3D scanning solution brought in to beat the heat on challenging fuel pipe demolition and replacement project

Sponsored Content BIM and Information Technology

3D scanning solution brought in to beat the heat on challenging fuel pipe demolition and replacement project

Acensium is an engineering consulting services firm with a focus on material handling retrofit projects and 3D scanning for as-built reality capture.


By Jason Schwartz, Principal at Acensium | August 28, 2017
3D model of a project

3D model of project shown in Navisworks, models developed in Cyclone and Revit.

Plant Bowen, a coal-fired power station owned by Georgia Power Company in Euharlee, Ga., needed to undergo an ambitious demolition and replacement of its Unit-4 fuel pipe. Coal dust, which is the consistency of talcum powder, is blown through the fuel pipe from the pulverizer for ignition. In order to tackle the challenging and inherently dangerous project, Georgia Power called upon Acensium to provide engineering support and take on the piping digitization to support demolition and installation/construction teams (Contractor: Zachary; Fabrication: JMS). Among the main issues the project faced was that the fuel pipe was confined by structural members, floor members, plant equipment, and the boiler itself with little clearance to perform the work. The looming question was how to remove the old pipe from the building and get the new pipe installed.

Acensium is an engineering consulting services firm with a focus on material handling retrofit projects and 3D scanning for as-built reality capture, originally founded in 2003 in Denver, Colorado. The team was able to successfully assess the difficult project and plot a course of action by tapping into its expertise providing engineering and intellectual services, operations, consulting and engineering support primarily for the power, steel and paper industries throughout the United States.

 

Cross section of single pulverizer outlet. FARO point cloud in Recap using the intensity filter.

 

CHALLENGES

The multi-million dollar project—the demolition and replacement of the #4 fuel pipe—included millions of dollars in erected scaffolding alone, as well as a 141-man crew, 7-day-a-week work schedule and 35 days of plant “outage time” to do the work within. Plans specified a completion timeframe of one year from the planning stage.

What made this project particularly challenging was that it necessitated working next to a boiler with an ambient temperature of 120 degrees F. The facility was built around the equipment so everything was a tight fit.

  • Our first job for Bowen had an area of concern 20ft X 20ft x 20ft.
  • This Bowen fuel pipe project encompasses a huge volume (sqft) (and a huge amount of data) 80ft x 300ft x 300ft.

Furthermore, this was a high-heat/high-hazard environment with high noise levels and large amounts of vibration in addition to the huge volume to scans. The complex project required specialized safety training, insurance requirements and background checks as it was not a standard industrial environment, including the need for scans to be taken just feet from a boiler with an internal temperature of over 1500 degrees F.

 

SOLUTIONS

As a result of recent successes on multimillion dollar projects and digital visualization for Georgia Power, plant management requested Acensium’s involvement during the planning phase. Acensium demonstrated what would be able to be done with example scans to illustrate for project leads what was possible. Georgia Power recognized that the project could not be accomplished without 3D scanning project control and so Acensium utilized the FARO® Focus Laser Scanners and SCENE Software.

Had more traditional methods been used instead, the process would have included arduous and time-consuming tasks of measurements, estimation and guesswork to determine what changes had been made since the original design from decades ago. As a typical project team cannot simply look at 2D as-built drawings and understand the full scope of what is going on, the use of 3D scanning gives insight to the whole team. With a building constructed around the equipment, clearances are at a minimum. Understanding the operation and arrangement of every pipe and support was crucial for project success.

With a facility that has been literally built around installed power plant equipment in 1975, everything had to be mapped for success. There were no clearances designed-in for removal or addition of components as you would see in a facility built before equipment is installed. Every support beam, pipe, bracket and bolt needed to be accounted for to ensure that components can come out of (and into) the facility as needed. For example, a 50-foot pipe may need to be replaced in 10-foot sections instead of the original 50-foot solid length. There may simply be no way to get 50 feet of pipe into the building if not sectioned out. To that end, FARO 3D scanning technology, coupled with a highly skilled team, was paramount.

Jason Adkins, Principal at Acensium, says, “The skills and experience of personnel is key. You have to have great equipment, but behind that equipment is an engineering mind. To be able to provide engineering consulting and support effectively on jobs like this, it takes a high-level industry expert. The 3D scanning, modeling and visualization then allows you to communicate that expertise to every project stakeholder.”

