After a decade and a half of downturn, Chicago envisions a new boom period for its South Loop convention center district. The Metropolitan Pier and Exposition Authority, known as McPier, is revamping McCormick Place, adding a hotel and arena through a $650 million McCormick Place Event Center expansion project.
Gensler designed the hotel, the 1,200-room, $450 million Marriott Marquis. The arena, designed by Pelli Clarke Pelli, is a basketball venue for DePaul, the city’s Division-I college hoops team. McPier funded a study that says the new buildings could generate $250 million in spending per year.
That figure, though, is fairly optimistic. The Chicago Tribune reports that experts are doubting the project, saying that the investments will ultimately cost taxpayers.
The McPier study has a few faulty assumptions. One, it is based on DePaul averaging nearly 10,000 fans a game, almost triple its current attendance. Two, McPier plans on using the arena for conventions, but studies have said that arenas are poor hosts for conventions due to their fixed seating. If the arena struggles to make money either in terms of basketball or conventions, then the hotel will have to make up that difference.
Stadiums have been found to be unsuccessful drivers of economic growth, which is an issue because McPier has already borrowed hundreds of millions of dollars and maxed out its debt limit.
"It was a dumb idea when it was proposed, it was a dumb idea when they approved it, and it will be a dumb idea in the future," Marc Ganis, a Chicago consultant who specializes in sports, said in the Tribune piece.
The Tribune has much more detail on the project, which is set to open in 2017.
Several issues have arisen with concerning the development over the last few years, including eminent domain battles, rising construction costs, and disagreements over $55 million in tax increment financing (TIF) funds.
Related Stories
| Mar 1, 2012
Cornell shortlists six architectural firms for first building on tech campus
Each of the firms will be asked to assemble a team of consultants and prepare for an interview to discuss their team’s capabilities to successfully design the university’s project.
| Mar 1, 2012
Bomel completes design-build parking complex at U.C. San Diego
The $24-million facility, which fits into a canyon setting on the university’s East Campus, includes 1,200 stalls in two adjoining garages and a soccer field on a top level.
| Feb 6, 2012
FMI releases 2012 Construction Productivity Report
Downsizing has resulted in retaining the most experienced and best-trained personnel who are the most capable of working more efficiently and harder.
| Feb 2, 2012
Shawmut Design and Construction launches sports venues division
Expansion caps year of growth for Shawmut.
| Jan 24, 2012
U of M installs new lighting at Crisler Player Development Center
Energy efficient lighting installed at PDC reduce costs and improves player performance.
| Jan 3, 2012
The Value of Historic Paint Investigations
An expert conservator provides a three-step approach to determining a historic building’s “period of significance”—and how to restore its painted surfaces to the correct patterns and colors.
| Dec 27, 2011
Nova completes $60M Clearwater Conference Center
Comprising an entire city block, the 450,000 sq. ft. facility features over 400 meeting rooms, six theaters, a full-service health spa, complete with an indoor running track, and a commercial kitchen that can efficiently accommodate over 1,000 diners
| Dec 27, 2011
BD+C's Under 40 Leadership Summit update
The two-day Under 40 Leadership Summit continued with a Leadership Style interactive presentation; Great Solutions presentations from Under 40 attendees; the Owner’s Perspective panel discussion; and the Blue Ocean Strategy presentation.
| Dec 14, 2011
Tyler Junior College and Sika Sarnafil team up to save energy
Tyler Junior College wanted a roofing system that wouldn’t need any attention for a long time.
| Dec 5, 2011
Summit Design+Build begins renovation of Chicago’s Esquire Theatre
The 33,000 square foot building will undergo an extensive structural remodel and core & shell build-out changing the building’s use from a movie theater to a high-end retail center.