The new home for the L.A. Rams and L.A. Chargers will not be opening as soon as was originally intended. The 70,000-seat stadium was initially scheduled to be ready in time for the 2019 NFL season, but thanks to a surfeit of rain the opening will be delayed until the start of the 2020 season, the Los Angeles Times reports.
The rainfall in the area didn’t just reach record amounts, but it also occurred at the worst possible time during the HKS-design stadium’s construction: the excavation phase.
At times, the stadium’s excavation site was filled with as much as 10 to 12 feet of standing water, which needed to be drained before work could resume. This caused the project, which is being built by Turner Construction and AECOM, to screech to a halt for two months.
The two months can’t be made up over the next two years, thus getting the project back on schedule, due to an already ambitious construction timetable and the increased workload associated with creating a stadium that will house two separate teams, according to the LA Times.
Due to the delay, the Rams will continue to play in the Coliseum for the 2019 season while the Chargers will have to play their home games at the StubHub Center for an extra season. While the Coliseum has a seating capacity of around 93,000, the StubHub center only offers 27,000 seats, but this will be expanded to 30,000 for Chargers games.
The stadium will be the focal point of a mixed-use entertainment district that will include a 300-room hotel, retail and office space, and a 6,000-seat performance venue.
Related Stories
| May 16, 2013
Chicago unveils $1.1 billion plan for DePaul arena, Navy Pier upgrades
Hoping to send a loud message that Chicago is serious about luring tourism and entertainment spending, Mayor Rahm Emanuel has released details of two initiatives that have been developing for more than a year and that it says will mean $1.1 billion in investment in the McCormick Place and Navy Pier areas.
| May 7, 2013
First look: Golden State Warriors stadium by Snøhetta, AECOM
Architects Snøhetta and AECOM have revealed their latest renderings of a new stadium for NBA basketball team the Golden State Warriors on the waterfront in San Francisco.
| May 2, 2013
Holl-designed Campbell Sports Center completed at Columbia
Steven Holl Architects celebrates the completion of the Campbell Sports Center, Columbia University’s new training and teaching facility.
| Apr 30, 2013
Tips for designing with fire rated glass - AIA/CES course
Kate Steel of Steel Consulting Services offers tips and advice for choosing the correct code-compliant glazing product for every fire-rated application. This BD+C University class is worth 1.0 AIA LU/HSW.
| Apr 26, 2013
BIG tapped to design Europa City in suburban Paris
Danish architecture firm, BIG - led by Bjarke Ingels – has been announced as the winner of an international invited competition for the design of Europa City, a 800,000 square meter cultural, recreational and retail development in Triangle de Gonesse, France.
| Apr 24, 2013
Los Angeles may add cool roofs to its building code
Los Angeles Mayor Antonio Villaraigosa wants cool roofs added to the city’s building code. He is also asking the Department of Water and Power (LADWP) to create incentives that make it financially attractive for homeowners to install cool roofs.
| Apr 12, 2013
Chicago rail conversion puts local twist on High Line strategy
Plans are moving forward to convert an unused, century-old Chicago rail artery to a 2.7 mile, 13 acre recreational facility and transit corridor.
Building Enclosure Systems | Mar 13, 2013
5 novel architectural applications for metal mesh screen systems
From folding façades to colorful LED displays, these fantastical projects show off the architectural possibilities of wire mesh and perforated metal panel technology.
| Mar 5, 2013
Recycled recreation: Waste-to-energy plant combines with ski resort
A new project near Copenhagen pushes the boundaries of the term "mixed use," combining a waste-to-energy plant with a ski resort.