Griffin Electric completes electrical work at Cary Arts Center

Griffin Electric completes electrical work at Cary Arts Center


By By BD+C Staff | November 14, 2011
Griffin Electric Cary Arts Center fire pump chiller handler elevators
The Griffin Electric team was responsible for replacing the previous electrical service on-site with a 1000A, 480/277V service a

Wayne J. Griffin Electric, Inc. (Griffin Electric) has recently completed the electrical installation work at the new Cary Arts Center, located in Cary, NC. 

Opened this spring, the former Cary Elementary/High School is the site of this new arts center, encompassing 48,000-sf.  A complete renovation of the former learning institution, the updated building includes rooms for classes, studio, rehearsal and performance, plus office space for visual arts, ceramic arts, and performing arts. 

A spacious lobby welcomes visitors and patrons, with an adjacent gallery space.  Also on the main floor is a concession area and 399-seat theater, in addition to three classrooms, which may also be used for lobby overflow. Furthermore, this level has the addition of a fly tower, which allows for theater sets to be built and stored on-site. The lower level of the building includes classrooms for ceramics, wood and fabric shops. The upper level, comprised of five classrooms, also includes rehearsal and conference rooms.

The Griffin Electric team was responsible for replacing the previous electrical service on-site with a 1000A, 480/277V service and providing electrical feeds for a new fire pump chiller, six air-handlers and two elevators.

Additionally, the team installed several new systems including, fire alarm, security and public address, lighting control and lightning protection.  A new state-of-the-art performance lighting system was furnished for the theater and rehearsal rooms, in addition to three new dimmer racks and smart switches within the main control room for the performance lighting system. BD+C

Related Stories

| Jan 14, 2016

How to succeed with EIFS: exterior insulation and finish systems

This AIA CES Discovery course discusses the six elements of an EIFS wall assembly; common EIFS failures and how to prevent them; and EIFS and sustainability.

Market Data | Jan 13, 2016

Morgan Stanley bucks gloom and doom, thinks U.S. economy has legs through 2020

Strong job growth and dwindling consumer debt give rise to hope.

Architects | Jan 13, 2016

‘Socially engaged’ architect Alejandro Aravena named 2016 Pritzker Architecture Prize Laureate

Known for his inventive social housing initiatives in his native Chile, Aravena epitomizes the revival of a more socially engaged architect, the Pritzker jury stated.

Architects | Jan 12, 2016

Dear Architecture: It's time to create a level field for female designers

If architecture took one moment to be introspective, it would discover appalling imbalances between the opportunities for women and men, as Perkins+Will's Vershaé Hite and Brittany Eaker-Kirkland wrote in an open letter.

Great Solutions | Jan 6, 2016

Shepley Bulfinch develops elegant design solution to address behavioral issues in emergency departments

ED scheme allows staff to isolate unruly patients and visitors in a secure area.

Market Data | Jan 5, 2016

Majority of AEC firms saw growth in 2015, remain optimistic for 2016: BD+C survey

By all indications, 2015 was another solid year for U.S. architecture, engineering, and construction firms.

Architects | Jan 5, 2016

Potential vs. credential: How men and women differ in career progress

Recent research suggests that women face yet another career impediment: the confidence gap.

Architects | Dec 17, 2015

Capturing utilization and activity data in the workplace

While utilization is an important metric to inform how frequently a space is used, it’s important to consider activity data.

Architects | Dec 17, 2015

Four winners named in NYC sidewalk shed competition

Firms in the Construction Shed Design Competition made designs that are simple to build and use readily-available materials.

Architects | Dec 16, 2015

Lohan Anderson to close, join Wight & Co.

Dirk Lohan, Floyd Anderson and eight others will be hired by the Illinois-based Wight & Co. next month.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021