2012 Reconstruction Award Platinum Winner: Building 1500, Naval Air Station Pensacola Pensacola, Fla.

2012 Reconstruction Award Platinum Winner: Building 1500, Naval Air Station Pensacola Pensacola, Fla.

The Building Team, led by local firms Caldwell Associates Architects and Greenhut Construction, had to tackle several difficult problems to make the historic building meet current Defense Department standards having to do with anti-terrorism, force protection, blast-proofing, and progressive collapse.


October 4, 2012
The historic naval facility at NAS Pensacola, Fla., required extensive renovatio
The historic naval facility at NAS Pensacola, Fla., required extensive renovation to adhere to military anti-terrorism/force pro
This article first appeared in the October 2012 issue of BD+C.

Building 1500 at Naval Air Station Pensacola, Fla., was constructed in 1939 as an Army barracks. Over the years, it was renovated a number of times and at one time served as the home of the Navy School of Photography. When funding became available under the American Recovery and Reinvestment Act of 2009, the Naval Facilities Engineering Command put together a design-build best value team to turn the vacant building into NAS Pensacola’s Base Command Headquarters.

The Building Team, led by local firms Caldwell Associates Architects and Greenhut Construction, had to tackle several difficult problems to make the historic building meet current Defense Department standards having to do with anti-terrorism, force protection, blast-proofing, and progressive collapse. Due to its location in a designated high-wind zone, the building also had to meet stringent wind load requirements.

Addressing anti-terrorism, force protection, and progressive collapse

Structural analysis of the exterior walls, which were constructed of terra cotta and finished with cement, determined that they could not meet anti-terrorism/force protection blast requirements or applicable wind-load standards. Given that the exterior could not be touched, AT/FP remedies had to be made from the inside out. The Building Team reinforced the interior face of the wall with six-inch-deep 18-gauge studs anchored into the terra cotta wall. Steel tracks at the base and head of the wall transferred loads into the existing concrete frame.

PROJECT SUMMARY


BUILDING 1500, NAVAL AIR STATION PENSACOLA
Pensacola, Fla.

Building Team
Submitting firm: Caldwell Associates Architects (architect)
Owner: Department of the Navy, NAVFAC Southeast
Interior design: Simpson Design Group
Structural engineer: Berube-Leonard
Mechanical/plumbing engineer: MEP Engineering Solutions
Electrical engineer: Klocke & Associates
Civil engineer: Fabre Engineering & Surveying
Fire protection engineer: FireLogix Engineering
Blast structural engineer: Simpson Gumpertz & Heger
General contractor: Greenhut Construction Co.

General Information
Size: 69,565 sf
Construction cost: $11,218,898
Construction time: October 2009 to November 2011
Delivery method: Design-build best value

Next, the team took on the replacement of the windows on the exterior walls. Any new windows had to be “historically consistent” with the original double-hung wood sash windows. The Building Team got approval to use aluminum sash windows that matched the sash profiles and glass-to-frame ratios, and a manufacturer (Graham Architectural Products) was able to produce windows that met AT/FP blast-resistance requirements.

Installing the windows to meet AT/FP demands was the next hurdle. Historic considerations dictated that the new windows be installed to the depth of the original windows in the existing masonry openings; however, doing so would not provide sufficient anchorage for blast and wind loads.

The Building Team devised a scheme that involved installing a steel frame and plate system on the interior side of the exterior wall to anchor the windows. They bolted tube steel jamb frames into the concrete frame at top and bottom and welded tube steel head and sill frames to the jamb pieces. Steel plate was welded to these frames to extend into the existing masonry window at the correct depth to allow the windows to be attached consistent with historic standards.

As for progressive collapse, the team determined that conventional steel or concrete reinforcement would be cumbersome and consume valuable space within the building shell, so they went to a carbon fiber reinforcement wrap over the existing concrete frame components, taking care not to allow penetrations into the system from other building infrastructure elements.

Not only is Building 1500 historic in nature, so is the archaeological site on which it sits. Early in construction, when post holes were being dug for the construction fence, the on-site archeologist consultant (required by the Navy) found artifacts of interest.

A full-blown archeological dig would have played havoc with the ARRA-based budget. As an alternative, the team dug “test pits” in a 5x5-meter grid across the site. Only a few areas requiring further excavation were discovered, and the project was able to proceed on schedule.

BD+C Reconstruction Awards Judge Daniel Moser, PE, summarized the project this way: “It was a really unique solution to solving the blast requirements while preserving the historic aspect of the building.” +

Related Stories

MFPRO+ New Projects | Oct 30, 2024

BIG’s One High Line finally reaches completion in New York City’s West Chelsea neighborhood

One High Line, a luxury residential project spanning a full city block in New York’s West Chelsea neighborhood, reached completion this summer following years of delays related to investor lawsuits. 

Urban Planning | Oct 30, 2024

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.

MFPRO+ New Projects | Oct 30, 2024

Luxury waterfront tower in Brooklyn features East River and Manhattan skyline views

Leasing recently began for The Dupont, a 41-story luxury rental property along the Brooklyn, N.Y., waterfront. Located within the 22-acre Greenpoint Landing, where it overlooks the newly constructed Newtown Barge Park, the high-rise features East River and Manhattan skyline views along with 20,000 sf of indoor and outdoor communal space.

Libraries | Oct 30, 2024

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

Resiliency | Oct 29, 2024

Climate change degrades buildings slowly but steadily

While natural disasters such as hurricanes and wildfires can destroy buildings in minutes, other factors exacerbated by climate change degrade buildings more slowly but still cause costly damage.

Office Buildings | Oct 29, 2024

Editorial call for Office Building project case studies

BD+C editors are looking to feature a roundup of office building projects for 2024, including office-to-residential conversions. Deadline for submission: December 6, 2024.

Healthcare Facilities | Oct 28, 2024

New surgical tower is largest addition to UNC Health campus in Chapel Hill

Construction on UNC Health’s North Carolina Surgical Hospital, the largest addition to the Chapel Hill campus since it was built in 1952, was recently completed. The seven-story, 375,000-sf structure houses 26 operating rooms, four of which are hybrid size to accommodate additional equipment and technology for newly developed procedures. 

Multifamily Housing | Oct 28, 2024

A case for mid-rise: How multifamily housing can reshape our cities

Often referred to as “five-over-ones,” the mid-rise apartment type is typically comprised of five stories of apartments on top of a concrete “podium” of ground-floor retail. The main criticism of the “five-over-one” is that they are often too predictable.

Sports and Recreational Facilities | Oct 24, 2024

Stadium renovation plans unveiled for Boston’s National Women’s Soccer League

A city-owned 75-year-old stadium in Boston’s historic Franklin Park will be renovated for a new National Women’s Soccer League team. The park, designed by Fredrick Law Olmsted in the 1880s, is the home of White Stadium, which was built in 1949 and has since fallen into disrepair.

Laboratories | Oct 23, 2024

From sterile to stimulating: The rise of community-centric life sciences campuses

To distinguish their life sciences campuses, developers are partnering with architectural and design firms to reimagine life sciences facilities as vibrant, welcoming destinations. By emphasizing four key elements—wellness, collaboration, biophilic design, and community integration—they are setting their properties apart. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021