Is it a cylinder or a cube? When speaking about the Faena Forum, the most prominent building of the Faena Arts Center site, the answer to that question changes depending on what angle one views the building from.
The 43,000-sf forum is divided into two volumes: the cylinder houses performance and gathering spaces; the cube accommodates flexible meeting areas. On the third floor, an Assembly Hall occupies both the cube and the cylinder and links the two spaces.
Melding a cylinder and a cube into one aesthetically pleasing design wasn’t the most difficult aspect of the Faena Arts Center project. That honor was reserved for the construction of the 22-foot-deep underground parking garage that sits just a hop, skip, and jump from the ocean and three feet above the groundwater table.
To build the underground parking garage, the project team received permission to temporarily vacate a public street so that it could perform the excavation and then return an elevated street to the city. A combination of steel sheet piles and an unreinforced concrete tremie slab were used to create a “bathtub” that allowed the contractor to work in the dry. A 16-inch-thick hydrostatic slab and basement walls were then cast directly against the steel sheet piles and concrete tremie.
The final element of the center, the Bazaar, took the historic Atlantic Beach Hotel and preserved and restored the existing lobby and façades, while reprogramming the building for retail.
Faena Forum’s cylinder and square motif (top) define the building’s functions. Photo courtesy Bruce Damonte.
Building Team – Submitting firm, Structural engineer DeSimone Consulting Engineers Architect OMA, Revuelta Architecture International Contractor Layton Construction
General Information – Size 288,000 sf Cost $150 million Construction time 2014 to 2016
Related Stories
Building Team Awards | Apr 9, 2015
IPD-driven fusion facility serves science and student life in Chicago
In dire need of modern science labs and a student union, North Park University built both—in the same building.
Building Team Awards | Apr 9, 2015
‘Prudent, not opulent’ sets the tone for this Catholic hospital
This Building Team stuck with a project for seven years to get a new hospital built for a faithful client.
Building Team Awards | Apr 9, 2015
9/11 museum triumphs over controversy
The Building Team for this highly visible project had much more than design, engineering, and construction problems to deal with.
Building Team Awards | Apr 7, 2015
Unique test facility will help make wind power more feasible
A new facility at Clemson University makes it possible to test the huge stresses that large-scale wind turbines must be able to withstand.
Building Team Awards | Apr 5, 2015
UK's leading foot and mouth disease lab turns containment design inside out
A daring Building Team breaks the bunker mentality common to research containment with this light-filled, open facility in the English countryside.
Building Team Awards | Apr 5, 2015
‘Project first’ philosophy shows team’s commitment to a true IPD on the San Carlos Center
Skanska and NBBJ join forces with Sutter Health on a medical center project where all three parties share the risk.