The Journal of Engineering and Construction Management recently published a study that found the design-build delivery method in construction contracting results in a majority of on-time projects, but half of projects using that method run over budget.
The study said that the perception of design-build’s cost savings advantage was uncertain. Researchers in China and Australia studied 418 projects in the Design-Build Institute of America database and found that although half of them resulted in cost overruns, and 75% were completed on time or ahead of schedule.
The Design-Build Institute of America responded to the study results and asserted that the researchers are off the mark, saying that they did not account for possible additional costs resulting from owner-initiated scope changes.
Related Stories
| Jan 7, 2013
Jerry Yudelson's issues his "Top 10 Green Building Megatrends" for 2013
Yudelson, a Contributing Editor to Building Design+Construction, says, “It looks like a good year ahead for the green building industry. Based on our experience, it seems clear that green building will continue its rapid expansion globally in 2013 in spite of the ongoing economic slowdown in most countries of Europe and North America. More people are building green each year, with 50,000 LEED projects underway by the latest counts; there is nothing on the horizon that will stop this Mega-trend or its constituent elements.”
| Dec 15, 2012
SAIC makes ready to lay off 700
SAIC, McLean, Va. (2011 construction revenues: $185,390,000), said it plans to cut its workforce by 700 employees in order to remain competitive in the federal market.