At Boston University’s dental school, ‘under construction’ won’t mean ‘closed for business’

Contractors

At Boston University’s dental school, ‘under construction’ won’t mean ‘closed for business’

A major renovation and addition are scheduled to minimize operational disruption.


By John Caulfield, Senior Editor | April 26, 2018

Boston University's Goldman School of Dental Medicine will increase its clinical space by 60% through a renovation and addition that are being conducted while the school stays open and continues to offer its services to students and the community. Image: SmithGroupjjr

On April 5, Shawmut Design and Construction broke ground on a 41,900-sf expansion and 53,100-sf renovation of Boston University’s Goldman School of Dental Medicine.

The building team that includes Smith Group JJR (design architect, SE, MEP), Compass Project Management (project manager), and Haley Aldrich (geotech engineer), expects to be onsite for 32 months, during which the school—an active building with over 200 students, plus faculty, staff, and thousands of patients per year—will remain open.

This is a common challenge for rehab projects, complicated in this case by a tight urban site and a building with only a 13,000-sf floor plate—“a postage stamp,” says Shawmut’s Vice President Kevin Sullivan—the building team has to work within.

To keep the school open during work, Sullivan says his firm started by “overcommunicating” with shareholders who included the school’s dean, and its directors of facilities and operations.

The Building Team came up with a multi-phase schedule that will work on the basement, first floor, and part of the second floor first; the two additions next; and then renovate the upper floors. Sullivan explains that this schedule allows for floors and utilities to be isolated, which will sometimes require installing temporary systems to avoid operational disruptions. It will also minimize the need to move students and patients around.

A link to download a virtual reality walkthrough video of this project, posted by Shawmut, can be accessed here.

A rendering of an operatory inside Boston University's renovated and expanded dental school. Image: SmithGroupjjr

 

The isolations will also allow the team to minimize vibration on occupants caused by drilling into concrete to install new façade that lets in more light into the building and blends in with the facades of other buildings in the neighborhood. Because of the tight site space, the Building Team had to close two traffic lanes and move a bus stop.

The expansion will include office, instructional, clinical, and student collaborative spaces on seven existing levels, plus support spaces and a new 140-seat auditorium on the first floor.

The renovation will reconfigure the layout of the patient and student/faculty entry, as well as its clinical, classroom, and student spaces.

All told, the project will increase clinical space by more than 60%, make treatment areas more comfortable and flexible, and provide a student and resident lounge, a café, and collaborative study area on the first floor. With the addition, the school’s floor plate will increase to 18,000 sf.  

The project’s completion data is slated for December 2020.

Related Stories

Building Team | Jul 18, 2022

Understanding the growing design-build market

FMI’s new analysis of the design-build market forecast for the next fives years shows that this delivery method will continue to grow, despite challenges from the COVID-19 pandemic.

Mixed-Use | Jul 18, 2022

Mixed-use development outside Prague uses a material made from leftover bricks

Outside Prague, the Sugar Factory, a mixed-used residential development with public space, marks the largest project to use the sustainable material Rebetong. 

Building Team | Jul 15, 2022

ABC: Construction materials prices increased in June, up 20% from a year ago

Construction input prices increased 1.9% in June compared to the previous month, according to an Associated Builders and Contractors analysis of U.S. Bureau of Labor Statistics’ Producer Price Index data released today.

Arenas | Jul 15, 2022

U. of Oregon renovation aims for ‘finest track and field facility in the world’

The renovation of the University of Oregon’s Hayward Field had the goal of creating the “finest track and field facility in the world.”

Building Team | Jul 14, 2022

ABC’s construction backlog inches lower in June; Contractor confidence falters

Associated Builders and Contractors reports today that its Construction Backlog Indicator fell 0.1 months in June and stands at 8.9 months, according to an ABC member survey conducted June 21 to July 5.

Sustainable Development | Jul 14, 2022

Designing for climate change and inclusion, with CBT Architects' Kishore Varanasi and Devanshi Purohit

Climate change is having a dramatic impact on urban design, in terms of planning, materials, occupant use, location, and the long-term effect of buildings on the environment. Joining BD+C's John Caulfield to discuss this topic are two experts from the Boston-based CBT Architects: Kishore Varanasi, a Principal and director of urban design; and Devanshi Purohit, an Associate Principal.

Multifamily Housing | Jul 14, 2022

Multifamily rents rise again in June, Yardi Matrix reports

Average U.S. multifamily rents rose another $19 in June to edge over $1,700 for the first time ever, according to the latest Yardi® Matrix Multifamily Report.

Building Team | Jul 14, 2022

Austin PBS gets a new state-of-the-art facility with three studios

Since the 1970s, Austin PBS, birthplace of the Austin City Limits TV series, has been based inside the communications building on the University of Texas campus—a space it has long outgrown.

Building Team | Jul 13, 2022

The YIMBY movement emerges as valuable advocate for affordable housing

Over the past few decades, developers grew accustomed to nothing but staunch opposition to dense affordable housing project proposals.

Energy | Jul 13, 2022

Electrification of buildings, new and old, furthers environmental responsibility and equity

 It’s almost a cliché in our industry, but nonetheless: The greenest building is the one that is already built. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021