It took 11 years and creative financing through a public-private partnership to resurrect UC Berkeley’s Bowles Hall, the nation’s first residential college. Built in 1928 and listed on the National Register of Historic Places, the Gothic-style building became too expensive to maintain and fell into disrepair over the years.
This project involved the renovation and restoration of the 57,000-sf hall, and the construction of a 4,200-sf addition. The Reconstruction Awards judges noted the project team’s meticulous work in revitalizing the historic structure, including the manual removal and reinstallation of 20,000 historic clay roof tiles (most of them mortared directly onto the roof); the construction of concrete walls, concrete mat foundations, and a buttress to strengthen the building against earthquakes; and the reconfiguration of the layout of the dorms to accommodate modern living needs, with Wi-Fi, central heating, and en suite baths. The team also cleverly converted underutilized attic space into the dean’s apartment.
Project Summary
Honorable Mention
Building Team: Clark Construction Group (submitting firm, GC) Bowles Hall Foundation (owner) EdR (developer) Pyatok (architect) Maffei Structural Engineering (SE) ACCO Engineered Systems (ME) Royal Electric Co. (EE) Pan-Pacific (PE).
Details: 61,200 sf. Total cost: $27.1 million. Construction time: June 2015 to August 2016. Delivery method: CM at risk.
SEE ALL OF THE 2017 RECONSTRUCTION AWARD WINNERS HERE
Related Stories
Reconstruction Awards | Nov 11, 2016
Exclusive Chicago club re-emerges as a boutique hotel
Built in 1893 for the World’s Columbian Exposition, the CAA was an exclusive social club founded by leading figures in American sports and commerce.
Reconstruction Awards | Dec 1, 2015
Massive Chicago parking garage gets overdue waterproofing
Millennium Lakeside Garage, the largest underground parking facility in the U.S., hadn’t been waterproofed since the 1970s. The massive project took nearly 2½ years and 33,554 man-hours.
Reconstruction Awards | Nov 30, 2015
Washington Monument restored after 2011 East Coast earthquake
This restoration and repair project, which was completed under budget and eight days early (despite several setbacks), involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs. Construction took place from November 2011 to May 2014.
Reconstruction Awards | Nov 30, 2015
Denver's 107-year-old seminary campus modernized
The scope of the project included the seminary dorms, library, and chapel, all of which posed their own set of obstacles.
Reconstruction Awards | Nov 24, 2015
Center of I.M. Pei-designed plaza part of Washington redevelopment
The L’Enfant Plaza, a three-story below-grade mall, was renovated to include a new glass atrium pavilion and a 40-foot-long, interactive LED.
Reconstruction Awards | Nov 24, 2015
Manhattan's first freestanding emergency department a result of adaptive reuse
The Lenox Hill Healthplex, a restoration of the Curran O’Toole Building, has glass-block walls and a carefully preserved exterior.
Reconstruction Awards | Nov 19, 2015
Nave restored at Yale’s Sterling Memorial Library
Turner Construction and Helpern Architects revived the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.
Reconstruction Awards | Nov 19, 2015
Infinite Chicago redevelopment bridges past to present
The renovation of three historic downtown buildings—the Gibbons and Steger Buildings and Pickwick Stables—includes a multi-level concrete walkway connection.
Reconstruction Awards | Nov 18, 2015
Sun Theater serves the youth of St. Louis
Lawrence Group and property owner TLG Beaux Arts raised $11 million to restore the 26,000-sf theater into a modern performance venue.
Reconstruction Awards | Nov 17, 2015
Smithsonian Institution’s Arts and Industries Building again an exposition and museum space
After removing decades’ worth of unfortunate additions to expose 17 historic interior spaces for the National Historic Landmark, the Building Team zoned in on the client’s key concern.