The American Institute of Architects (AIA) Academy of Architecture for Health (AAH) is recognizing seven projects with its Healthcare Design Awards for cutting-edge designs that help solve aesthetic, civic, urban, and social problems while also being functional and sustainable.
AIA/AAH bestows the awards annually for leading healthcare building design, healthcare planning, and healthcare design-oriented research. The seven projects were honored at the AIA AAH/ACHA Summer Leadership Summit in Chicago on Saturday, July 28.
The jury included:
David King, FAIA (Chair), SmithGroup JJR, Los Angeles
Tom Clark, FAIA, Clark/Kjos Architects, Portland, Oregon
Lari Diaz, AIA, KMD Architects, San Francisco
Walter Jones, AIA, The MetroHealth System, Cleveland
Patricia Malick, ARRAY Architects, Conshohocken, Pennsylvania
Paul Mankins, FAIA, substancearchitecture, Des Moines
David Ruthven, AIA, Philips Design, Cambridge, Massachusetts
Projects were awarded in the following categories:
Built: Less than $25 million in construction cost
Story County Medical Center Outpatient Unit Expansion, Nevada, Iowa
INVISION Architecture
Cameron Campbell
This one story addition and renovation to an existing hospital promotes a zoned healthcare campus. All outpatient services including primary care, therapy, rehabilitation and wellness, are consolidated in a state of the art facility focused on quality of care. Natural light, views and carefully crafted spaces enhance the patient experience. A sensitive use of new materials complement the existing palette but provide a more progressive and energy efficient design. The Ipé and terra cotta façades are woven into the interior design, complemented by additional natural materials and graphics that promote health and wellness. The design is adaptable and forward-thinking to accommodate growth and transition.
Jury statement: “An excellent functional plan using ‘on-stage, off-stage’ concept for clinics, and direct way-finding for patients. An appropriate and inviting shift to wellness for a small community that says, 'The highest quality care is delivered here.’”
Project Team:
Owner: Story County Medical Center
Architect: INVISION Architecture
Civil Engineer: Bishop Engineering
MEP Engineer: MODUS Engineering
Structural Engineer: KJWW
Landscape Architect: Ritland + Kuiper
General Contractor: Graham Construction
Photographer: Cameron Campbell
Project Information:
Construction cost or anticipated construction cost: $10 million
Building area or anticipated building area: 37,100 sf
Construction start date: March 2016
Substantial completion date: May 2017
Cameron Campbell
Maggie’s Centre Barts, London
Steven Holl Architects
Iwan Baan
Maggie’s Centre Barts is the latest facility for Maggie’s Centres, an organization that provides support to cancer patients and their families. The buildings are designed with the utmost care in design sensibility for their patients’ well-being. Located on a historic site in central London, the three-story centre was envisioned as a “vessel within a vessel within a vessel.” The structure is a branching concrete frame, wrapped in perforated bamboo inside and a façade of matte white glass with colored glass fragments, which wash the interior in shifting colored light.
Jury statement: “A delightful piece of candy among serious buildings. Interior has ethereal light, artful color based on musical notations layered with bamboo staircase of warmth and comfort—a healing environment.”
Project Team:
Owner: Maggie’s Cancer Caring Centres
Design architect: Steven Holl Architects
Mechanical Engineer: Arup
Climate Engineer: Arup
Civil Engineer: Arup
Landscape Architect: Darren Hawkes
Historic Building Adviser: Donald Insall Associates
Lighting Consultant: L'Observatoire International
CDM Coordinator: Floor Projects LLP
Code Consultant: Butler & Young
Planning Advisor: DP9
Cost Estimator: Gardiner & Theobald
Archaeology: MOLA (Museum of London Archaeology)
Glass Consultant: Arup
Construction Manager: Sir Robert McAlpine
Photographer: Iwan Baan
Project Information:
Construction cost or anticipated construction cost: Withheld by client
Building area or anticipated building area GSF: 6,534
Construction start date: June 2015
Substantial completion date: December 2017
Iwan Baan
Built: More than $25 million in construction cost
Lucile Packard Children’s Hospital Stanford, Palo Alto, Calif.
Perkins+Will and HGA Architects and Planners
Tim Griffith
This major campus transformation resulted in a technologically advanced, sustainable, and family-focused children’s hospital dedicated to supporting a child’s journey to health. The LEED Platinum building integrates innovative building systems to dramatically reduce energy and water consumption. By seamlessly linking gardens and terraces with nature and biophilic design elements in materials, art, and wayfinding, the design responds holistically to mind, body, and spirit. It is an “un-self-conscious” setting where staff, children, and families are comforted by its familiarity and inspired by opportunities for discovery—a place where learning nurtures healing.
Jury statement: “This children’s hospital focuses on the user's experience, with a comforting organic richness of spaces, a deep integration with nature with biophilic forms, and clear environmental partnership.”
