flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Digital tools accelerated the design and renovation of one contractor’s new office building

BIM and Information Technology

Digital tools accelerated the design and renovation of one contractor’s new office building

One shortcut: sending shop drawings created from laser scans directly to a wood panel fabricator.


By John Caulfied, Senior Editor | March 28, 2017

Photo courtesy of Heywood Chan Photography

Portland, Ore.-based Hoffman Construction is a national contractor that prides itself on using digital tools to complete its projects.

So, in mid 2015, when it was planning to renovate a 10,000-sf office space in Seattle, Hoffman challenged its interior designer, Gensler, to take a similar approach that would highlight Hoffman’s digital integration and technical delivery techniques.

With the help of a host of digital products—including SketchUp, Revit, Faro, Navisworks, Cyclone, AutoCAD and CNC—the Building Team designed the space in just four weeks and helped the client build it in seven.

“Hoffman is always looking to do the impossible in a possible amount of time. Gensler saw us as innovators showcasing our talents with this project,” says Kevin Ryan, operations manager and GM for Hoffman Construction in Seattle.

The focal point was the Think Tank, a 2,000-sf space that would serve as the office’s central hub. That space, according to Jeroen Teeuw, Senior Associate at Gensler who was Lead Designer on this design-build project, is clad in over 100 unique panels that were fabricated from shop drawings produced by digital scans. Fuller Cabinets in Eugene, Ore., supplied the panels, which were fabricated by Straight-Up Carpentry in Oregon.

 

Photo courtesy of Heywood Chan Photography.

 

Teeuw says that, before this job, Gensler had only rarely employed digital scanning for interior projects. The scans, he says, were accurate to the point where no tweaks to the design were necessary. “Hoffman had a lot of trust in us,” he says.

Demolition started on Sept. 1, 2015, and included four weeks of asbestos mitigation. Building started the first week October. Hoffman wanted to occupy the building by Christmas, “so we had to identified what absolutely needed to be done in order to satisfy the fire marshals and inspectors,” recalls Ryan. The Building Team stripped the floors, knocked down walls, and installed new T-bar ceilings.

For the renovation, the Building Team broke up the shop drawings into several packages, which Ryan says all but eliminated material waste.

Hoffman achieved its goal, even though the office wasn’t fully completed until April 2016. The space includes conference rooms and private offices, a central teaming area, pantry/lounge/kitchen, open workspace, facilities space, and a reception area.

Related Stories

BIM and Information Technology | Mar 10, 2017

'Reality modeling' arrives

Advanced reality capture technologies are breaking down the barriers between the job site and project models.

BIM and Information Technology | Feb 6, 2017

BIM for O+M: Less about the model, more about the data

How one Building Team is giving a university client what its facilities staff really wants from BIM: information, please.

Codes and Standards | Jan 13, 2017

New BIM guide for owners released

National Institute of Building Sciences releases a manual for developing standard set of BIM documents.

Designers | Jan 13, 2017

The mind’s eye: Five thoughts on cognitive neuroscience and designing spaces

Measuring how the human mind responds to buildings could improve design.

Architects | Oct 11, 2016

A good imagination and a pile of junk: How maker culture is influencing the way AEC firms solve problems

“Fail” is no longer a dirty four-letter word: for maker culture, it has become a crucial stop along the way

Building Technology | Oct 7, 2016

How much is that LEED point worth? A new tool provides answers

Autocase analyzes the financial, social, and environmental benefits of certification.

Sponsored | BIM and Information Technology | Oct 3, 2016

A laser scanning solution for challenging topographic surveys

DeWalt Corporation, which has completed thousands of surveys over the last 50 years, began using 3D laser scanning technology nearly five years ago. 

BIM and Information Technology | Sep 15, 2016

8 tips for perfecting co-location

Experts share tips and tricks for maximizing cross-team collaboration.

BIM and Information Technology | Sep 7, 2016

Energy Star Portfolio Manager tool updated to factor in waste management

The costs and benefits of managing 29 types of waste are now included.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021