Calif.-based Bomel Construction Co. recently completed the structural concrete phase of the largest construction project ever undertaken at San Diego International Airport.
The $1 billion expansion, called Green Build, consists of a 430,000-sf. terminal building with 10 gates on the west side of Terminal 2 West, a dual-level roadway separating arriving and departing passengers, additional security lanes and an expanded concession area. The design-build project will be completed in the first quarter of 2013, with the new terminal opening soon thereafter.
Green Build, which includes a number of energy-saving and environmentally sensitive measures, is being built to achieve LEED Silver certification from the USGBC.
Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.
Construction of the baggage-handling tunnel, which preceded construction of the terminal building above it, was completed in January 2011.
The metal decks and incline column phases of the project were completed in October 2011, while the slab-on-grade for the new building was finished in January 2012. Bomel employed between 25 and 30 workers during the duration of the project.
By the time it’s completed next year, Green Build will have employed between 2,500 and 3,000 construction workers. +
Related Stories
| Aug 11, 2010
Jacobs, HDR top BD+C's ranking of the nation's 100 largest institutional building design firms
A ranking of the Top 100 Institutional Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants
| Aug 11, 2010
Earthquake engineering keeps airport grounded
Istanbul, Turkey's new 2.15 million-sf Sabiha Gökçen International Airport opened on October 31, 2009, becoming the world's largest seismically isolated building. Arup's global airport planning and engineering team, in collaboration with architects Dogan Tekeli Sami Sisa Mimarlik Ofisi and contractor LIMAK-GMR JV, working within an 18-month timeline, designed and built the facility wi...