flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Digital tools accelerated the design and renovation of one contractor’s new office building

BIM and Information Technology

Digital tools accelerated the design and renovation of one contractor’s new office building

One shortcut: sending shop drawings created from laser scans directly to a wood panel fabricator.


By John Caulfied, Senior Editor | March 28, 2017

Photo courtesy of Heywood Chan Photography

Portland, Ore.-based Hoffman Construction is a national contractor that prides itself on using digital tools to complete its projects.

So, in mid 2015, when it was planning to renovate a 10,000-sf office space in Seattle, Hoffman challenged its interior designer, Gensler, to take a similar approach that would highlight Hoffman’s digital integration and technical delivery techniques.

With the help of a host of digital products—including SketchUp, Revit, Faro, Navisworks, Cyclone, AutoCAD and CNC—the Building Team designed the space in just four weeks and helped the client build it in seven.

“Hoffman is always looking to do the impossible in a possible amount of time. Gensler saw us as innovators showcasing our talents with this project,” says Kevin Ryan, operations manager and GM for Hoffman Construction in Seattle.

The focal point was the Think Tank, a 2,000-sf space that would serve as the office’s central hub. That space, according to Jeroen Teeuw, Senior Associate at Gensler who was Lead Designer on this design-build project, is clad in over 100 unique panels that were fabricated from shop drawings produced by digital scans. Fuller Cabinets in Eugene, Ore., supplied the panels, which were fabricated by Straight-Up Carpentry in Oregon.

 

Photo courtesy of Heywood Chan Photography.

 

Teeuw says that, before this job, Gensler had only rarely employed digital scanning for interior projects. The scans, he says, were accurate to the point where no tweaks to the design were necessary. “Hoffman had a lot of trust in us,” he says.

Demolition started on Sept. 1, 2015, and included four weeks of asbestos mitigation. Building started the first week October. Hoffman wanted to occupy the building by Christmas, “so we had to identified what absolutely needed to be done in order to satisfy the fire marshals and inspectors,” recalls Ryan. The Building Team stripped the floors, knocked down walls, and installed new T-bar ceilings.

For the renovation, the Building Team broke up the shop drawings into several packages, which Ryan says all but eliminated material waste.

Hoffman achieved its goal, even though the office wasn’t fully completed until April 2016. The space includes conference rooms and private offices, a central teaming area, pantry/lounge/kitchen, open workspace, facilities space, and a reception area.

Related Stories

Sponsored | BIM and Information Technology | Dec 17, 2015

How is the Value of VDC for Design Management Translating Outside the US?

Sascha Vesterlund, a VDC Specialist, Design Processer with MT Højgaard, and Nathan Wood, Innovation at DPR Construction, shared their perspectives on VDC

BIM and Information Technology | Dec 3, 2015

New app visualizes cellular and Wi-Fi signals in an area

Using data collected from millions of cell towers and Wi-Fi routers, the app makes the invisible visible.

BIM and Information Technology | Nov 30, 2015

Light-based wireless technology is 100 times faster than Wi-Fi

Li-Fi, which reaches speeds of 224 gigabits per second, is being tested in Estonia.

Sponsored | BIM and Information Technology | Nov 25, 2015

Contractor leverages dynamic site logistic plan as BIM deliverable

I recently sat down with two Architects-Turned-VDC-Process-Managers to discuss the ways in which they are leveraging technology to bring the value of BIM downstream

BIM and Information Technology | Nov 24, 2015

Solving the data conundrum with better tools to capture, share, and analyze information

At a recent Thornton Tomasetti symposium, experts showed how designs and projects can be improved by granular information that’s accessible to more users. 

Modular Building | Nov 19, 2015

AECOM and Project Frog form partnership for building modular data centers

The Rapid Deployment Team will provide solutions for data centers both small (1 MW) and large (50+ MW).

BIM and Information Technology | Nov 18, 2015

AIA: Energy modeling key to reaching carbon neutrality in buildings

Energy modeling allows architects to be more ambitious with energy-saving in their design projects.

Green | Nov 17, 2015

DOE launches new data collaborative to help cities and states boost building efficiency

The SEED Standard will help manage, standardize, share performance data.

Sponsored | BIM and Information Technology | Nov 12, 2015

Is the PDF revolution advancing BIM workflows?

Many project teams who struggle to get everyone up to speed with BIM, find PDFs a useful tool to bridge the gap between the BIM world and the paper world

BIM and Information Technology | Nov 3, 2015

How virtual and augmented reality can shape architecture and design

Gensler's Alan Robles examines a few ways VR and AR could create value for architecture and design professionals.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021