The new home for the L.A. Rams and L.A. Chargers will not be opening as soon as was originally intended. The 70,000-seat stadium was initially scheduled to be ready in time for the 2019 NFL season, but thanks to a surfeit of rain the opening will be delayed until the start of the 2020 season, the Los Angeles Times reports.
The rainfall in the area didn’t just reach record amounts, but it also occurred at the worst possible time during the HKS-design stadium’s construction: the excavation phase.
At times, the stadium’s excavation site was filled with as much as 10 to 12 feet of standing water, which needed to be drained before work could resume. This caused the project, which is being built by Turner Construction and AECOM, to screech to a halt for two months.
The two months can’t be made up over the next two years, thus getting the project back on schedule, due to an already ambitious construction timetable and the increased workload associated with creating a stadium that will house two separate teams, according to the LA Times.
Due to the delay, the Rams will continue to play in the Coliseum for the 2019 season while the Chargers will have to play their home games at the StubHub Center for an extra season. While the Coliseum has a seating capacity of around 93,000, the StubHub center only offers 27,000 seats, but this will be expanded to 30,000 for Chargers games.
The stadium will be the focal point of a mixed-use entertainment district that will include a 300-room hotel, retail and office space, and a 6,000-seat performance venue.
Related Stories
| Feb 22, 2013
Westlake Reed Leskosky will renovate training center for Cleveland Browns
Local firm Westlake Reed Leskosky has been chosen to design renovations to the Cleveland Browns' Training and Administrative Complex in Berea, Ohio.
| Feb 14, 2013
Brasfield & Gorrie breaks ground on New College Football Hall of Fame in Atlanta
General contractor Brasfield & Gorrie is scheduled to kick off construction on the new College Football Hall of Fame in downtown Atlanta. With an anticipated completion date of fall 2014, the $66.5 million project will continue the revitalization of the city’s tourist district.
| Feb 6, 2013
George W. Bush Presidential Center among award-winning roofing projects honored by Sika Sarnafil
Winners of the 2012 Contractor Project of the Year Competition were announced this week by Sika Sarnafil. The annual competition highlights excellence in roofing installation. Roofing contractors are judged based on project complexity, design uniqueness, craftsmanship, and creative problem solving.
| Dec 5, 2012
McIntyre appointed Business Development Director for Shawmut’s Sports Venue Group
McIntyre will be tasked with expanding existing client relationships and creating new partnerships.
| Dec 4, 2012
Wagner joins Ghafari as Manager of Structural Engineering
Wagner comes to Ghafari from Walter P Moore, where he served as a principal, chaired the construction administration task force and led the design of numerous projects ranging in size from $10 million to $70 million.
| Sep 24, 2012
$3.8-million athletic field and track opens in Glen Head, N.Y.
The complex also includes a new, one-story, multi-purpose building that serves as the main entry port to the athletic facilities.
| Sep 7, 2012
Duffy joins Thornton Tomasetti
At Hardesty & Hanover, Duffy partnered with Thornton Tomasetti on a number of projects.
| Aug 24, 2012
Meis heads to Woods Bagot Sport
Staples Center, Paul Brown Stadium architect to leverage global studio to serve clients worldwide.
| Aug 8, 2012
Giants 300 Sports Facilities Report
BD+C's Giants 300 Top 25 AEC Firms in the Sports Facilities sector.