Project Team:
Owner: Lucile Salter Packard Children's Hospital at Stanford
Executive Architect: HGA
Design Architect: Perkins+Will
Structural Engineer: Degenkolb
Civil Engineer: Sandis
MEPFP Engineer: Mazzetti
Low Voltage/Security: Teecom
Medical Equipment: RTKL
Landscape Design: AECOM (formerly EDAW)
Graphics/Signage: Kate Keating Associates
Art Consultant: Aesthetics, Inc
Construction Manager: DPR
Photographers: Tim Griffith (exterior); Vittoria Zupicich (interior)
Project Information:
Construction cost or anticipated construction cost: Withheld by owner
Building area or anticipated building area: 521,000
Construction start date: 2012
Substantial completion date: April 2018
Vittoria Zupicich
Memorial Sloan Kettering Monmouth (N.J.)
Architect: Perkins+Will
Halkin Mason Photography
This thoughtful renovation creates a light-filled, uplifting regional outpatient cancer center from what was once a dark, deep floorplate suburban office building. A three-story courtyard bisects the floorplate and follows the arc of the sun, enhancing patient arrival and wayfinding by increasing natural light and views. Upper-level glass-enclosed bridges connect patient areas and amplify the courtyard experience. Together, the client and design team produced a comfortable, memorable healing environment that combines signature Memorial Sloan Kettering brand elements, natural materials, and experiential design that recalls “a walk in the woods.”
Jury statement: “Department areas are planned to create exceptional patient experience as well as effective staff environment—infusion lounge (patient oriented to light, with soft screened glass/staff visualization).”
Project Team:
Owner: Memorial Sloan Kettering Cancer Center
Architectural & Interior Design: Perkins+Will
Civil Engineer/ Landscape Architect: Langan Engineering & Environmental Services
Structural Engineer: Stratford Engineering LLC
MEP FP Engineering: Syska Hennessy Group, Inc.
Lighting Design: SBLD Studio
AV Design: Shen Milsom & Wilke, Inc.
Door Hardware Consulting: Assa Abloy Door Security Solutions
Code Consulting: Code Consultants Professional Engineers, PC
Acoustic Consulting: Cerami & Associates
Elevator Consultant: VDA
Construction Management: Turner Construction Company
Photographer: Halkin Mason Photography
Project Information:
Construction cost or anticipated construction cost: $80 million
Building area or anticipated building area: 154,000 square feet
Construction start date: October 2014
Substantial completion date: January 2018
Halkin Mason Photography
Cedars Sinai Advanced Health Sciences Pavilion, Los Angeles
HOK
John Edward Linden Photography
The Advanced Health Sciences Pavilion (AHSP) is one of the first translational research facilities of its kind allowing outpatient care and research facilities to exist contiguously, enabling a new level of collaboration between physicians and researchers. Housing the Neuroscience and Heart Institutes, the LEED Gold facility is one of the West Coast’s largest and most advanced diagnostic, translational research and treatment facilities. The building is situated on a public edge of the Cedars-Sinai campus adjacent to its primary circulation spine. Due to this high profile location, the AHSP creates a new symbolic entry to the medical center. A gentle, curving façade invites visitors and provides a welcoming public face to the surrounding community.
Jury statement: “Interior public areas are elegantly detailed with enough articulation to give it human scale, wood accents and warm toned furnishings add warmth. Daylight is brought in judiciously to create uplifting clinical areas.”
Project Team:
Owner: Zeke Triana
Structural Engineer: John A. Martin & Associates
Civil Engineer: Psomas
Mechanical/Electrical/Plumbing Engineer: IBE Consulting Engineers
Landscape Architect: EPT Design
Parking Consultant: Walker Parking Consultants
General Contractor: Hathaway Dinwiddie
Photographer: John Edward Linden Photography
Project Information:
Construction cost or anticipated construction cost: Confidential
Building area or anticipated building area: 820,000 sq. ft.: 400,000 sq. ft. (parking garage); 420,000 sq. ft. (program)
Construction start date: October 2009
Substantial completion date: May 2013
John Edward Linden Photography
Renovations/Remodeled
Cedars-Sinai, Playa Vista Physician Office & Urgent Care, Playa Vista, Calif.
ZGF Architects
Tim Griffith
The Playa Vista clinic prototypes a new model of community-based care for Cedars-Sinai, and the design reflects the culture and aesthetic of its “Silicon Beach” neighborhood. New technology and innovative care models are fully integrated into the hyper-efficient, yet flexible floor plans, which are cloaked with an upscale palette of rich color and texture. Floor-to-ceiling windows along the southern façade flood the layered spaces with natural light, where custom, hospitality-style furnishings and finishes were developed using healthcare-compliant materials. The result is a welcoming, healing environment for all.
