$150 million Amazon fulfillment center near Grand Rapids will be built on fast-paced 22-week schedule

Industrial Facilities

$150 million Amazon fulfillment center near Grand Rapids will be built on fast-paced 22-week schedule

The warehouse will be Amazon’s fourth in Michigan.


By David Malone, Associate Editor | June 25, 2018

COurtesy: flickr, Maryland GovPics

A new 2,225,000-sf Amazon fulfillment center near Grand Rapids, Mich., will be built on an expedited construction schedule set to start in September and complete 22 weeks later in February.

Ben Hur Construction and Ideal Contracting have partnered to build the $150 million facility. The warehouse will contain 8,100 tons of structural steel and 2,900 tons of joists. Ideal Contracting will be self-performing structural steel and miscellaneous work on the project with Iron Workers Local 25 in Detroit. Approximately 70 ironworkers will be on the project at any given time.

The Grand Rapids project will be Amazon's fourth warehouse in Michigan and first in the western part of the state.

 

See Also: ‘Amazon tax’ could slow Seattle’s construction boom

Related Stories

| May 22, 2014

Facebook, Telus push the limits of energy efficiency with new data centers

Building Teams are employing a range of creative solutions—from evaporative cooling to novel hot/cold-aisle configurations to heat recovery schemes—in an effort to slash energy and water demand.

| May 22, 2014

7 ways it pays to use BIM for data centers

Here’s where AEC firms and owners are getting the most bang for the buck when using BIM/VDC to coordinate data center projects.

| May 22, 2014

Big Data meets data centers – What the coming DCIM boom means to owners and Building Teams

The demand for sophisticated facility monitoring solutions has spurred a new market segment—data center infrastructure management (DCIM)—that is likely to impact the way data center projects are planned, designed, built, and operated. 

| May 20, 2014

Kinetic Architecture: New book explores innovations in active façades

The book, co-authored by Arup's Russell Fortmeyer, illustrates the various ways architects, consultants, and engineers approach energy and comfort by manipulating air, water, and light through the layers of passive and active building envelope systems.

| May 19, 2014

What can architects learn from nature’s 3.8 billion years of experience?

In a new report, HOK and Biomimicry 3.8 partnered to study how lessons from the temperate broadleaf forest biome, which houses many of the world’s largest population centers, can inform the design of the built environment.

| May 13, 2014

19 industry groups team to promote resilient planning and building materials

The industry associations, with more than 700,000 members generating almost $1 trillion in GDP, have issued a joint statement on resilience, pushing design and building solutions for disaster mitigation.

| May 11, 2014

Final call for entries: 2014 Giants 300 survey

BD+C's 2014 Giants 300 survey forms are due Wednesday, May 21. Survey results will be published in our July 2014 issue. The annual Giants 300 Report ranks the top AEC firms in commercial construction, by revenue.

| Apr 29, 2014

Best of Canada: 12 projects nab nation's top architectural prize [slideshow]

The conversion of a Mies van der Rohe-designed gas station and North Vancouver City Hall are among the recently completed projects to win the 2014 Governor General's Medal in Architecture. 

| Apr 29, 2014

USGBC launches real-time green building data dashboard

The online data visualization resource highlights green building data for each state and Washington, D.C.

| Apr 9, 2014

Steel decks: 11 tips for their proper use | BD+C

Building Teams have been using steel decks with proven success for 75 years. Building Design+Construction consulted with technical experts from the Steel Deck Institute and the deck manufacturing industry for their advice on how best to use steel decking.

boombox1
boombox2
native1

More In Category


Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021