The project’s attention to detail sets it apart from many other renovation and restoration efforts. Many small details were restored and recreated by hand. 

 

Hand restored paintings in the Wyoming Capitol

 

For example, previous restoration efforts painted over many decorative paintings and details within the building. The build team wanted to restore these details to their previous luster. This meant removing the paint layer by layer to expose the original decorative paint schemes and colors, and then recreating and restoring them. An original painting at the top Capitol Rotunda (above) was slowly revealed and then hand painted to recreate the original work. 

Murals that had previously been painted over and forgotten about were rediscovered on six vault doors. After being restored to their original state, the murals became a highlight of the project as they were not previously documented and had not been seen by the public for decades. Other interior efforts included restoring original marble floors and elaborate woodwork throughout the building.

 

Mural on vault door in Washington CapitolPhoto: Girt Communications.

 

The exterior of the building also required meticulous restoration efforts. The Capitol dome was regilded in gold while hand carved stone elements that had been deteriorated by weather over the last 100+ years were recreated by hand. The replacement and restoration of the original sandstone required the reopening of the original quarry where the stone was mined in Rawlins, Wyo. The quarry had been closed for over 100 years but reopening it allowed the build team to get the exact same stone as was used in the original construction.

 

Restoring exterior carved stone elementsPhoto: Girt Communications.

 

The building’s original architect created four niches in the Capitol Rotunda that were meant to be adorned by statues, but the vision never came to fruition. The project sought to change that. Delissalde, a sculptor, was commissioned to create four statues to place in these niches and complete the original vision of the architect from 130 years ago.

 

Capitol Rotunda in Wyoming Capitol with new statues in nichesPhoto: Dan Schwalm Photography.

 

The project not only needed to accommodate a large construction crew (over 3,900 people were employed to work on various components over the four-year project), but also over 300 state employees that worked on-site in the Herschler Building. The Herschler project was phased in a way that allowed for half of the building to remain occupied while the other have was renovated and the expansion was built. When the first phase was completed, the employees were moved to the new half while construction commenced on the second phase.

The Wyoming Capitol Square project is believed to be the largest of its kind in Wyoming history.

 

PROJECT INFORMATION: Size 490,401 sf  Construction start and finish April 2016 to July 2019 Cost $252,600,000 Delivery method CM/Risk, negotiated

BUILDING TEAM: Submitting firm JE Dunn Construction Owner/Developer State of Wyoming Architect HDR Architecture SE Silman MEP Loring Engineering GC JE Dunn Construction Program Manager MOCA Systems

Related Stories

Adaptive Reuse | Dec 17, 2020

A train engine repair building is turned into an innovation center that’s part of a massive riverfront redevelopment in Pittsburgh

The adaptive reuse of the Roundhouse is the latest step forward for Hazelwood Green.

Urban Planning | Dec 6, 2020

Ford lays out plans for mobility innovation district in Detroit

Its centerpiece is an abandoned train depot whose architecture and decay reflect two sides of this city’s past.

Multifamily Housing | Dec 4, 2020

The Weekly show: Designing multifamily housing for COVID-19, and trends in historic preservation and adaptive reuse

This week on The Weekly show, BD+C editors spoke with leaders from Page & Turnbull and Grimm + Parker Architects about designing multifamily housing for COVID-19, and trends in historic preservation and adaptive reuse

Giants 400 | Dec 3, 2020

2020 Reconstruction Sector Giants: Top architecture, engineering, and construction firms in the U.S. building reconstruction and renovation sector

Gensler, Jacobs, and STO Building Group head BD+C's rankings of the nation's largest reconstruction sector architecture, engineering, and construction firms, as reported in the 2020 Giants 400 Report.

Adaptive Reuse | Oct 26, 2020

Mall property redevelopments could result in dramatic property value drops

Retail conversions to fulfillment centers, apartments, schools, or medical offices could cut values 60% to 90%.

Reconstruction & Renovation | Oct 26, 2020

New guidelines for replacing windows without removing exterior brick veneer

The guidelines cover residential and light commercial buildings of less than four stories above grade.

Mixed-Use | Oct 19, 2020

Commonwealth Pier revitalization project begins construction in Boston’s Seaport

CBT, in collaboration with Schmidt Hammer Lassen Architects designed the project.

Reconstruction & Renovation | Sep 30, 2020

SOM reimagines former Cook County Hospital into mixed-use destination

The project is the first phase of a proposed $1 billion redevelopment plan for the area in Chicago.

boombox1
boombox2
native1

More In Category

Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.



Brick and Masonry

A journey through masonry reclad litigation

This blog post by Walter P Moore's Mallory Buckley, RRO, PE, BECxP + CxA+BE, and Bob Hancock, MBA, JD, of Munsch Hardt Kopf & Harr PC, explains the importance of documentation, correspondence between parties, and supporting the claims for a Plaintiff-party, while facilitating continuous use of the facility, on construction litigation projects.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021