Jury statement: “A well designed efficient clinic open team center approach for staff. For patients, clear circulation and close in ‘living room’ waiting in each cluster, kudos for not creating the usual impersonal large waiting rooms! Nicely planned staff areas.”
Project Team:
Owner: Cedars-Sinai
MEP Engineer: Syska Hennessy Group
Structural Engineer: John A. Martin & Associates
Telecom / Data / IT: Vantage Technology Consulting
General Contractor: TIS Construction Services
Photographer: Tim Griffith
Project Information:
Construction cost or anticipated construction cost: $11,305,000
Building area or anticipated building area: 31,532 SF
Construction start date: February 2017
Substantial completion date: November 2017
Tim Griffith
Unbuilt
Eastside Health Clinic, Portland, Ore.
Ankrom Moisan Architects
Ankrom Moisan Architects
Eastside Health Center is a six-story building with a healthcare facility, retail, 34 transitional housing studios, 10 palliative care rooms, 118 SROs, and 12 respite care beds. Central City Concern will provide comprehensive case management and clinical services to support stabilization for rebuilding lives. Our concept explores the importance of ‘feeling at home’ and creating a sense of comfort, community, uplift and safety. The building was envisioned as a home for health and recovery, utilizing the referential gable that symbolizes the essence of home that happens to have a clinic.
Jury statement: “The scale of the building is human providing spaces that emphasize recovery over warehousing.”
Project Team:
Owner: Central City Concern
Civil Engineer: HHPR Consulting Engineers
Structural Engineer: Miller Consulting Engineers
Mechanical Engineer: Glumac
Plumbing: Glumac
Electrical: Glumac
Energy Modeling: Glumac
Lighting Design: Glumac
Landscape Architect: Shapiro Didway Landscape Architects
Renderings: Ankrom Moisan Architects
Project Information:
Construction cost or anticipated construction cost: $52 million
Building area or anticipated building area: 110,000 sq. ft.
Construction start date: February 2018
Substantial completion date or anticipated substantial completion date: November 2018
Ankrom Moisan Architects
Related Stories
| May 22, 2014
Big Data meets data centers – What the coming DCIM boom means to owners and Building Teams
The demand for sophisticated facility monitoring solutions has spurred a new market segment—data center infrastructure management (DCIM)—that is likely to impact the way data center projects are planned, designed, built, and operated.
| May 21, 2014
Evidence-based design practices for the palliative care environment
Palliative care strives to make patients comfortable as they are receiving treatment for a severe illness. As hospitals seek to avoid Affordable Care Act penalties for poor patient satisfaction, many expect this field to grow quickly.
| May 20, 2014
Kinetic Architecture: New book explores innovations in active façades
The book, co-authored by Arup's Russell Fortmeyer, illustrates the various ways architects, consultants, and engineers approach energy and comfort by manipulating air, water, and light through the layers of passive and active building envelope systems.
| May 20, 2014
Using fire-rated glass in exterior applications
Fire-rated glazing and framing assemblies are just as beneficial on building exteriors as they are on the inside. But knowing how to select the correct fire-rated glass for exterior applications can be confusing. SPONSORED CONTENT
| May 19, 2014
What can architects learn from nature’s 3.8 billion years of experience?
In a new report, HOK and Biomimicry 3.8 partnered to study how lessons from the temperate broadleaf forest biome, which houses many of the world’s largest population centers, can inform the design of the built environment.
| May 14, 2014
Prefab payback: Mortenson quantifies cost and schedule savings from prefabrication techniques
Value-based cost-benefit analysis of prefab approaches on the firm's 360-bed Exempla Saint Joseph Heritage Project shows significant savings for the Building Team.
| May 13, 2014
19 industry groups team to promote resilient planning and building materials
The industry associations, with more than 700,000 members generating almost $1 trillion in GDP, have issued a joint statement on resilience, pushing design and building solutions for disaster mitigation.
| May 11, 2014
Final call for entries: 2014 Giants 300 survey
BD+C's 2014 Giants 300 survey forms are due Wednesday, May 21. Survey results will be published in our July 2014 issue. The annual Giants 300 Report ranks the top AEC firms in commercial construction, by revenue.
| May 7, 2014
Design competition: $900,000 on the line in Las Vegas revitalization challenge
Las Vegas Mayor Carolyn Goodman wants your economic development ideas for remaking four areas within the city, including the Cashman Center and the Las Vegas Medical District.
| May 3, 2014
Health system capital planning for the future: The benefits of master plan portfolio analysis and ambulatory market modeling
Money continues to be scarce, yet U.S. health systems need to invest and re-invest in their physical future. Healthcare facilities planning experts from CBRE Healthcare outline tools and strategies for identifying where to best allocate precious resources.