 

Hoist rail beam spacing shown in Navisworks, models developed in Cyclone and Revit.

 

The Modeling Aspect

Dynamic visualization was used to show parts moving in and out of the constricted project area. The modeling was a mix of clash detection and project process planning. Visualization was also used to enhance communication between project stakeholders.

It should be noted that Acensium was called in late in the process. Typically, Acensium is present from day one of planning. Scans started only 48 hours before the scaffolding build-out began. The scanning had to be completed before the scaffolding blocked key viewpoint angles. Acensium’s team worked around the clock to get the initial as-built scanning done. Modeling and visualization support throughout demolition and installation processes allowed the team to account for unforeseen issues. Additional scans of specific areas can be taken, if needed, to resolve an issue.

 

Workflow Details

FARO Focus hardware and settings dealt with constant high vibrations. Care had to be taken in a high-heat environment with human exposure-time. FARO equipment operated for hours in a high-heat environment at 120 degrees F to produce key scans.

 

RESULTS

Final Deliverables

Final deliverables included model point-cloud overlay, engineering support and project control throughout the project — planning through completion.

 

Time and Costs Savings

While it is nearly impossible to measure exactly the time saved, it can safely be stated that if modeling had not been performed, many unforeseen issues would have occurred. For instance, it takes 22 man-hours to weld one joint. Rigging a pipe to be picked up takes 12 man-hours. If done incorrectly, it has to be disconnected and another pipe rigged. Easily, 1500+ man-hours were saved in avoided risk. Without visualization, 20% cost overruns would not be unheard of. 

 

CONCLUSION

Since 2009, Acensium has had numerous projects through Georgia Power, including six prior laser-scanning-based coal-handling projects at Bowen plant. As a testament to the client’s satisfaction with the work completed, recurring business through Bowen is expected to continue, with new projects currently in the works.

 

For more information, visit www.acensium.com.

 

Related Stories

BIM and Information Technology | Jun 7, 2016

6 ways smart AEC firms are using computational design methods

Rapid prototyping, custom plug-ins, and data dashboards are among the common applications for computational design.

BIM and Information Technology | May 20, 2016

AIA and Autodesk introduce new feature to automate 2030 Commitment reporting data

The new automated connection will allow the more than 350 AIA 2030 committed firms to report their project and portfolio performance to the DDx directly from Autodesk Insight 360.

AEC Tech | May 10, 2016

Thornton Tomasetti launches new tech company

TTWiiN initially features six products and will add more via its own incubator.

Sponsored | BIM and Information Technology | May 10, 2016

Advanced laser scanning technology supports data collection and modeling efforts for Missouri’s Iatan 1 Power Plant

For the installation of a new heat exchanger, the power division of Black & Veatch contracted an engineering firm to laser scan the site, make a piping model in Autodesk® Revit®, and export it into AutoCAD® to deliver results.

AEC Tech | May 9, 2016

Is the nation’s grand tech boom really an innovation funk?

Despite popular belief, the country is not in a great age of technological and digital innovation, at least when compared to the last great innovation era (1870-1970).

Big Data | May 5, 2016

Demand for data integration technologies for buildings is expected to soar over the next decade

A Navigant Research report takes a deeper dive to examine where demand will be strongest by region and building type. 

BIM and Information Technology | May 2, 2016

How HDR used computational design tools to create Omaha's UNO Baxter Arena

Three years after writing a white paper about designing an arena for the University of Nebraska Omaha, HDR's Matt Goldsberry says it's time to cherry-pick the best problem-solving workflows.

Drones | Apr 25, 2016

The Tremco SkyBEAM UAV is the first to be approved by the FAA for nighttime commercial operation

The SkyBEAM UAV is used for identifying energy leaks, rooftop damage, deteriorating façades, and safety issues without requiring scaffolding or cranes.

AEC Tech | Apr 15, 2016

Should architects learn to code?

Even if learning to code does not personally interest you, the growing demand for having these capabilities in an architectural business cannot be overlooked, writes computational design expert Nathan Miller.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021

Â